Exelon/PEPCO Cluster
Exelon/PEPCO Cluster. Presented by PJM in PJM planning materials (PEPCO zone).
Profile
The Exelon/PEPCO Cluster is the solution PJM selected in its 2025 Window 1 for 500 kV and 230 kV overloads in the PEPCO zone and on the PEPCO/Dominion tie: proposal 2025-W1-919, a new Dickerson 500/230 kV substation cut into the Aspen - Rocky Point 500 kV line, plus additional upgrades. (p. 60, p. 24, p. 25, p. 58) PJM presented it as a recommended solution at the January 6, 2026 Transmission Expansion Advisory Committee meeting, at an estimated total cost of $282.16 million and a projected in-service date of June 1, 2032; at the December 8, 2025 first read the same cost carried a projected in-service date of June 1, 2031. (p. 1, p. 24, p. 25, p. 1, p. 60) PJM's problem statement places the overloads in the 2032 base case and says they worsen with the NJOSW delay and an additional 3.5 GW of PPL load not included in the 2025 load forecast; PJM attributes the higher transfer into MAAC mainly to load growth in PPL of approximately 5 GW. (p. 24, p. 54) Exelon/PEPCO submitted the only three proposals for the cluster: PJM wrote that proposal 851 ($102 million, reconductoring the BGE portion of Doubs - Brighton 500 kV) does not address all the violations, and that proposal 371 ($857 million, a station plus a 500 kV Dickerson - Brighton line) is the most expensive, requires a greenfield, and that its 500 kV line is no longer needed with the regional MAAC solution in place. (p. 56, p. 58) PJM selected proposal 919, which it says addresses the needs, provides a source to the PEPCO zone and can scale to the future 500 kV line proposed in 371. (p. 58) The new Dickerson station with its two 500/230 kV transformers made up $257.61 million of the first-read total; the rest of the recommended scope is line terminations and remote-end work at Rocky Point and Aspen, a series reactor and a circuit relocation at Dickerson, and equipment replacements at Brighton, Quince Orchard and Bells Mill. (p. 60, p. 25)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| New Dickerson 500/230 kV substation (b4052.1) | New 500/230 kV substation (Dickerson) by cutting into the Aspen - Rocky Point 500 kV line | p. 25 |
| Dickerson transformers (b4052.2) | Install two 500/230 kV transformers connecting the new 500 kV Dickerson station and the Dickerson "H" 230 kV station, including 230 kV substation work | p. 25 |
| Line terminations at Dickerson | Rocky Point - Dickerson and Aspen - Dickerson (new 500 kV) termination work at Dickerson 500 kV | p. 25 |
| Remote-end work at Rocky Point and Aspen | Rocky Point 500 kV and Aspen 500 kV remote-end work for the new Dickerson lines | p. 25 |
| Edwards Ferry - Dickerson series reactor | Install a 3.2% 230 kV series reactor at the Dickerson "H" terminal of the Edwards Ferry - Dickerson circuit | p. 25 |
| Dickerson - Quince Orchard relocation | Relocate Dickerson "D" - Quince Orchard 23035 to terminate at Dickerson "H" | p. 25 |
| Brighton 500 kV equipment | Replace 2 breakers, 1 bushing CT, 1 stranded bus conductor and 4 disconnect switches at Brighton 500 kV substation | p. 25 |
| Quince Orchard 230 kV equipment | Replace 1 stranded bus conductor, 3 thermal relays and 2 disconnect switches at Quince Orchard 230 kV substation | p. 25 |
| Bells Mill transformer | Replace the Bells Mill T3 transformer with a new PEPCO standard 260 MVA 230/138 kV transformer | p. 25 |
Details as printed
| Proposing entity | Exelon/PEPCO, the only entity to submit proposals for this cluster (three proposals) | p. 56 |
|---|---|---|
| Criteria | Baseline Load Growth Deliverability & Reliability | p. 24 |
| Problem statement | Multiple 500kV and 230 kV facilities overloaded in PEPCO and on the PEPCO/Dominion tie in the 2032 RTEP base case, worsened by the NJOSW delay and an additional 3.5 GW of PPL load not in the 2025 load forecast | p. 24 |
