Dominion 230 kV Reinforcements (2024-W1-24)
2024-W1-24 - Dominion Reinforcements. Presented by PJM in PJM planning materials (Dominion zone, VA (South Hill, Virginia, for the Raines - Cloud line)).
Profile
This is a package of Dominion zone upgrades, not a single line: proposal 2024-W1-24, listed in PJM's 2024 Window 1 portfolios as Dominion Reinforcements, which PJM presented to its Transmission Expansion Advisory Committee on January 7, 2025 as a recommended solution at $672.43 million, with a projected in-service date of June 1, 2029. (p. 74, p. 1, p. 67, p. 68) It combines about a dozen 230kV pieces: rebuilds or reconductors of existing lines such as Marsh Run - Remington CT, Gainesville - Wheeler, Thelma - Lakeview, Chesterfield - Tyler - Locks - Poe and Carson - Poe, new lines such as Nokesville - Hornbaker, Elmont - Ladysmith, Cloverhill - Ox, Raines - Cloud and Morrisville - Anderson Branch, and a 115kV-to-230kV conversion between Poe and a new Prince George substation. (p. 67, p. 69, p. 68) The largest cost in PJM's January 2025 table is the new 24.5-mile Cloverhill - Ox line, at $287.54 million, followed by the Raines - Cloud line at $77.50 million. (p. 69, p. 1) The only reason printed for a single component is for Raines - Cloud: electrical violations caused by significant load growth in South Hill, Virginia. (p. 69) The package total was the same $672.43 million on the preferred-solution slide and in the recommendation. (p. 81, p. 68) Later changes are piecemeal: in May 2026 the Anderson Branch terminal work (b4000.339, $0.95 million) was listed under cancellations in PJM's Yeat substation update, and in October 2026 the Nokesville line was re-terminated at Bristow, next to Hornbaker, at $18.14 million with no additional cost and no change to its June 1, 2029 date. (p. 20, p. 11, p. 1, p. 1)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Marsh Run - Remington CT 230kV lines #280 and #299 | Rebuild, with terminal equipment upgrades at Marsh Run and Remington | p. 67 |
| Gainesville - Wheeler 230kV line #2161 | Partial reconductor / partial wreck and rebuild, terminal upgrades at Gainesville and Wheeler, relay resets at Trident | p. 67 |
| Thelma - Lakeview 230kV lines #213 and #225 | Rebuild; new conductor summer rating 1573 MVA | p. 69 |
| Chesterfield - Tyler - Locks - Poe 230kV line #2003 | Reconductor, terminal upgrades at Poe and Tyler, relay resets at Chesterfield | p. 67 |
| Carson - Poe 230kV line #2002 | Reconductor; new conductor summer rating 1573 MVA; $30.29M | p. 69 |
| Nokesville - Hornbaker (later Bristow) 230kV line | New line on the vacant arms of existing double circuit monopole structures, terminal upgrades at both ends | p. 67 |
| Elmont - Ladysmith 230kV line | New 26.38-mile line on the existing 5-2 structures between the two stations | p. 69 |
| Cloverhill - Ox 230kV line | New 24.5-mile line; the cost column beside it prints $287.54M (layout text also shows the neighboring row ID b4000.307) | p. 69 |
| Raines - Cloud 230kV line | New single circuit line plus an idle 230kV circuit between the stations; $77.50M | p. 69 |
| Poe - Prince George 115kV line #121 | Reconductor and convert to 230kV, terminal upgrades at Poe and Prince George | p. 68 |
| Prince George 230-115kV substation | New substation along the existing 115 or 230kV corridor | p. 69 |
| Morrisville - Anderson Branch 230kV line #9491 | New line on existing towers of 500kV line #545 Bristers - Morrisville, terminal upgrades at Morrisville and Anderson Branch | p. 68 |
Details as printed
| Portfolio list, October 2024 | Listed in a Window 1 portfolio beside 2024-W1-708, 2024-W1-551, 2024-W1-81 and 2024-W1-781; both 2024-W1-24 and 2024-W1-781 are labeled Dominion Reinforcements | p. 74 |
|---|---|---|
| Preferred solution, December 2024 | Preferred solution estimate $672.43 M, projected in service 6/1/2029 | p. 81 |
| Printed reason, Raines - Cloud | New Raines - Cloud line to solve electrical violations caused by significant load growth in South Hill, Virginia | p. 69 |
