Patina 765/345 kV, Marysville (Dayton-2025-008)
Dayton-2025-008. Presented by AES Ohio in PJM planning materials (Dayton zone, OH).
Profile
AES Ohio presented this solution for need number Dayton-2025-008 at PJM's February 2026 solution meeting, at an estimated cost of $246 million and a project in-service date of 05/01/2031. (p. 6, p. 7) The project driver is a customer request for service near AES Ohio's Darby Substation in Marysville, Ohio, listed as 270 MW by May 2030, 540 MW by November 2031 and 800 MW by May 2033. (p. 7, p. 6) When the need was first presented in September 2025, the deck listed the full 800 MW for January 2029. (p. 3) The solution is a new 765/345 kV Patina substation cut into the Marysville - Flatlick 765 kV line, estimated at $168 million, and a new 345 kV Weaver substation near the customer site, estimated at $25 million. (p. 7) Two new approximately 5-mile 345 kV lines would join Patina to Weaver for an estimated $46 million, and two 345 kV feeds from Weaver to the customer are estimated at $7 million. (p. 7) AES Ohio lists the status as Conceptual and says two longer 345 kV lines to its Peoria substation were not selected due to higher cost. (p. 7) AES Ohio's later solution deck for its separate Piqua need marks a 345 kV Patina substation upgrade as to be built in future by AEP, while this deck lists constructing Patina among its own items. (p. 7, p. 7)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Patina 765/345 kV substation | New 765 kV/345 kV Patina substation cut into the Marysville (AEP) - Flatlick (AEP) 765 kV line, 750MVA/phase transformers; estimated $168M | p. 7 |
| Weaver 345 kV substation | New 345 kV Weaver substation near the customer site; estimated $25M | p. 7 |
| Patina - Weaver 345 kV lines | Two new ~5-mile single-circuit 345 kV lines from Patina to Weaver; estimated $46M | p. 7 |
| Weaver 345 kV customer feeds | Two 345kV feeds from Weaver to the customer; estimated $7M | p. 7 |
Details as printed
| Project driver | Customer Request | p. 7 |
|---|---|---|
| Customer request, Darby (Marysville) | 270 MW by 5/2030, 540 MW by 11/2031, 800 MW by 5/2033 | p. 6 |
| Need presented | Need Meeting 9/9/2025 | p. 3 |
| Original load request | 800 MW by 1/2029 | p. 3 |
| Alternative considered | Two longer 345 kV lines to AES Peoria and expansion of Peoria substation were not selected due to higher cost | p. 7 |
| Patina in the Piqua deck | Patina 345 kV substation upgrade: to be built in future by AEP (Piqua deck) | p. 7 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| September 9, 2025 | Item 07 - Dayton Supplemental Projects PDF | not printed | 1/2029 | Need Meeting 9/9/2025 | |
| February 3, 2026 | Item 06 - Dayton Supplemental Projects PDF | $246M | 05/01/2031 | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Patina (DAYTON): described as new
- Weaver (DAYTON): described as new
- Darby Substation (DAYTON)
- Flatlick (AEP) Substation (DAYTON)
- Marysville (AEP) (DAYTON)
- Peoria (DAYTON)
Not printed
- The decks describe the requester only as a customer; they do not name it or say what the load is.
- No county is printed for the Patina or Weaver sites.
- The February 2026 deck does not say which utility builds or owns Patina; it lists constructing Patina as an item of this solution, while the May 2026 Piqua deck (Dayton-2025-007) marks the Patina upgrade as to be built in future by AEP.
- No supplemental project (s-number) is printed yet; the latest tracked deck is the February 3, 2026 solution meeting.
- No news article about this program could be opened (searched 2026-11-27).
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.