North Anna - Thornburg - Bristers 500kV Line
New 500kV Line North Anna - Thornburg - Bristers. Presented by PJM in PJM planning materials (Dominion zone).
Profile
PJM's May 8, 2026 Reliability Analysis Update presents baseline projects b4000.344 and b4000.345 as a new 500kV line from North Anna to a new substation called Thornburg (formerly Kraken) and on to Bristers, with a total proposed cost estimate of $661.63M and a revised in-service date of 9/16/2030. (p. 1, p. 14, p. 15) The line began as part of proposal 2024-W1-967, listed in October 2024 as the Kraken loop; PJM's December 2024 preferred solution priced the whole proposal, which also included the new Kraken substation and work at North Anna, Ladysmith and Elmont, at $704.25 M, and PJM's recommendation the following month revised that to $704.33 M with a 6/1/2029 in-service date. (p. 74, p. 76, p. 60) In the recommended solution the North Anna - Kraken segment was $186.67M (b4000.344) and the Kraken - Yeat segment was $394.71M (b4000.345); in April 2026 the second segment was redirected to end at Bristers and its estimate changed to $384.96M. (p. 14, p. 59, p. 15) The May 2026 scope change switched the line to 5/2 structures that can carry a 230 kV underbuild, adding $90M ($29.5M for b4000.344 and $60.5M for b4000.345) to a transmission estimate of $571.63M; the slide gives load growth near the corridor, mainly data centers, since the 2024 RTEP Open Window 1 as the reason. (p. 1, p. 15, p. 14) A separate Dominion supplemental project (need DOM-2026-0022, project s4032) would string 230kV conductor rated at 1573 MVA on the same structures from North Anna to Bristers to serve approximately 3 GW of requested load, at $33.75 M with a projected in-service date of Q4 2030; Dominion's need slide says at least ten new delivery point requests for data center load in the corridor total close to 3000 MW. (p. 4, p. 81) The Thornburg substation itself (b4000.348) is listed under Valley Link Transmission, while the Bristers cut-in (b4000.346, $5.00M) was re-designated from Valley Link to Dominion/Vepco and the Ladysmith - Possum Point line cut-ins at Thornburg (b4000.351 and b4000.352) are designated to Dominion. (p. 14, p. 8)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| North Anna - Thornburg 500kV line (b4000.344) | 500kV line from North Anna (bypassing Ladysmith) to new Thornburg substation; $186.67M before the later scope change | p. 14 |
| Thornburg - Bristers 500kV line (b4000.345) | 500kV line from Thornburg to Bristers; $384.96M before the later scope change | p. 14 |
| Cut-in at Bristers (b4000.346) | Cut-in of the 500 kV line from Kraken into Bristers; $5M, no cost change | p. 15 |
| North Anna substation equipment (b4000.347) | Upgrade/install equipment at North Anna to 5000A; $9.12M | p. 59 |
| Elmont terminal equipment (b4000.353, part of 2024-W1-967) | Upgrade 500kV terminal equipment at Elmont; $8.9M | p. 60 |
| Ladysmith expansion (b4000.354, part of 2024-W1-967) | Expand Ladysmith substation with redundant breakers; $8.24M | p. 60 |
Details as printed
| Voltage | 500kV | p. 14 |
|---|---|---|
| Kraken renamed Thornburg | Kraken Substation has been renamed to Thornburg | p. 14 |
| Estimate before the May 2026 scope change | Transmission estimated cost $571.63M; required and projected in service 6/1/2029; previously presented 1/7/2025 (b4000.344) and 4/7/2026 (b4000.345) | p. 14 |
| Scope change, May 2026 | Switch to 5/2 structures for the whole line, with a 0.36-mile segment from Stafford to Aquia Harbor on 5/5 structures | p. 15 |
| Reason for scope change and cost update | Load growth near the corridor, mainly data centers, since the project was proposed in the 2024 RTEP Open Window 1 | p. 15 |
| Reason for 230 kV underbuild | 230 kV underbuilt capability enables reuse of existing structures and minimizes future environmental impacts | p. 15 |
| First listed, October 2024 portfolios | Proposal 2024-W1-967, titled Kraken loop | p. 74 |
| Preferred solution, December 2024 (whole proposal) | Estimated cost $704.25 M, required and projected in service 6/1/2029 | p. 76 |
| Recommended solution, January 2025 (whole proposal) | Estimated cost $704.25 M revised to $704.33 M, required in service 6/1/2029 | p. 60 |
| Kraken - Yeat segment, January 2025 | 500kV line from Kraken to Yeat, $394.71M (b4000.345) | p. 59 |
| Second segment redirected to Bristers, April 2026 | Endpoint changed from Yeat to Bristers; estimate $394.71M changed to $384.96M (b4000.345) | p. 15 |
