Customer in Elk Grove (ComEd-2024-003)
Customer in Elk Grove. Presented by ComEd in PJM planning materials (ComEd zone).
Profile
ComEd presented Customer in Elk Grove (need ComEd-2024-003, supplemental projects s3584.1 and s3584.2) to PJM's Western subregional RTEP committee on September 19, 2025, at a total estimated transmission cost of $319.4 million. (p. 7, p. 1, p. 8) The deck describes a new customer looking for transmission service in the Elk Grove area, with initial loading of 16 MW in December 2027, 56 MW in 2029 and an ultimate load of 250 MW. (p. 7) The first phase serves a new customer substation radially over two new 1.5 mile 138 kV underground lines from Dierking substation; the second adds two new 2.7 mile underground lines from Pine substation and a second cable per phase on the Elk Grove East - Dierking and Itasca - Pine underground lines. (p. 7, p. 8) ComEd puts the two phases at $125.2 million and $194.2 million, with projected in-service dates of December 31, 2027 and December 31, 2028, and lists the status as Engineering. (p. 7, p. 8) ComEd's 2025 Local Plan submission, whose process stage is dated March 26, 2025, lists the same project at $289.4 million with the status Conceptual, 1.7 mile Dierking lines and 3 mile Pine lines, and without the 56 MW step in 2029. (p. 15, p. 17, p. 16, p. 7) That submission says the need was first presented at a need meeting on January 19, 2024 and a solutions meeting on September 20, 2024. (p. 15)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Dierking - customer 138kV underground lines (Phase 1) | Two new 1.5 mile underground lines, 2500mm2 XLPE cables per phase | p. 7 |
| Customer substation (Phase 1) | 11 circuit breakers, 138kV double ring bus, 3 138/34 kV 112 MVA transformers | p. 7 |
| Dierking 138kV substation (Phase 1) | Install 2 new 138kV circuit breakers | p. 7 |
| Elk Grove East - Dierking 138kV lines (Phase 2) | Second 2500mm2 XLPE cable per phase on two 1.8 mile underground lines | p. 8 |
| Itasca - Pine 138kV lines (Phase 2) | Second 2500mm2 XLPE cable per phase on two 2.9 mile underground lines | p. 8 |
| Pine 138kV substation (Phase 2) | Install two new 138kV circuit breakers | p. 8 |
| Pine - customer 138kV underground lines (Phase 2) | Two new 2.7 mile underground lines | p. 8 |
Details as printed
| Project driver | Customer Service | p. 7 |
|---|---|---|
| Customer request, Elk Grove | 16 MW in December 2027, 21 MW in 2028, 56 MW in 2029, ultimate 250 MW | p. 7 |
| Phase 1 cost (s3584.1) | Direct connect facilities: $125.2M | p. 7 |
| Phase 2 cost (s3584.2) | Direct connect facilities: $194.2M | p. 8 |
| Local Plan submission | Submission of Supplemental Project for inclusion in the Local Plan March 26, 2025 | p. 15 |
| Previously presented | Solutions Meeting 9/20/2024; Need Meeting 1/19/2024 | p. 15 |
| Customer request, Local Plan version | 16 MW in December 2027, 21 MW in 2028, ultimate 250 MW | p. 15 |
| Cost in the Local Plan submission | $289.4M | p. 17 |
| Status in the Local Plan submission | Conceptual | p. 17 |
| Phase 1 lines, Local Plan version | Two new 1.7 mile 138 kV underground lines from Dierking | p. 16 |
| Phase 2 lines, Local Plan version | Two new 3 mile 138 kV underground lines from Pine | p. 17 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| September 19, 2025 | Item 04 - ComEd Supplemental Projects PDF | Customer in Elk Grove | $319.4M | 12/31/2027 (s3584.1), 12/31/2028 (s3584.2) | Engineering |
| October 8, 2025 | Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2025 PDF | Customer in Elk Grove | $289.4M | 12/31/2027 (s3584.1), 12/31/2028 (s3584.2) | Conceptual |
| Date not printed | Comed  PDF | Customer in Elk Grove | $289.4M | 12/31/2027 (s3584.1), 12/31/2028 (s3584.2) | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- ComEd Dierking (COMED)
- ComEd Elk Grove East (COMED)
- ComEd Itasca (COMED)
- ComEd Pine (COMED)
- Dierking (COMED)
- Elk Grove East (COMED)
- Itasca (COMED): expansion described
- Pine (COMED)
Not printed
- No state or county is printed on the cited pages; Illinois is not printed.
- The deck names the customer only as Customer; it does not say what the load is.
- The September 19, 2025 deck prints no process stage for this project.
- PJM's tracked history puts the Local Plan document (posted for the October 8, 2025 TEAC meeting) after the September 19, 2025 deck, but its content is the March 26, 2025 submission, so its $289.4M is the older figure.
- A separate Customer in Elk Grove need (ComEd-2023-005, s3579.1, Elk Grove substation GIS expansion) appears in the same Local Plan; nothing printed ties it to this customer, so it is not a member.
- No news articles about this program were found (searched 2026-11-27). TD World reported on ComEd's GRIT project, which includes a Dierking substation in Elk Grove Village, but the article does not mention this need or customer, so it is not listed.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.