Northwest Ohio 345kV

Northwest Ohio 345kV Customer Delivery Points & System Reinforcements. Presented by AEP in PJM planning materials (AEP zone, OH).

$607.548 Mcost estimate as printed p. 49
09/26/2031projected in service p. 49
Scopingstatus as printed p. 49

Profile

AEP presented this program to PJM's Transmission Expansion Advisory Committee for its December 2026 meeting, at a transmission cost estimate of $607.548 million and a projected in-service date of September 26, 2031. (p. 1, p. 33, p. 49) It combines four customer service requests in Lima, Findlay and Van Wert, Ohio with a condition need on the East Lima - Sorenson 345kV line, which AEP describes as mostly 1955-era steel lattice towers. (p. 26, p. 28, p. 29, p. 30) The largest request listed is 1,300 MW at a site south of Maddox Creek station in Van Wert, with 500 MW expected by December 31, 2028 and the remaining 800 MW by the third quarter of 2031. (p. 29) AEP says it considered reconductoring the line with advanced conductor, but that a double circuit rebuild is required to support a proposed total demand of approximately 2.3 GW in northwest Ohio. (p. 49) The plan includes four new 345kV stations (Pyrite, Norse, Lyka and Saidin), an expansion of Maddox Creek, and a $129 million STATCOM at East Lima, the largest single item listed. (p. 36, p. 37) AEP lists the project status as Scoping. (p. 49)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Sorenson - Pyrite 345kV lineRebuild ~21.2 miles of single circuit 345kV as double circuit; estimated $118 Mp. 33
Maddox Creek - Pyrite 345kV lineString a second circuit, ~21.4 miles; estimated $32 Mp. 33
Maddox Creek - Norse 345kV lineNew ~2.5 mile double circuit; estimated $35 Mp. 33
Lyka 345kV extensionNew ~5.0 mile double circuit from a cut-in on the Maddox Creek - East Lima line; estimated $29.5 Mp. 34
Pyrite 345kV stationNew breaker-and-a-half substation, 10 circuit breakers; estimated $73 Mp. 36
Maddox Creek 345kV stationExpand onto additional property, 8 circuit breakers; estimated $29 Mp. 36
Norse 345kV stationNew substation, 14 circuit breakers and 2 capacitor banks; estimated $31.6 Mp. 36
Lyka 345kV stationNew station, 10 circuit breakers; estimated $43 Mp. 37
East Lima 345kV station150 MVAR STATCOM, station yard expanded; estimated $129 Mp. 37
Saidin 345kV stationNew substation, 3 circuit breakers; estimated $27 Mp. 37
Waynedale - Hillcrest - Wayne Trace 138kV lineLine rebuild; estimated $31.048 Mp. 38

Details as printed

Area demand citedapproximately 2.3 GW in the NW OH areap. 49
Customer request, Lima500 MW initial, 900 MW ultimate, west of East Lima station in Lima, OH; requested in service 12/31/2028p. 26
Customer request, Flag City (Findlay)150 MW at 138 kV, northeast of Flag City station in Findlay, OH; requested in service 9/30/2027p. 27
Customer request, Findlay300 MW near the East Lima-Fostoria Central 345 kV line in Findlay, OH; requested in service 9/30/2028p. 28
Customer request, Van Wert1,300 MW at 345 kV south of Maddox Creek station in Van Wert, OH; 500 MW by 12/31/2028, remaining 800 MW by Q3 2031p. 29
Condition needEast Lima - Sorenson 345kV line: 1955-era double circuit steel lattice towersp. 30
Alternative consideredReconductoring with advanced conductor was considered; a rebuild to double circuit is required for the new load additionsp. 49

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
November 6, 2024Item 07 - AEP Supplemental Projects PDFFort Wayne, IN not printednot printedNeed Meeting: 11/6/2024
August 5, 2025Item 07 - AEP Supplemental Projects PDFMaddox Creek, OH/E. Lima, OH not printed12/31/2028Need Meeting 08/05/2025
August 5, 2025Item 07 - AEP Supplemental Projects PDFE. Lima, OH/Fostoria Ctl, OH not printed9/30/2028Need Meeting 08/05/2025
August 5, 2025Item 07 - AEP Supplemental Projects PDFMaddox Creek, OH not printed12/31/2028Need Meeting 08/05/2025
August 15, 2025Item 02 - AEP Supplemental Projects PDFFlag City, OH not printed9/30/2027Need Meeting 08/15/2025
August 4, 2026Item 06 - AEP Supplemental Projects PDFVan Wert Area Customer not printednot printedNeed Meeting 08/04/2026, previously presented on 08/05/2025
December 1, 2026Item 03 - AEP Supplemental Projects - PresentationNorthwest Ohio 345kV Customer Delivery Points & System Reinforcements $607.548 M09/26/2031Scoping

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.