Substation Scout

Customer in Joliet (ComEd-2025-016)

Customer in Joliet. Presented by ComEd in PJM planning materials (ComEd zone).

$269Mcost estimate as printed p. 15
7/1/2028projected in service p. 15
Conceptualstatus as printed p. 15

Profile

ComEd presented Customer in Joliet (need ComEd-2025-016) as a solution to PJM's TEAC on February 3, 2026, at an estimated transmission cost of $269 million, a projected in-service date of July 1, 2028 and the status Conceptual. (p. 14, p. 15, p. 1) The deck describes a new customer looking for transmission service in the Joliet area, with initial loading of 225 MW in June 2029 and an ultimate load of 1,800 MW in 2033. (p. 14) The proposed solution cuts into the existing 345 kV Goodings Grove - Elwood lines and extends 4 lines 0.2 miles each to a new Rowell substation, initially 24 345 kV gas-insulated circuit breakers in a breaker and a half configuration with two 150 MVAR capacitor banks. (p. 15) Each new customer-owned substation would be served radially by two new 345 kV lines of about 0.5 mile from Rowell; the one-line diagram shows five customer substations, but the text does not give a count. (p. 15) ComEd first presented the need at a need meeting on September 9, 2025 with the same load figures. (p. 11) ComEd's July 7, 2026 345KV STATCOMS solution lists ComEd-2025-016 among the eight needs it addresses. (p. 13)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Goodings Grove - Elwood 345kV cut-inCut into existing Goodings Grove - Elwood lines; extend 4 lines 0.2 miles each to a new Rowell substationp. 15
Rowell 345kV substation (new)24 345 kV GIS circuit breakers in a breaker and a half configurationp. 15
Rowell capacitor banks2-150 MVAR, 345kV capacitor banksp. 15
Rowell - customer 345kV linesEach new customer-owned substation radially served by two new approximately 0.5-mile 345 kV linesp. 15

Details as printed

Project driverCustomer Servicep. 14
Customer request, Joliet225 MW in June 2029, ultimate 1,800 MW in 2033p. 14
Need presentedNeed Meeting 9/9/2025p. 11
Customer request, need meeting version225 MW in June 2029, ultimate 1,800 MW in 2033p. 11
Model2029 RTEPp. 15
Also listed under 345KV STATCOMS (July 2026)ComEd-2025-016 is one of eight need numbers on the 345KV STATCOMS solution, Solution Meeting 7/7/2026p. 13

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
September 9, 2025Item 12 - ComEd Supplemental Projects PDFCustomer in Joliet not printednot printedNeed Meeting 9/9/2025
February 3, 2026Item 10 - ComEd Supplemental Projects PDFCustomer in Joliet $269M7/1/2028Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first