Substation Scout

North Anna - Thornburg - Bristers 500kV Line

New 500kV Line North Anna - Thornburg - Bristers. Presented by PJM in PJM planning materials (Dominion zone).

$661.63Mcost estimate as printed p. 15
9/16/2030projected in service p. 15
Approved baselinestatus as printed p. 81

Profile

PJM's May 8, 2026 Reliability Analysis Update presents baseline projects b4000.344 and b4000.345 as a new 500kV line from North Anna to a new substation called Thornburg (formerly Kraken) and on to Bristers, with a total proposed cost estimate of $661.63M and a revised in-service date of 9/16/2030. (p. 1, p. 14, p. 15) The line began as part of proposal 2024-W1-967, listed in October 2024 as the Kraken loop; PJM's December 2024 preferred solution priced the whole proposal, which also included the new Kraken substation and work at North Anna, Ladysmith and Elmont, at $704.25 M, and PJM's recommendation the following month revised that to $704.33 M with a 6/1/2029 in-service date. (p. 74, p. 76, p. 60) In the recommended solution the North Anna - Kraken segment was $186.67M (b4000.344) and the Kraken - Yeat segment was $394.71M (b4000.345); in April 2026 the second segment was redirected to end at Bristers and its estimate changed to $384.96M. (p. 14, p. 59, p. 15) The May 2026 scope change switched the line to 5/2 structures that can carry a 230 kV underbuild, adding $90M ($29.5M for b4000.344 and $60.5M for b4000.345) to a transmission estimate of $571.63M; the slide gives load growth near the corridor, mainly data centers, since the 2024 RTEP Open Window 1 as the reason. (p. 1, p. 15, p. 14) A separate Dominion supplemental project (need DOM-2026-0022, project s4032) would string 230kV conductor rated at 1573 MVA on the same structures from North Anna to Bristers to serve approximately 3 GW of requested load, at $33.75 M with a projected in-service date of Q4 2030; Dominion's need slide says at least ten new delivery point requests for data center load in the corridor total close to 3000 MW. (p. 4, p. 81) The Thornburg substation itself (b4000.348) is listed under Valley Link Transmission, while the Bristers cut-in (b4000.346, $5.00M) was re-designated from Valley Link to Dominion/Vepco and the Ladysmith - Possum Point line cut-ins at Thornburg (b4000.351 and b4000.352) are designated to Dominion. (p. 14, p. 8)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
North Anna - Thornburg 500kV line (b4000.344)500kV line from North Anna (bypassing Ladysmith) to new Thornburg substation; $186.67M before the later scope changep. 14
Thornburg - Bristers 500kV line (b4000.345)500kV line from Thornburg to Bristers; $384.96M before the later scope changep. 14
Cut-in at Bristers (b4000.346)Cut-in of the 500 kV line from Kraken into Bristers; $5M, no cost changep. 15
North Anna substation equipment (b4000.347)Upgrade/install equipment at North Anna to 5000A; $9.12Mp. 59
Elmont terminal equipment (b4000.353, part of 2024-W1-967)Upgrade 500kV terminal equipment at Elmont; $8.9Mp. 60
Ladysmith expansion (b4000.354, part of 2024-W1-967)Expand Ladysmith substation with redundant breakers; $8.24Mp. 60

Details as printed

Voltage500kVp. 14
Kraken renamed ThornburgKraken Substation has been renamed to Thornburgp. 14
Estimate before the May 2026 scope changeTransmission estimated cost $571.63M; required and projected in service 6/1/2029; previously presented 1/7/2025 (b4000.344) and 4/7/2026 (b4000.345)p. 14
Scope change, May 2026Switch to 5/2 structures for the whole line, with a 0.36-mile segment from Stafford to Aquia Harbor on 5/5 structuresp. 15
Reason for scope change and cost updateLoad growth near the corridor, mainly data centers, since the project was proposed in the 2024 RTEP Open Window 1p. 15
Reason for 230 kV underbuild230 kV underbuilt capability enables reuse of existing structures and minimizes future environmental impactsp. 15
First listed, October 2024 portfoliosProposal 2024-W1-967, titled Kraken loopp. 74
Preferred solution, December 2024 (whole proposal)Estimated cost $704.25 M, required and projected in service 6/1/2029p. 76
Recommended solution, January 2025 (whole proposal)Estimated cost $704.25 M revised to $704.33 M, required in service 6/1/2029p. 60
Kraken - Yeat segment, January 2025500kV line from Kraken to Yeat, $394.71M (b4000.345)p. 59
Second segment redirected to Bristers, April 2026Endpoint changed from Yeat to Bristers; estimate $394.71M changed to $384.96M (b4000.345)p. 15
Thornburg substation (Valley Link)Thornburg substation b4000.348 listed under VLT VA: $84.41M original, $142.80M updatedp. 14
Cut-in b4000.346 re-designatedb4000.346 ($5.00M), originally awarded to Valley Link Transmission, re-designated to Dominion/Vepcop. 14
Line #568 cut-in at Thornburg (Dominion, separate tracked row)b4000.351 and b4000.352, $7.2M, designated entity Dominion; projected in service 9/16/2030p. 8
Related supplemental needNeed DOM-2026-0022, need meeting 05/08/2026p. 4
Data center requests in the corridor (Dominion need slide)At least ten new delivery point requests for data center load in the corridor, total requested load approaching 3000 MWp. 4
Related supplemental project s4032230kV conductor rated 1573 MVA on the same structures from North Anna to Bristers, to serve approximately 3 GW of requested load; $33.75 M, Q4 2030, Engineeringp. 81

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 3, 2024Item 11 - Reliability Analysis Update PDF2024W1 – Regional Cluster Preferred Solution: 2024-W1-967 $704.25 M6/1/2029
January 7, 2025Item 12 - Reliability Analysis Update PDFRecommended Solution: 2024-W1-967 $704.33 M6/1/2029
May 8, 2026Item 10 - Reliability Analysis Update PDFDominion Transmission Zone: Baseline New 500kV Line North Anna - Thornburg - Bristers $661.63M9/16/2030First Read

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first