| Thornburg substation (Valley Link) | Thornburg substation b4000.348 listed under VLT VA: $84.41M original, $142.80M updated | p. 14 |
| Cut-in b4000.346 re-designated | b4000.346 ($5.00M), originally awarded to Valley Link Transmission, re-designated to Dominion/Vepco | p. 14 |
| Line #568 cut-in at Thornburg (Dominion, separate tracked row) | b4000.351 and b4000.352, $7.2M, designated entity Dominion; projected in service 9/16/2030 | p. 8 |
| Related supplemental need | Need DOM-2026-0022, need meeting 05/08/2026 | p. 4 |
| Data center requests in the corridor (Dominion need slide) | At least ten new delivery point requests for data center load in the corridor, total requested load approaching 3000 MW | p. 4 |
| Related supplemental project s4032 | 230kV conductor rated 1573 MVA on the same structures from North Anna to Bristers, to serve approximately 3 GW of requested load; $33.75 M, Q4 2030, Engineering | p. 81 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 3, 2024 | Item 11 - Reliability Analysis Update PDF | 2024W1 – Regional Cluster Preferred Solution: 2024-W1-967 | $704.25 M | 6/1/2029 | |
| January 7, 2025 | Item 12 - Reliability Analysis Update PDF | Recommended Solution: 2024-W1-967 | $704.33 M | 6/1/2029 | |
| May 8, 2026 | Item 10 - Reliability Analysis Update PDF | Dominion Transmission Zone: Baseline New 500kV Line North Anna - Thornburg - Bristers | $661.63M | 9/16/2030 | First Read |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Kraken (PJM system-wide): described as new
- Thornburg (DOM): described as new
- Yeat (PJM system-wide): described as new
- Aquia Harbor (DOM)
- Bristers (DOM)
- Elmont (PJM system-wide)
- Ladysmith (DOM)
- Ladysmith (PJM system-wide): expansion described
- North Anna (DOM): expansion described
- North Anna (PJM system-wide)
- Possum Point (PJM system-wide)
- Stafford (DOM)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- Stafford supervisors continue to register opposition to power line project, Fredericksburg Free Press, December 17, 2025. The Fredericksburg Free Press reported that the Stafford County Board of Supervisors unanimously reaffirmed its opposition to an above-ground North Anna-Kraken Loop line, after asking Dominion to bury it, and hired a law firm and explored ways to take part in the State Corporation Commission case.
- New 765 kV Line Ties To Stafford Project, Potomac Local News, February 13, 2026. Potomac Local News reported that the roughly 70-mile North Anna to Bristers 500 kV line would cross roughly 15 to 20 miles of Stafford County on easements of about 300 feet, and that it is separate from but designed to work with the Valley Link 765 kV line.
- Stafford County homeowners battle the proposed 'Kraken' electric transmission, WJLA, June 25, 2026. WJLA reported that Stafford County homeowners object to the route of Dominion's 70-mile line, which would carry 230 kV and 500 kV circuits on shared structures, and that Dominion cites grid reliability as data centers come online.
- They said it was impossible… Stafford residents just stalled the Kraken, Potomac Local News, August 18, 2026. Potomac Local News reported that Dominion confirmed it will file the line with the State Corporation Commission as two applications, North Anna to Thornburg in fall 2026 and Thornburg to Bristers, which includes the Stafford County route, in fall 2027.
Not printed
- No state or county is printed on the cited PJM or Dominion pages for North Anna, Thornburg or Bristers; Virginia locations appear only in the news coverage.
- PJM's pages print no project status such as Engineering for b4000.344 and b4000.345; the status shown is Dominion's description of them as approved baseline projects on its supplemental slide.
- The May 2026 slides do not give a reason for the change of in-service date from 6/1/2029 to 9/16/2030 beyond the scope change.
- The cited pages do not name the designated entity for b4000.347 (North Anna), b4000.353 (Elmont) or b4000.354 (Ladysmith); they are listed as part of proposal 2024-W1-967 only.
- The December 2024 and January 2025 proposal totals ($704.25 M, $704.33 M) include the Kraken (Thornburg) substation, later listed under Valley Link, so they are not directly comparable with the $661.63M line estimate.
- Tracked rows id:b4000.351 (line #568 cut-in at Thornburg) and need:DOM-2026-0022 (230 kV conductor on the same structures) are related but printed under their own titles, so they are cited as facts here, not members.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.