Northwest Ohio 345kV
Northwest Ohio 345kV Customer Delivery Points & System Reinforcements. Presented by AEP in PJM planning materials (AEP zone, OH).
Profile
AEP presented this program to PJM's Transmission Expansion Advisory Committee for its December 2026 meeting, at a transmission cost estimate of $607.548 million and a projected in-service date of September 26, 2031. (p. 1, p. 33, p. 49) It combines four customer service requests in Lima, Findlay and Van Wert, Ohio with a condition need on the East Lima - Sorenson 345kV line, which AEP describes as mostly 1955-era steel lattice towers. (p. 26, p. 28, p. 29, p. 30) The largest request listed is 1,300 MW at a site south of Maddox Creek station in Van Wert, with 500 MW expected by December 31, 2028 and the remaining 800 MW by the third quarter of 2031. (p. 29) AEP says it considered reconductoring the line with advanced conductor, but that a double circuit rebuild is required to support a proposed total demand of approximately 2.3 GW in northwest Ohio. (p. 49) The plan includes four new 345kV stations (Pyrite, Norse, Lyka and Saidin), an expansion of Maddox Creek, and a $129 million STATCOM at East Lima, the largest single item listed. (p. 36, p. 37) AEP lists the project status as Scoping. (p. 49)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Sorenson - Pyrite 345kV line | Rebuild ~21.2 miles of single circuit 345kV as double circuit; estimated $118 M | p. 33 |
| Maddox Creek - Pyrite 345kV line | String a second circuit, ~21.4 miles; estimated $32 M | p. 33 |
| Maddox Creek - Norse 345kV line | New ~2.5 mile double circuit; estimated $35 M | p. 33 |
| Lyka 345kV extension | New ~5.0 mile double circuit from a cut-in on the Maddox Creek - East Lima line; estimated $29.5 M | p. 34 |
| Pyrite 345kV station | New breaker-and-a-half substation, 10 circuit breakers; estimated $73 M | p. 36 |
| Maddox Creek 345kV station | Expand onto additional property, 8 circuit breakers; estimated $29 M | p. 36 |
| Norse 345kV station | New substation, 14 circuit breakers and 2 capacitor banks; estimated $31.6 M | p. 36 |
| Lyka 345kV station | New station, 10 circuit breakers; estimated $43 M | p. 37 |
| East Lima 345kV station | 150 MVAR STATCOM, station yard expanded; estimated $129 M | p. 37 |
| Saidin 345kV station | New substation, 3 circuit breakers; estimated $27 M | p. 37 |
| Waynedale - Hillcrest - Wayne Trace 138kV line | Line rebuild; estimated $31.048 M | p. 38 |
Details as printed
| Area demand cited | approximately 2.3 GW in the NW OH area | p. 49 |
|---|---|---|
| Customer request, Lima | 500 MW initial, 900 MW ultimate, west of East Lima station in Lima, OH; requested in service 12/31/2028 | p. 26 |
| Customer request, Flag City (Findlay) | 150 MW at 138 kV, northeast of Flag City station in Findlay, OH; requested in service 9/30/2027 | p. 27 |
| Customer request, Findlay | 300 MW near the East Lima-Fostoria Central 345 kV line in Findlay, OH; requested in service 9/30/2028 | p. 28 |
| Customer request, Van Wert | 1,300 MW at 345 kV south of Maddox Creek station in Van Wert, OH; 500 MW by 12/31/2028, remaining 800 MW by Q3 2031 | p. 29 |
| Condition need | East Lima - Sorenson 345kV line: 1955-era double circuit steel lattice towers | p. 30 |
| Alternative considered | Reconductoring with advanced conductor was considered; a rebuild to double circuit is required for the new load additions | p. 49 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| November 6, 2024 | Item 07 - AEP Supplemental Projects PDF | Fort Wayne, IN | not printed | not printed | Need Meeting: 11/6/2024 |
| August 5, 2025 | Item 07 - AEP Supplemental Projects PDF | Maddox Creek, OH/E. Lima, OH | not printed | 12/31/2028 | Need Meeting 08/05/2025 |
| August 5, 2025 | Item 07 - AEP Supplemental Projects PDF | E. Lima, OH/Fostoria Ctl, OH | not printed | 9/30/2028 | Need Meeting 08/05/2025 |
| August 5, 2025 | Item 07 - AEP Supplemental Projects PDF | Maddox Creek, OH | not printed | 12/31/2028 | Need Meeting 08/05/2025 |
| August 15, 2025 | Item 02 - AEP Supplemental Projects PDF | Flag City, OH | not printed | 9/30/2027 | Need Meeting 08/15/2025 |
| August 4, 2026 | Item 06 - AEP Supplemental Projects PDF | Van Wert Area Customer | not printed | not printed | Need Meeting 08/04/2026, previously presented on 08/05/2025 |
| December 1, 2026 | Item 03 - AEP Supplemental Projects - Presentation | Northwest Ohio 345kV Customer Delivery Points & System Reinforcements | $607.548 M | 09/26/2031 | Scoping |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Lyka (AEP): described as new
- Norse (AEP): described as new
- Pyrite (AEP): described as new
- Saidin (AEP): described as new
- Allen (AEP): expansion described
- Bosc 1A & 1B (CUSTOMER) (AEP)
- Bosc 2A & 2B (CUSTOMER) (AEP)
- East Lima (AEP)
- Ebersole (AEP)
- Flag City (AEP)
- Fostoria Central (AEP)
- Hillcrest (AEP)
- Maddox Creek (AEP): expansion described
- North Findlay (AEP)
- Palmer 1 & 2 (CUSTOMER) (AEP)
- Peony 1 & 2 (CUSTOMER) (AEP)
- RP Mone (AEP)
- Sorenson (AEP)
- Valor 1 & 2 (CUSTOMER) (AEP)
- Wayne Trace (AEP)
- Waynedale (AEP)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- Butterfly Meadows, AEP hold open houses, The Van Wert Independent, August 12, 2026. The Van Wert Independent reported on AEP's open house for the Norse substation and the Maddox Creek - Norse line, said AEP did not name the customer, and reported that QTS will be responsible for the cost of the connections between Norse and its planned data center site nearby.
- AEP Ohio Plans New Substation on Google Site to Support Data Centre Power Demand, Transformer Technology, April 22, 2026. Transformer Technology, citing The Lima News, reported that the Lyka substation will be built on customer-owned land in Sugar Creek Township for a customer facility it described as believed to be linked to Google.
Not printed
- The deck names the customers only as Customer; it does not say what the loads are.
- No county is printed for Pyrite, Norse, Lyka or Saidin.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.