Bramah–High Ridge 500 kV
Bramah-High Ridge 500 kV line. Presented by PJM in PJM planning materials (BGE, PECO, PEPCO, DPL zone).
Profile
This is the part of PJM's 2022 Window 3 East cluster solution that Exelon proposed (2022-W3-344/660): a new North Delta – High Ridge 500 kV line, a new High Ridge 500 kV substation and a rebuild of the existing Peach Bottom – Conastone 500 kV line (5012), presented by PJM on December 5, 2023 at a proposed cost of $708.77 million. (p. 52, p. 54, p. 53, p. 1, p. 56) The line starts at North Delta near the Peach Bottom 500 kV stations, and the same slides list terminal, relay and breaker work at Conastone, Brighton, Chalk Point and Red Lion. (p. 52, p. 55, p. 56) The December 2023 slide prints a required in-service date of June 1, 2027 and a projected in-service window of 2028-2030. (p. 56, p. 1) North Delta is now printed as Bramah, a Transource substation; on March 10, 2026 PJM added $1.37 million of terminal work at Rock Springs 500 kV (B3800.55) because the original scope for terminating the Rock Springs line at Bramah/North Delta did not cover it. (p. 10, p. 1) At the October 6, 2026 TEAC, Exelon's updated estimates put the BGE segment of the Bramah-High Ridge line (b3800.32, about 59 miles, down from about 65 miles in 2023) at $810.14 million, up from $407.11 million, and the PECO segment (b3800.31) at $71.2 million, up from $13.36 million. (p. 1, p. 19, p. 54, p. 1) PJM's slide attributes the increases to estimates now based on at least 30% design and engineering, and to competition for labor, materials and manufacturing capacity from data center construction and other programs; it notes that cost containment provisions apply to most of the BGE and PEPCO 2022 Window 3 projects. (p. 20)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Peach Bottom South - North Delta 500 kV line | New line cut into Peach Bottom tie #1 and extended to North Delta, about 1.25 miles of new right-of-way | p. 52 |
| North Delta 500 kV terminations | North Delta terminations for the North Delta - High Ridge line, the Rock Springs line (5034/5014) and the new Peach Bottom - North Delta line | p. 52 |
| High Ridge 500 kV substation (new) | Build High Ridge 500 kV substation cut into the Brighton - Waugh Chapel 500 kV line: three bay breaker-and-a-half, two 500/230 kV transformers (B3800.26 - B3800.30) | p. 53 |
| Rebuild of line 5012, Peach Bottom - Conastone | Rebuild the existing Peach Bottom - Conastone 500 kV line (5012) on single circuit structures in existing right-of-way, cut into North Delta and Graceton 500 kV (B3800.34 - B3800.36) | p. 54 |
| North Delta - High Ridge 500 kV line | New North Delta - High Ridge 500 kV line, about 65 miles (B3800.31 and B3800.32) | p. 54 |
| Conastone - Brighton 500 kV (5011) | Replace terminal equipment at Conastone and Brighton 500 kV (B3800.40, B3800.41) | p. 55 |
| Brighton - Waugh Chapel 500 kV (5053) | Replace terminal equipment at Brighton 500 kV (B3800.33) | p. 55 |
| Chalk Point - Cheltanham 500 kV (5073) | Replace relay at Chalk Point 500 kV (B3800.38) | p. 55 |
| Conastone breakers (5012) | Upgrade two existing 500 kV breakers at Conastone from 4000A to 5000A (B3800.37) | p. 55 |
| Peach Bottom North and South 500 kV | Reconfigure and upgrade terminal and substation equipment at both Peach Bottom 500 kV substations (B3800.42) | p. 56 |
| Red Lion - Hope Creek 500 kV | Replace terminal equipment at Red Lion (B3800.39) | p. 56 |
Details as printed
| Proposal | Exelon proposal 2022-W3-344/660, recommended for the East cluster | p. 52 |
|---|---|---|
| North Delta now printed as Bramah | The North Delta 500 kV substation is printed as Bramah/North Delta, proposed by Transource | p. 10 |
| Update meeting | TEAC March 10, 2026 | p. 1 |
| Added scope, Rock Springs (B3800.55) | Added scope B3800.55 (Rock Springs terminal equipment), $1.37M, projected in service 3/31/2027 | p. 10 |
| Cost update meeting | TEAC October 6, 2026 | p. 1 |
| Bramah-High Ridge line, BGE (b3800.32) | $407.11M original, $810.14M updated, change $403.03M; cost containment applicable | p. 19 |
| Bramah-High Ridge line, PECO (b3800.31) | $13.36M original, $71.2M updated, change $57.84M; cost containment not applicable | p. 19 |
| High Ridge transformers, BGE (b3800.30) | $22.11M original, $78.34M updated, change $56.23M | p. 19 |
| Bramah termination, PECO (b3800.44) | $3.4M original, $5.0M updated, change $1.6M | p. 19 |
| Exelon 2022 Window 3 cost table, total | Table total: $753.49M original, $1420.98M updated, change $667.49M (the table also lists rows outside this program, such as the Otter Creek - Doubs BGE row and Doubs-area PEPCO rows) | p. 19 |
| Stated drivers of the increases | Updated estimates reflect at least 30% design and engineering and procurement of long-lead equipment | p. 20 |
| Stated drivers, market | Competition for labor, materials and manufacturing capacity from data center construction and other programs | p. 20 |
| Cost containment | Cost containment provisions apply to most of the BGE and PEPCO 2022 Window 3 projects | p. 20 |
| Related: North Delta expansion (Transource, not a member) | Transource's North Delta expansion (B3737.47, NJOSW SAA 1.0) is presented beside this solution at $104.1 M | p. 51 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | Recommended Solutions to Address Clusters - East | $708.77 M | 2028-2030 | |
| March 10, 2026 | Item 11 - Reliability Analysis Update PDF | 2022 Window 3 Upgrades Additional Scope Replace Terminal Equipment at Rock Springs 500 kV | $1.37M | 3/31/2027 |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Bramah/North Delta (PJM system-wide): described as new
- High Ridge (PJM system-wide): described as new
- North Delta (PJM system-wide): described as new
- Peach Bottom South (PJM system-wide): described as new
- Brighton (PJM system-wide)
- Chalk Point (PJM system-wide)
- Cheltanham (PJM system-wide)
- Conastone (PJM system-wide)
- Gracetone (PJM system-wide)
- Hope Creek (PJM system-wide)
- Peach Bottom (PJM system-wide)
- Peach Bottom North (PJM system-wide)
- Red Lion (PJM system-wide)
- Rock Springs (PJM system-wide)
- Waugh Chapel (PJM system-wide)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- SUN: BGE proposes $1.1B transmission line through Baltimore, Howard, Harford counties, WBFF FOX45 Baltimore (from The Baltimore Sun), July 9, 2026. FOX45, citing The Baltimore Sun, reported that BGE filed a Certificate of Public Convenience and Necessity application on June 26 for a nearly $1.1 billion, 59-mile 500 kV line from the High Ridge substation in Howard County to the Maryland-Pennsylvania line near the Graceton substation in Harford County, one of five proposals in BGE's Tri-County Transmission Upgrade Project.
Not printed
- No state or county is printed on the cited PJM pages; the counties in the news item are the outlet's.
- No updated total for the whole Exelon 2022-W3-344/660 East package is printed; the October 2026 table gives per-baseline updates and a total that also covers rows outside this program.
- No project status (engineering, construction) is printed on the PJM slides.
- No updated in-service date is printed after December 2023.
- The 2023 slides do not separate the cost of the line from the rest of the package.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.