Substation Scout

Archbald Mountain

Archbald Mountain, PA. Presented by PPL in PJM planning materials (PPL zone, PA).

$220 Mcost estimate as printed p. 7
05/30/2028projected in service p. 7
Project Developmentstatus as printed p. 7

Profile

PPL presented this customer service project to PJM's Transmission Expansion Advisory Committee as a solution in February 2026, at a transmission cost estimate of $220 million and a projected in-service date of May 30, 2028. (p. 1, p. 6, p. 7) The need, first presented in September 2025, is a customer request to serve a facility from a 230kV source in Archbald, Pennsylvania, with a total load of approximately 1,000 MW by 2031 and a requested in-service date of May 2027. (p. 4, p. 6) PPL lists the load ramping from 166 MW at initial in-service in 2027 to 500 MW in 2028 and 900 MW in 2030. (p. 6) The plan centers on a new Archbald Mountain station with a 500kV yard ($78 million, two 750 MVA 500-230kV transformers) and a 230kV switchyard ($50 million), cut into the existing Lackawanna - Hopatcong 500kV and Callender Gap - Paupack 230kV lines. (p. 7) It also includes a ~4.6-mile double circuit 230kV line from Callender Gap to Archbald Mountain and four 230kV lead lines of approximately 4.0 miles to the customer substation, the largest line item at $36 million. (p. 7) PPL says there were no feasible alternatives because the customer site is closest to the existing 500kV and 230kV lines, and lists the project status as Project Development. (p. 7)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Archbald Mountain 500kV yardThree bays of a new 500kV yard with two 750 MVA 500-230kV transformers; estimated $78 Mp. 7
Archbald Mountain 230kV yardSeven bays of new BAAH 230kV switchyard with a 125MVAR capacitor bank; estimated $50 Mp. 7
Callender Gap - Paupack 230kV lineBifurcate into the new Archbald Mountain 230kV switchyard (~0.25 miles); estimated $6 Mp. 7
Lackawanna - Hopatcong 500kV lineBifurcate into the new Archbald Mountain 500kV switchyard (~0.25 miles); estimated $10 Mp. 7
Callender Gap 230kV yard230kV terminals for three 230kV lines; estimated $5 Mp. 7
Sturges 230kV yard230kV terminals for two 230kV lines; estimated $3.5 Mp. 7
Sturges - Callender Gap #2 230kV line2.7 miles of second circuit on the Sturges - Callender Gap #1 pole line (from PPL-2025-013); estimated $3.5 Mp. 7
Lackawanna - Sturges 230kV lineNew 1-mile single circuit 230kV line (from PPL-2025-005); estimated $6 Mp. 7
Callender Gap - Archbald Mountain #2 & #3 230kV linesNew ~4.6-mile double circuit 230kV line; estimated $22 Mp. 7
Archbald Mountain 230kV customer lead linesFour 230kV lead lines, approximately 4.0 miles, to the customer substation; estimated $36 Mp. 7

Details as printed

Need presentedNeed Meeting 9/09/2025p. 4
Project driverCustomer Servicep. 6
Customer request, ArchbaldFacility served from a 230kV source in Archbald, PA; approximately 1,000 MW total (2031); requested in service 05/2027p. 6
Load ramp166 MW initial in-service 2027; 500 MW projected 2028; 900 MW projected 2030p. 6
Alternatives consideredNo feasible alternatives; the customer site is closest to the HOPA-LACK 500kV and CAGA-PAUP 230kV linesp. 7

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
September 9, 2025Item 09 - PPL Supplemental Projects PDFArchbald Mountain, PA not printed05/2027Need Meeting 9/09/2025
February 3, 2026Item 07 - PPL Supplemental Projects PDFArchbald Mountain, PA $220 M05/30/2028Project Development

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.