Dominion 230 kV Reinforcements (2024-W1-24)

2024-W1-24 - Dominion Reinforcements. Presented by PJM in PJM planning materials (Dominion zone, VA (South Hill, Virginia, for the Raines - Cloud line)).

$672.43Mcost estimate as printed p. 68
6/1/2029projected in service p. 68
Recommended Solutionstatus as printed p. 67

Profile

This is a package of Dominion zone upgrades, not a single line: proposal 2024-W1-24, listed in PJM's 2024 Window 1 portfolios as Dominion Reinforcements, which PJM presented to its Transmission Expansion Advisory Committee on January 7, 2025 as a recommended solution at $672.43 million, with a projected in-service date of June 1, 2029. (p. 74, p. 1, p. 67, p. 68) It combines about a dozen 230kV pieces: rebuilds or reconductors of existing lines such as Marsh Run - Remington CT, Gainesville - Wheeler, Thelma - Lakeview, Chesterfield - Tyler - Locks - Poe and Carson - Poe, new lines such as Nokesville - Hornbaker, Elmont - Ladysmith, Cloverhill - Ox, Raines - Cloud and Morrisville - Anderson Branch, and a 115kV-to-230kV conversion between Poe and a new Prince George substation. (p. 67, p. 69, p. 68) The largest cost in PJM's January 2025 table is the new 24.5-mile Cloverhill - Ox line, at $287.54 million, followed by the Raines - Cloud line at $77.50 million. (p. 69, p. 1) The only reason printed for a single component is for Raines - Cloud: electrical violations caused by significant load growth in South Hill, Virginia. (p. 69) The package total was the same $672.43 million on the preferred-solution slide and in the recommendation. (p. 81, p. 68) Later changes are piecemeal: in May 2026 the Anderson Branch terminal work (b4000.339, $0.95 million) was listed under cancellations in PJM's Yeat substation update, and in October 2026 the Nokesville line was re-terminated at Bristow, next to Hornbaker, at $18.14 million with no additional cost and no change to its June 1, 2029 date. (p. 20, p. 11, p. 1, p. 1)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Marsh Run - Remington CT 230kV lines #280 and #299Rebuild, with terminal equipment upgrades at Marsh Run and Remingtonp. 67
Gainesville - Wheeler 230kV line #2161Partial reconductor / partial wreck and rebuild, terminal upgrades at Gainesville and Wheeler, relay resets at Tridentp. 67
Thelma - Lakeview 230kV lines #213 and #225Rebuild; new conductor summer rating 1573 MVAp. 69
Chesterfield - Tyler - Locks - Poe 230kV line #2003Reconductor, terminal upgrades at Poe and Tyler, relay resets at Chesterfieldp. 67
Carson - Poe 230kV line #2002Reconductor; new conductor summer rating 1573 MVA; $30.29Mp. 69
Nokesville - Hornbaker (later Bristow) 230kV lineNew line on the vacant arms of existing double circuit monopole structures, terminal upgrades at both endsp. 67
Elmont - Ladysmith 230kV lineNew 26.38-mile line on the existing 5-2 structures between the two stationsp. 69
Cloverhill - Ox 230kV lineNew 24.5-mile line; the cost column beside it prints $287.54M (layout text also shows the neighboring row ID b4000.307)p. 69
Raines - Cloud 230kV lineNew single circuit line plus an idle 230kV circuit between the stations; $77.50Mp. 69
Poe - Prince George 115kV line #121Reconductor and convert to 230kV, terminal upgrades at Poe and Prince Georgep. 68
Prince George 230-115kV substationNew substation along the existing 115 or 230kV corridorp. 69
Morrisville - Anderson Branch 230kV line #9491New line on existing towers of 500kV line #545 Bristers - Morrisville, terminal upgrades at Morrisville and Anderson Branchp. 68

Details as printed

Portfolio list, October 2024Listed in a Window 1 portfolio beside 2024-W1-708, 2024-W1-551, 2024-W1-81 and 2024-W1-781; both 2024-W1-24 and 2024-W1-781 are labeled Dominion Reinforcementsp. 74
Preferred solution, December 2024Preferred solution estimate $672.43 M, projected in service 6/1/2029p. 81
Printed reason, Raines - CloudNew Raines - Cloud line to solve electrical violations caused by significant load growth in South Hill, Virginiap. 69
Scope change, October 2026Nokesville - Hornbaker line re-terminated at Bristow, which will be located directly adjacent to Hornbaker; $18.14M, no additional cost, 6/1/2029 in service, no changep. 11
Nokesville - Hornbaker, original solution$15.28M line (b4000.322) plus $2.86M terminal upgrades (b4000.323 and b4000.324); $18.14M total, previously presented 1/7/2025p. 10
Cancellation, May 2026Anderson Branch terminal equipment (b4000.339, $0.95M) listed under Cancellations on PJM's Yeat substation scope-change slidep. 20
Later reference: Nebula customer deliveryDominion's Nebula customer delivery loops the future Cloud - Raines line, which it describes as selected in the PJM 2024 Window 1 and assigned baseline numbers b4000.331, 332 and 333p. 12
Later reference: James Hill deliveryDominion's James Hill delivery cites the Poe six-breaker 230kV ring bus project (b4000.334-.336) as leaving no room for further line terminals at Poep. 6
Meeting, Yeat updatePJM Reliability Analysis Update, TEAC May 8, 2026p. 1
Meeting, Nokesville scope changePJM Reliability Analysis Update, TEAC October 6, 2026p. 1

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 3, 2024Item 11 - Reliability Analysis Update PDF2024W1 – Regional Cluster Preferred Solution: 2024-W1-24 $672.43 M6/1/2029
January 7, 2025Item 12 - Reliability Analysis Update PDFRecommended Solution: 2024-W1-24 $672.43 M6/1/2029
October 6, 2026Item 16 - Reliability Analysis Update - Presentation PDFNokesville – Hornbaker Bristow New 230kV Line $18.14M6/1/2029

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.