Sammis – Star 345 kV

Sammis – Star 345 kV Line. Presented by FirstEnergy in PJM planning materials (ATSI zone).

$343.70Mcost estimate as printed p. 48
5/30/2031projected in service p. 48
Conceptualstatus as printed p. 10

Profile

FirstEnergy presented a rebuild of the approximately 68.6-mile Sammis – Star 345 kV line to PJM as a supplemental project, at an estimated project cost of $343.70 million and a projected in-service date of May 30, 2031. (p. 1, p. 48) The need was presented in April 2024 and the solution in July 2025, and FirstEnergy submitted the project for inclusion in the local plan in September 2025 as supplemental project s3717.1. (p. 47, p. 48) FirstEnergy lists the driver as equipment material condition, performance and risk: the line was built approximately 65 years ago and consists of 375 steel lattice towers and 22 wood pole H-frame structures. (p. 47) The slides say the suspension towers are susceptible to cascading failures, cite a tornado-induced tower failure that destroyed 13 towers, and say current modeling indicates the steel towers do not have the structural strength to withstand NESC required load cases. (p. 47) The only alternative listed is to maintain the line in its existing condition, with an elevated risk of failure. (p. 10) FirstEnergy lists the line's SN rating rising from 1382 MVA to 2504 MVA after the rebuild, and the July 2025 slides list the project status as Conceptual. (p. 10, p. 1)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Sammis – Star 345 kV lineRebuild the existing line, approximately 68.6 milesp. 48
Sammis and Star substationsReplace line relayingp. 10

Details as printed

Previously presentedNeed Meeting - 04/02/2024; Solution Meeting - 07/08/2025p. 47
Supplemental IDs3717.1p. 48
Project driverEquipment Material Condition, Performance and Riskp. 47
Line conditionBuilt approximately 65 years ago; approximately 68.6 miles; 375 steel lattice towers and 22 wood pole H-frame structuresp. 47
Cascading failure riskSuspension towers susceptible to cascading failures; a tornado-induced tower failure destroyed 13 towersp. 47
Structural strengthSteel towers modeled as not able to withstand NESC required load cases or FirstEnergy's additional wind and ice load casesp. 47
Line ratings, before and afterBefore: 1382 / 1712 / 1637 / 2116 MVA; after: 2504 / 2883 / 2505 / 3033 MVA (SN/SE/WN/WE)p. 10
Alternative consideredMaintain the line in its existing condition, with elevated risk of failurep. 10

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
July 8, 2025Item 03 - ATSI Supplemental Projects PDFSammis – Star 345 kV Line $343.70M5/30/2031Conceptual
October 8, 2025Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2025 PDFSammis – Star 345 kV Line $343.70M5/30/2031Submission of Supplemental Projects for Inclusion in the Local Plan – 09/25/2025
Date not printedATSI&nbsp PDFSammis – Star 345 kV Line $343.70M5/30/2031Submission of Supplemental Projects for Inclusion in the Local Plan – 09/25/2025

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.