| Transfer driver | PJM attributes the increased transfer to MAAC mainly to load growth in PPL (approximately 5 GW) and the delay of NJOSW generation in MAAC | p. 54 |
| Tie lines affected | The increased South-to-MAAC transfer significantly impacts the three tie lines to SWMAAC or PEPCO: Doubs - Brighton 500 kV, Burches Hill - Possum Point 500 kV, Edwards Ferry - Dickerson 230 kV | p. 54 |
| Status, November 2025 | PJM still evaluating the three PEPCO proposals, to finalize by the December TEAC | p. 71 |
| Proposals, November 2025 ($M) | Proposal total costs ($M): 371 857.22; 851 101.86; 919 257.61 | p. 71 |
| First read presented | First read presented at TEAC December 8, 2025 | p. 1 |
| First read, December 2025 | First read: estimated total cost $282.16 M, projected ISD 6/1/2031 | p. 60 |
| Dickerson station, first-read cost | New Dickerson 500 kV substation cut into Aspen - Rocky Point with two new 500/230kV transformers: $257.61M of the first-read total | p. 60 |
| Proposal 851, PJM evaluation | Proposal #851 (reconductor the BGE portion of Doubs - Brighton 500 kV, $102 M) does not address all the violations in the area | p. 58 |
| Proposal 371, PJM evaluation | Proposal #371 (500/230 kV station and 500 kV Dickerson-Brighton line, $857 M): stronger transfer capability, but the most expensive and requires a greenfield; with the regional MAAC solution in place the need for the 500 kV line is eliminated | p. 58 |
| Selection | Proposal #919 (new Dickerson 500/230 kV station tapping the 500 kV Aspen - Rocky Point, $282 M, plus additional upgrades) addresses the needs, provides a source to the PEPCO zone, supports the Doubs 230 kV area, is scalable for the future 500kV line proposed in 371, and is selected by PJM as the more efficient or cost-effective solution | p. 58 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| September 9, 2025 | Item 16 - Reliability Analysis Update PDF | 2025-W1-919 | not printed | not printed | |
| December 8, 2025 | Item 11 - Reliability Analysis Update PDF | PEPCO Transmission Zone: Baseline Exelon/PEPCO Cluster | $282.16 M | 6/1/2031 | First Read |
| January 6, 2026 | Item 09 - Reliability Analysis Update PDF | Exelon/PEPCO Cluster | $282.16 M | 6/1/2032 | Recommended Solution |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Dickerson (PEPCO): described as new
- Aspen (PEPCO)
- Bells Mill (PEPCO)
- Brighton (PEPCO)
- Quince Orchard (PEPCO)
- Rocky Point (PEPCO)
Not printed
- No state or county is printed on the cluster slides, so states is left empty (Dickerson, Quince Orchard and Bells Mill are not given a location in the decks).
- The archived decks do not print a PJM Board approval date; the latest printed stage is Recommended Solution (January 6, 2026). PJM's February 2026 Board whitepaper, which per search results lists b4052.1 and b4052.2 separately, is not in data/rtep-archive and is not cited.
- The January 2026 slide lists baseline IDs b4052.1 to b4052.11 in one column and descriptions in another; only b4052.1 and b4052.2 sit on the same line as their descriptions, so the other components are listed without IDs.
- Per-component costs on the December 2025 slide for the Brighton, Quince Orchard and Bells Mill items (3.75, 12.8, 8) do not line up unambiguously with their rows in the extracted text, so they are not listed.
- The decks do not say why the projected in-service date moved from 6/1/2031 (December 2025) to 6/1/2032 (January 2026).
- No news article about this cluster specifically was found; Utility Dive's February 17, 2026 report on the PJM Board's $11.8 billion approval gives a Pepco total (about $292 million) without naming the cluster or Dickerson, so it is not listed.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.