Customer in Joliet (ComEd-2025-016)
Customer in Joliet. Presented by ComEd in PJM planning materials (ComEd zone).
Profile
ComEd presented Customer in Joliet (need ComEd-2025-016) as a solution to PJM's TEAC on February 3, 2026, at an estimated transmission cost of $269 million, a projected in-service date of July 1, 2028 and the status Conceptual. (p. 14, p. 15, p. 1) The deck describes a new customer looking for transmission service in the Joliet area, with initial loading of 225 MW in June 2029 and an ultimate load of 1,800 MW in 2033. (p. 14) The proposed solution cuts into the existing 345 kV Goodings Grove - Elwood lines and extends 4 lines 0.2 miles each to a new Rowell substation, initially 24 345 kV gas-insulated circuit breakers in a breaker and a half configuration with two 150 MVAR capacitor banks. (p. 15) Each new customer-owned substation would be served radially by two new 345 kV lines of about 0.5 mile from Rowell; the one-line diagram shows five customer substations, but the text does not give a count. (p. 15) ComEd first presented the need at a need meeting on September 9, 2025 with the same load figures. (p. 11) ComEd's July 7, 2026 345KV STATCOMS solution lists ComEd-2025-016 among the eight needs it addresses. (p. 13)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Goodings Grove - Elwood 345kV cut-in | Cut into existing Goodings Grove - Elwood lines; extend 4 lines 0.2 miles each to a new Rowell substation | p. 15 |
| Rowell 345kV substation (new) | 24 345 kV GIS circuit breakers in a breaker and a half configuration | p. 15 |
| Rowell capacitor banks | 2-150 MVAR, 345kV capacitor banks | p. 15 |
| Rowell - customer 345kV lines | Each new customer-owned substation radially served by two new approximately 0.5-mile 345 kV lines | p. 15 |
Details as printed
| Project driver | Customer Service | p. 14 |
|---|---|---|
| Customer request, Joliet | 225 MW in June 2029, ultimate 1,800 MW in 2033 | p. 14 |
| Need presented | Need Meeting 9/9/2025 | p. 11 |
| Customer request, need meeting version | 225 MW in June 2029, ultimate 1,800 MW in 2033 | p. 11 |
| Model | 2029 RTEP | p. 15 |
| Also listed under 345KV STATCOMS (July 2026) | ComEd-2025-016 is one of eight need numbers on the 345KV STATCOMS solution, Solution Meeting 7/7/2026 | p. 13 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| September 9, 2025 | Item 12 - ComEd Supplemental Projects PDF | Customer in Joliet | not printed | not printed | Need Meeting 9/9/2025 |
| February 3, 2026 | Item 10 - ComEd Supplemental Projects PDF | Customer in Joliet | $269M | 7/1/2028 | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Rowell (COMED): described as new
- Elwood (COMED)
- Goodings Grove (COMED)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- 795-acre data center planned for Joliet, Shaw Local (The Herald-News), October 3, 2025. The Herald-News reported that a 795-acre data center complex proposed for farmland south of the Chicagoland Speedway includes construction of a ComEd substation at the site, which a developer representative said the developer would pay for; the article does not cite a PJM need number.
- Joliet OKs controversial 795-acre data center, Shaw Local (The Herald-News), March 20, 2026. The Herald-News reported that the Joliet City Council approved the Joliet Technology Center, which developers Hillwood and PowerHouse Data Centers say would use 1.8 gigawatts at full use, with construction starting in early 2027; the article does not mention ComEd or this PJM need.
Not printed
- No state or county is printed on the cited pages; Illinois is not printed.
- The decks name the customer only as a new customer; they do not say what the load is.
- The projected in-service date (7/1/2028) is earlier than the first printed load step (June 2029); the deck does not explain the gap.
- No cost breakdown by component and no Local Plan submission for this need were found in the archived documents.
- The 2026 RTEP Window 1 proposal list (TEAC, November 3, 2026) includes several Joliet - Elwood 345 kV line proposals; nothing printed ties them to this need, so they are not members.
- Neither news article cites ComEd-2025-016 or the Rowell substation; the 1.8 gigawatt figure and the location south of Joliet match the deck, but the link between the Joliet Technology Center and this need is not printed by ComEd, PJM or the outlets.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.