500kV Line #579 Rebuild (Septa - Yadkin)
500kV Line #579 Rebuild (End of Life Criteria). Presented by PJM in PJM planning materials (Dominion zone).
Profile
PJM Transmission Planning presented this Dominion end-of-life rebuild to the Transmission Expansion Advisory Committee on January 7, 2025 for second review, as recommended solution Proposal 2024-W1-980, at an estimated cost of $216.78 million with required and projected in-service dates of June 1, 2029. (p. 1, p. 53, p. 54) Line #579 is about 33.1 miles of 500kV line from Septa to Yadkin; about 8.4 miles of it carries the 230kV Line #2110 underbuilt on 5-2 Corten towers, and the structures were installed in 1985. (p. 53) The slides say a third party assessment found the towers corroded, with premature thinning of structure members and packout at joints, and that if left unaddressed this could result in failure of structures and potentially collapse of the line; the need is filed under Dominion's FERC 715 end-of-life criteria. (p. 53) The estimate breaks down as $191.25 million to rebuild about 33.09 miles of Line #579, $21.25 million to rebuild about 7.7 miles of Line #2110 Suffolk - Thrasher on the shared towers, and $3.84 million and $0.44 million for upgrades at Septa and Yadkin substations. (p. 54) The slides list the line's existing summer normal rating as 3426 MVA and a preliminary rating of 4357 MVA after the rebuild. (p. 53, p. 54) VEPCO's window proposal 980 was listed at $216.7 million in PJM's November 6, 2024 deck, and PJM showed $216.78 million at first review on December 3, 2024 and again at second review in January 2025. (p. 70, p. 1, p. 1, p. 74, p. 1, p. 54)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| b3929.1 Line #579 rebuild | Rebuild approx. 33.09 miles of 500kV Line #579, Septa to Yadkin; $191.25M | p. 54 |
| b3929.4 Line #2110 rebuild | Rebuild approx. 7.7 miles of 230kV Line #2110 Suffolk - Thrasher on the shared towers; $21.25M | p. 54 |
| b3929.2 Septa substation | Breaker, breaker switches and line leads upgraded to 5000A; $3.84M | p. 54 |
| b3929.3 Yadkin substation | Line leads upgraded to 5000A; $0.44M | p. 54 |
Details as printed
| Required in-service | 6/1/2029 (required) | p. 54 |
|---|---|---|
| Recommended solution | Recommended solution: Proposal 2024-W1-980 | p. 54 |
| Criteria | Dominion's FERC 715 Planning Criteria (C.2.9 - End of Life Criteria) | p. 53 |
| Condition | About 33.1 miles of 500kV line from Septa to Yadkin; about 8.4 miles carries 230kV Line #2110 underbuilt on 5-2 Corten towers; structures installed in 1985 | p. 53 |
| Third party assessment | Third party assessment: towers corroded, with premature thinning of members and packout at joints; could result in failure of structures and potentially collapse of the line | p. 53 |
| Existing rating | Existing rating 3426/3426/3984/4018 MVA (SN/SE/WN/WE) | p. 53 |
| Preliminary rating after rebuild | Preliminary rating 4357/4357/5155/5155 MVA (SN/SE/WN/WE) | p. 54 |
| First review meeting | First Review, TEAC December 3, 2024 | p. 1 |
| Cost at first review | $216.78 M at first review | p. 74 |
| 2024 Window 1 proposal | Window proposal 980 (VEPCO, cluster DOM - 1): Line #579 EOL Rebuild_Septa to Yadkin, $216.7M | p. 70 |
| Proposal listing meeting | TEAC November 6, 2024 | p. 1 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 3, 2024 | Item 11 - Reliability Analysis Update PDF | 500kV Line #579 Rebuild (End of Life Criteria) | $216.78 M | 6/1/2029 | First Review |
| January 7, 2025 | Item 12 - Reliability Analysis Update PDF | 500kV Line #579 Rebuild (End of Life Criteria) | $216.78 M | 6/1/2029 | Second Review |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
Not printed
- No state, county or city is printed on the cited pages (Suffolk appears only as a station name).
- The decks print no project status beyond the review stage; PJM Board approval of b3929 is not in the archived decks.
- No news article about the Line #579 (Septa - Yadkin) rebuild was found; only Dominion's own project page and PJM's redacted proposal turned up.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.