Bramah–High Ridge 500 kV

Bramah-High Ridge 500 kV line. Presented by PJM in PJM planning materials (BGE, PECO, PEPCO, DPL zone).

$708.77Mcost estimate as printed p. 56
2028-2030projected in service p. 56
Cost updatestatus as printed p. 19

Profile

This is the part of PJM's 2022 Window 3 East cluster solution that Exelon proposed (2022-W3-344/660): a new North Delta – High Ridge 500 kV line, a new High Ridge 500 kV substation and a rebuild of the existing Peach Bottom – Conastone 500 kV line (5012), presented by PJM on December 5, 2023 at a proposed cost of $708.77 million. (p. 52, p. 54, p. 53, p. 1, p. 56) The line starts at North Delta near the Peach Bottom 500 kV stations, and the same slides list terminal, relay and breaker work at Conastone, Brighton, Chalk Point and Red Lion. (p. 52, p. 55, p. 56) The December 2023 slide prints a required in-service date of June 1, 2027 and a projected in-service window of 2028-2030. (p. 56, p. 1) North Delta is now printed as Bramah, a Transource substation; on March 10, 2026 PJM added $1.37 million of terminal work at Rock Springs 500 kV (B3800.55) because the original scope for terminating the Rock Springs line at Bramah/North Delta did not cover it. (p. 10, p. 1) At the October 6, 2026 TEAC, Exelon's updated estimates put the BGE segment of the Bramah-High Ridge line (b3800.32, about 59 miles, down from about 65 miles in 2023) at $810.14 million, up from $407.11 million, and the PECO segment (b3800.31) at $71.2 million, up from $13.36 million. (p. 1, p. 19, p. 54, p. 1) PJM's slide attributes the increases to estimates now based on at least 30% design and engineering, and to competition for labor, materials and manufacturing capacity from data center construction and other programs; it notes that cost containment provisions apply to most of the BGE and PEPCO 2022 Window 3 projects. (p. 20)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Peach Bottom South - North Delta 500 kV lineNew line cut into Peach Bottom tie #1 and extended to North Delta, about 1.25 miles of new right-of-wayp. 52
North Delta 500 kV terminationsNorth Delta terminations for the North Delta - High Ridge line, the Rock Springs line (5034/5014) and the new Peach Bottom - North Delta linep. 52
High Ridge 500 kV substation (new)Build High Ridge 500 kV substation cut into the Brighton - Waugh Chapel 500 kV line: three bay breaker-and-a-half, two 500/230 kV transformers (B3800.26 - B3800.30)p. 53
Rebuild of line 5012, Peach Bottom - ConastoneRebuild the existing Peach Bottom - Conastone 500 kV line (5012) on single circuit structures in existing right-of-way, cut into North Delta and Graceton 500 kV (B3800.34 - B3800.36)p. 54
North Delta - High Ridge 500 kV lineNew North Delta - High Ridge 500 kV line, about 65 miles (B3800.31 and B3800.32)p. 54
Conastone - Brighton 500 kV (5011)Replace terminal equipment at Conastone and Brighton 500 kV (B3800.40, B3800.41)p. 55
Brighton - Waugh Chapel 500 kV (5053)Replace terminal equipment at Brighton 500 kV (B3800.33)p. 55
Chalk Point - Cheltanham 500 kV (5073)Replace relay at Chalk Point 500 kV (B3800.38)p. 55
Conastone breakers (5012)Upgrade two existing 500 kV breakers at Conastone from 4000A to 5000A (B3800.37)p. 55
Peach Bottom North and South 500 kVReconfigure and upgrade terminal and substation equipment at both Peach Bottom 500 kV substations (B3800.42)p. 56
Red Lion - Hope Creek 500 kVReplace terminal equipment at Red Lion (B3800.39)p. 56

Details as printed

ProposalExelon proposal 2022-W3-344/660, recommended for the East clusterp. 52
North Delta now printed as BramahThe North Delta 500 kV substation is printed as Bramah/North Delta, proposed by Transourcep. 10
Update meetingTEAC March 10, 2026p. 1
Added scope, Rock Springs (B3800.55)Added scope B3800.55 (Rock Springs terminal equipment), $1.37M, projected in service 3/31/2027p. 10
Cost update meetingTEAC October 6, 2026p. 1
Bramah-High Ridge line, BGE (b3800.32)$407.11M original, $810.14M updated, change $403.03M; cost containment applicablep. 19
Bramah-High Ridge line, PECO (b3800.31)$13.36M original, $71.2M updated, change $57.84M; cost containment not applicablep. 19
High Ridge transformers, BGE (b3800.30)$22.11M original, $78.34M updated, change $56.23Mp. 19
Bramah termination, PECO (b3800.44)$3.4M original, $5.0M updated, change $1.6Mp. 19
Exelon 2022 Window 3 cost table, totalTable total: $753.49M original, $1420.98M updated, change $667.49M (the table also lists rows outside this program, such as the Otter Creek - Doubs BGE row and Doubs-area PEPCO rows)p. 19
Stated drivers of the increasesUpdated estimates reflect at least 30% design and engineering and procurement of long-lead equipmentp. 20
Stated drivers, marketCompetition for labor, materials and manufacturing capacity from data center construction and other programsp. 20
Cost containmentCost containment provisions apply to most of the BGE and PEPCO 2022 Window 3 projectsp. 20
Related: North Delta expansion (Transource, not a member)Transource's North Delta expansion (B3737.47, NJOSW SAA 1.0) is presented beside this solution at $104.1 Mp. 51

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 5, 2023Item 15 - Reliability Analysis Update 2022 Window 3Recommended Solutions to Address Clusters - East $708.77 M2028-2030
March 10, 2026Item 11 - Reliability Analysis Update PDF2022 Window 3 Upgrades Additional Scope Replace Terminal Equipment at Rock Springs 500 kV $1.37M3/31/2027

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.