| Scope change, October 2026 | Nokesville - Hornbaker line re-terminated at Bristow, which will be located directly adjacent to Hornbaker; $18.14M, no additional cost, 6/1/2029 in service, no change | p. 11 |
| Nokesville - Hornbaker, original solution | $15.28M line (b4000.322) plus $2.86M terminal upgrades (b4000.323 and b4000.324); $18.14M total, previously presented 1/7/2025 | p. 10 |
| Cancellation, May 2026 | Anderson Branch terminal equipment (b4000.339, $0.95M) listed under Cancellations on PJM's Yeat substation scope-change slide | p. 20 |
| Later reference: Nebula customer delivery | Dominion's Nebula customer delivery loops the future Cloud - Raines line, which it describes as selected in the PJM 2024 Window 1 and assigned baseline numbers b4000.331, 332 and 333 | p. 12 |
| Later reference: James Hill delivery | Dominion's James Hill delivery cites the Poe six-breaker 230kV ring bus project (b4000.334-.336) as leaving no room for further line terminals at Poe | p. 6 |
| Meeting, Yeat update | PJM Reliability Analysis Update, TEAC May 8, 2026 | p. 1 |
| Meeting, Nokesville scope change | PJM Reliability Analysis Update, TEAC October 6, 2026 | p. 1 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 3, 2024 | Item 11 - Reliability Analysis Update PDF | 2024W1 – Regional Cluster Preferred Solution: 2024-W1-24 | $672.43 M | 6/1/2029 | |
| January 7, 2025 | Item 12 - Reliability Analysis Update PDF | Recommended Solution: 2024-W1-24 | $672.43 M | 6/1/2029 | |
| October 6, 2026 | Item 16 - Reliability Analysis Update - Presentation PDF | Nokesville – Hornbaker Bristow New 230kV Line | $18.14M | 6/1/2029 |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Bristow (DOM): described as new
- Hornbaker (DOM): described as new
- Prince George (PJM system-wide): described as new
- Anderson (PJM system-wide)
- Anderson Branch (PJM system-wide)
- Carson (PJM system-wide)
- Chesterfield (PJM system-wide)
- Cloud (PJM system-wide)
- Cloverhill (PJM system-wide)
- Elmont (PJM system-wide)
- Gainesville (PJM system-wide)
- Hornbaker (PJM system-wide)
- Ladysmith (PJM system-wide): expansion described
- Lakeview (PJM system-wide)
- Locks (PJM system-wide)
- Marsh Run (PJM system-wide)
- Morrisville (PJM system-wide)
- Nokesville (DOM): expansion described
- Nokesville (PJM system-wide)
- Poe (PJM system-wide)
- Raines (PJM system-wide)
- Remington CT (PJM system-wide)
- Remington Sub (PJM system-wide)
- Thelma (PJM system-wide)
- Trident (PJM system-wide)
- Tyler (PJM system-wide)
- Wheeler (PJM system-wide)
Not printed
- No program name beyond the proposal number and "Dominion Reinforcements" is printed; the slides do not print the proposing entity in a separate field. The Dominion attribution rests on that portfolio label and the Dominion Transmission Zone heading on the October 2026 slide.
- No problem statement or flowgate list for 2024-W1-24 is printed on the archived pages; only the Raines - Cloud row states a reason. PJM's 2024 RTEP Window 1 reliability analysis report (March 2025) is not in the archive.
- No board approval date and no project status such as Engineering or Construction is printed for the package; no updated package total is printed after January 2025.
- No county is printed for any station; the only state printed is Virginia (South Hill, for Raines - Cloud).
- The January 2025 cost table prints two columns side by side, so the archived text interleaves rows; the per-ID costs used here sum to $672.42M against the printed $672.43M total.
- Rows not included as members: need:DOM-2024-0054 (Nebula 230kV customer delivery, a Dominion supplemental project that loops the new Cloud - Raines line), need:DOM-2024-0063-DNH (Devlin - Vint Hill circuit on structures built under b4000.304-.310), need:DOM-2024-0036 (James Hill delivery, which cites the Poe ring bus) and id:b4000.355 (Valley Link Yeat slides, which list the b4000.339 cancellation). Each references this package but is a separate project.
- No news coverage of 2024-W1-24 or its components was found; searches returned only Dominion project pages and PJM documents.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.