Piqua data center service (Dayton-2025-007)
Dayton-2025-007. Presented by AES Ohio in PJM planning materials (Dayton zone, OH).
Profile
AES Ohio presented this solution for need number Dayton-2025-007 at PJM's May 2026 solution meeting, at a total estimated cost of $591.5 million and a projected in-service date of June 30, 2032. (p. 3, p. 4, p. 8) The project driver is a datacenter customer request for service near AES Ohio's Eldean Substation in Piqua, Ohio, listed as 45 MW by December 2027 rising to 1400 MW by May 2033. (p. 3) When the need was first presented in July 2025 the request topped out at 600 MW by December 2030; AES Ohio presented a need change in February 2026. (p. 7, p. 3) The solution is built in four phases, from July 31, 2028 to June 30, 2032: a new Concord substation near the customer site, first at 138 kV and then at 345 kV, and a new Brown 345 kV substation cut into the Miami - Shelby line, joined to Concord by three 345 kV circuits. (p. 4, p. 7, p. 5, p. 6) The largest single item is a new approximately 37-mile 345 kV line from Brown to AEP's Patina substation, estimated at $174.2 million; the deck marks the Patina upgrade as to be built in future by AEP. (p. 7) Two customer feed items, $8.4 million at 138 kV and $14.8 million at 345 kV, are labeled Paid by Customer. (p. 4, p. 6) AES Ohio lists the status as Conceptual and says rebuilds in AEP's Lima territory were not selected due to higher costs and extensive outages. (p. 8)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Concord 138 kV substation (Phase 1) | Cut in the West Milton - Eldean 138 kV line, ~2-mile double circuit to a new 138 kV Concord substation with two 31.2 MVAR capacitor banks; estimated $41.6M | p. 4 |
| Concord 138 kV customer feeds (Phase 1) | Three 138kV feeds to the customer; estimated $8.4M (Paid by Customer) | p. 4 |
| Brown 345 kV substation (Phase 2) | Cut the Miami - Shelby 345 kV line into a new Brown substation; estimated $40.8M | p. 5 |
| Brown - Miami 345 kV rebuild (Phase 2) | Rebuild ~11 miles from Brown to Miami as double circuit; estimated $22.3M | p. 5 |
| Miami 345 kV substation (Phase 2) | Expand Miami 345 kV; estimated $5.4M | p. 5 |
| Concord 345 kV substation (Phase 2) | New Concord 345 kV substation with two 61.2 MVAR capacitor banks and two 450MVA 138/345kV transformers; estimated $50.4M | p. 5 |
| Brown - Concord 345 kV lines 1 & 2 (Phase 2) | ~10-mile double circuit Brown - Concord; estimated $67.2M | p. 5 |
| Concord 345 kV customer feeds (Phase 3) | Six 345 kV feeds to the customer; estimated $14.8M (Paid by Customer) | p. 6 |
| Brown - Concord 345 kV line 3 (Phase 3) | New ~10-mile single circuit Concord - Brown; estimated $48.2M | p. 6 |
| Concord STATCOMs (Phase 3) | Two 50 MVar STATCOMs at Concord; estimated $44M | p. 6 |
| Concord 345 kV expansion (Phase 3) | Expand Concord 345 kV; estimated $46.8M | p. 6 |
| Brown 345 kV expansion (Phase 3) | Expand Brown 345 kV; estimated $4.7M | p. 6 |
| Brown - Patina 345 kV line (Phase 4) | New ~37-mile single circuit 345 kV line from Brown to AEP's Patina substation; estimated $174.2M | p. 7 |
| Brown 345 kV expansion (Phase 4) | Expand Brown 345 kV; estimated $4.7M | p. 7 |
| Patina 345 kV expansion (Phase 4) | Expand AEP's Patina 345 kV substation; estimated $18M | p. 7 |
Details as printed
| Project driver | Customer Request | p. 3 |
|---|---|---|
| Customer request, Eldean (Piqua) | 45 MW by 12/2027, rising to 600 MW by 12/2029 and 1400 MW by 05/2033 | p. 3 |
| Need presented | Need Meeting 7/08/2025 | p. 7 |
| Original load request | 12/2027 45 MW, 12/2028 205 MW, 12/2029 440 MW, 12/2030 600 MW | p. 7 |
| Need change | Need change presented at the Need Meeting 02/03/2026 | p. 3 |
| Phase 1 in-service | Phase 1 in service July 31, 2028 | p. 4 |
| Phase 2 in-service | December 31,2030 | p. 5 |
| Phase 3 in-service | April 30,2031 | p. 6 |
| Phase 4 in-service | Phase 4 in service June 30, 2032 | p. 7 |
| Alternative considered | Rebuilds in AEP Lima territory, including the ~30-mile Brown - Shelby - Gristmill - SW Lima 345kV corridor, were not selected due to higher costs and extensive outages | p. 8 |
| Patina substation | Patina 345 kV substation upgrade: to be built in future by AEP | p. 7 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| July 8, 2025 | Item 05 - Dayton Supplemental Projects PDF | not printed | 12/2030 | Need Meeting 7/08/2025 | |
| February 3, 2026 | Item 06 - Dayton Supplemental Projects PDF | not printed | not printed | Need Meeting 02/03/2026 | |
| May 8, 2026 | item 05 - Dayton Supplemental Projects PDF | $591.5M | June 30th, 2032 | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
Not printed
- The decks describe the customer only as a datacenter customer; they do not name it.
- No county is printed for the Concord or Brown sites.
- No supplemental project (s-number) is printed yet; the latest tracked deck is the May 8, 2026 solution meeting.
- No news article about this program could be opened (searched 2026-11-27).
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.