500kV Line #579 Rebuild (Septa - Yadkin)

500kV Line #579 Rebuild (End of Life Criteria). Presented by PJM in PJM planning materials (Dominion zone).

$216.78 Mcost estimate as printed p. 54
6/1/2029projected in service p. 54
Second Reviewstatus as printed p. 53

Profile

PJM Transmission Planning presented this Dominion end-of-life rebuild to the Transmission Expansion Advisory Committee on January 7, 2025 for second review, as recommended solution Proposal 2024-W1-980, at an estimated cost of $216.78 million with required and projected in-service dates of June 1, 2029. (p. 1, p. 53, p. 54) Line #579 is about 33.1 miles of 500kV line from Septa to Yadkin; about 8.4 miles of it carries the 230kV Line #2110 underbuilt on 5-2 Corten towers, and the structures were installed in 1985. (p. 53) The slides say a third party assessment found the towers corroded, with premature thinning of structure members and packout at joints, and that if left unaddressed this could result in failure of structures and potentially collapse of the line; the need is filed under Dominion's FERC 715 end-of-life criteria. (p. 53) The estimate breaks down as $191.25 million to rebuild about 33.09 miles of Line #579, $21.25 million to rebuild about 7.7 miles of Line #2110 Suffolk - Thrasher on the shared towers, and $3.84 million and $0.44 million for upgrades at Septa and Yadkin substations. (p. 54) The slides list the line's existing summer normal rating as 3426 MVA and a preliminary rating of 4357 MVA after the rebuild. (p. 53, p. 54) VEPCO's window proposal 980 was listed at $216.7 million in PJM's November 6, 2024 deck, and PJM showed $216.78 million at first review on December 3, 2024 and again at second review in January 2025. (p. 70, p. 1, p. 1, p. 74, p. 1, p. 54)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
b3929.1 Line #579 rebuildRebuild approx. 33.09 miles of 500kV Line #579, Septa to Yadkin; $191.25Mp. 54
b3929.4 Line #2110 rebuildRebuild approx. 7.7 miles of 230kV Line #2110 Suffolk - Thrasher on the shared towers; $21.25Mp. 54
b3929.2 Septa substationBreaker, breaker switches and line leads upgraded to 5000A; $3.84Mp. 54
b3929.3 Yadkin substationLine leads upgraded to 5000A; $0.44Mp. 54

Details as printed

Required in-service6/1/2029 (required)p. 54
Recommended solutionRecommended solution: Proposal 2024-W1-980p. 54
CriteriaDominion's FERC 715 Planning Criteria (C.2.9 - End of Life Criteria)p. 53
ConditionAbout 33.1 miles of 500kV line from Septa to Yadkin; about 8.4 miles carries 230kV Line #2110 underbuilt on 5-2 Corten towers; structures installed in 1985p. 53
Third party assessmentThird party assessment: towers corroded, with premature thinning of members and packout at joints; could result in failure of structures and potentially collapse of the linep. 53
Existing ratingExisting rating 3426/3426/3984/4018 MVA (SN/SE/WN/WE)p. 53
Preliminary rating after rebuildPreliminary rating 4357/4357/5155/5155 MVA (SN/SE/WN/WE)p. 54
First review meetingFirst Review, TEAC December 3, 2024p. 1
Cost at first review$216.78 M at first reviewp. 74
2024 Window 1 proposalWindow proposal 980 (VEPCO, cluster DOM - 1): Line #579 EOL Rebuild_Septa to Yadkin, $216.7Mp. 70
Proposal listing meetingTEAC November 6, 2024p. 1

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 3, 2024Item 11 - Reliability Analysis Update PDF500kV Line #579 Rebuild (End of Life Criteria) $216.78 M6/1/2029First Review
January 7, 2025Item 12 - Reliability Analysis Update PDF500kV Line #579 Rebuild (End of Life Criteria) $216.78 M6/1/2029Second Review

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.