Customer in Elk Grove (ComEd-2024-003)

Customer in Elk Grove. Presented by ComEd in PJM planning materials (ComEd zone).

$319.4Mcost estimate as printed p. 8
12/31/2027, 12/31/2028projected in service p. 8
Engineeringstatus as printed p. 8

Profile

ComEd presented Customer in Elk Grove (need ComEd-2024-003, supplemental projects s3584.1 and s3584.2) to PJM's Western subregional RTEP committee on September 19, 2025, at a total estimated transmission cost of $319.4 million. (p. 7, p. 1, p. 8) The deck describes a new customer looking for transmission service in the Elk Grove area, with initial loading of 16 MW in December 2027, 56 MW in 2029 and an ultimate load of 250 MW. (p. 7) The first phase serves a new customer substation radially over two new 1.5 mile 138 kV underground lines from Dierking substation; the second adds two new 2.7 mile underground lines from Pine substation and a second cable per phase on the Elk Grove East - Dierking and Itasca - Pine underground lines. (p. 7, p. 8) ComEd puts the two phases at $125.2 million and $194.2 million, with projected in-service dates of December 31, 2027 and December 31, 2028, and lists the status as Engineering. (p. 7, p. 8) ComEd's 2025 Local Plan submission, whose process stage is dated March 26, 2025, lists the same project at $289.4 million with the status Conceptual, 1.7 mile Dierking lines and 3 mile Pine lines, and without the 56 MW step in 2029. (p. 15, p. 17, p. 16, p. 7) That submission says the need was first presented at a need meeting on January 19, 2024 and a solutions meeting on September 20, 2024. (p. 15)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Dierking - customer 138kV underground lines (Phase 1)Two new 1.5 mile underground lines, 2500mm2 XLPE cables per phasep. 7
Customer substation (Phase 1)11 circuit breakers, 138kV double ring bus, 3 138/34 kV 112 MVA transformersp. 7
Dierking 138kV substation (Phase 1)Install 2 new 138kV circuit breakersp. 7
Elk Grove East - Dierking 138kV lines (Phase 2)Second 2500mm2 XLPE cable per phase on two 1.8 mile underground linesp. 8
Itasca - Pine 138kV lines (Phase 2)Second 2500mm2 XLPE cable per phase on two 2.9 mile underground linesp. 8
Pine 138kV substation (Phase 2)Install two new 138kV circuit breakersp. 8
Pine - customer 138kV underground lines (Phase 2)Two new 2.7 mile underground linesp. 8

Details as printed

Project driverCustomer Servicep. 7
Customer request, Elk Grove16 MW in December 2027, 21 MW in 2028, 56 MW in 2029, ultimate 250 MWp. 7
Phase 1 cost (s3584.1)Direct connect facilities: $125.2Mp. 7
Phase 2 cost (s3584.2)Direct connect facilities: $194.2Mp. 8
Local Plan submissionSubmission of Supplemental Project for inclusion in the Local Plan March 26, 2025p. 15
Previously presentedSolutions Meeting 9/20/2024; Need Meeting 1/19/2024p. 15
Customer request, Local Plan version16 MW in December 2027, 21 MW in 2028, ultimate 250 MWp. 15
Cost in the Local Plan submission$289.4Mp. 17
Status in the Local Plan submissionConceptualp. 17
Phase 1 lines, Local Plan versionTwo new 1.7 mile 138 kV underground lines from Dierkingp. 16
Phase 2 lines, Local Plan versionTwo new 3 mile 138 kV underground lines from Pinep. 17

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
September 19, 2025Item 04 - ComEd Supplemental Projects PDFCustomer in Elk Grove $319.4M12/31/2027 (s3584.1), 12/31/2028 (s3584.2)Engineering
October 8, 2025Informational Only - ComEd Local Plan Submission of the Supplemental Projects for 2025 PDFCustomer in Elk Grove $289.4M12/31/2027 (s3584.1), 12/31/2028 (s3584.2)Conceptual
Date not printedComed&nbsp PDFCustomer in Elk Grove $289.4M12/31/2027 (s3584.1), 12/31/2028 (s3584.2)Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.