Substation Scout

Patina 765/345 kV, Marysville (Dayton-2025-008)

Dayton-2025-008. Presented by AES Ohio in PJM planning materials (Dayton zone, OH).

$246Mcost estimate as printed p. 7
05/01/2031projected in service p. 7
Conceptualstatus as printed p. 7

Profile

AES Ohio presented this solution for need number Dayton-2025-008 at PJM's February 2026 solution meeting, at an estimated cost of $246 million and a project in-service date of 05/01/2031. (p. 6, p. 7) The project driver is a customer request for service near AES Ohio's Darby Substation in Marysville, Ohio, listed as 270 MW by May 2030, 540 MW by November 2031 and 800 MW by May 2033. (p. 7, p. 6) When the need was first presented in September 2025, the deck listed the full 800 MW for January 2029. (p. 3) The solution is a new 765/345 kV Patina substation cut into the Marysville - Flatlick 765 kV line, estimated at $168 million, and a new 345 kV Weaver substation near the customer site, estimated at $25 million. (p. 7) Two new approximately 5-mile 345 kV lines would join Patina to Weaver for an estimated $46 million, and two 345 kV feeds from Weaver to the customer are estimated at $7 million. (p. 7) AES Ohio lists the status as Conceptual and says two longer 345 kV lines to its Peoria substation were not selected due to higher cost. (p. 7) AES Ohio's later solution deck for its separate Piqua need marks a 345 kV Patina substation upgrade as to be built in future by AEP, while this deck lists constructing Patina among its own items. (p. 7, p. 7)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Patina 765/345 kV substationNew 765 kV/345 kV Patina substation cut into the Marysville (AEP) - Flatlick (AEP) 765 kV line, 750MVA/phase transformers; estimated $168Mp. 7
Weaver 345 kV substationNew 345 kV Weaver substation near the customer site; estimated $25Mp. 7
Patina - Weaver 345 kV linesTwo new ~5-mile single-circuit 345 kV lines from Patina to Weaver; estimated $46Mp. 7
Weaver 345 kV customer feedsTwo 345kV feeds from Weaver to the customer; estimated $7Mp. 7

Details as printed

Project driverCustomer Requestp. 7
Customer request, Darby (Marysville)270 MW by 5/2030, 540 MW by 11/2031, 800 MW by 5/2033p. 6
Need presentedNeed Meeting 9/9/2025p. 3
Original load request800 MW by 1/2029p. 3
Alternative consideredTwo longer 345 kV lines to AES Peoria and expansion of Peoria substation were not selected due to higher costp. 7
Patina in the Piqua deckPatina 345 kV substation upgrade: to be built in future by AEP (Piqua deck)p. 7

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
September 9, 2025Item 07 - Dayton Supplemental Projects PDF not printed1/2029Need Meeting 9/9/2025
February 3, 2026Item 06 - Dayton Supplemental Projects PDF $246M05/01/2031Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first