Substation Scout

Jeffersonville, Wilmington

Jeffersonville, Wilmington, OH. Presented by AES Ohio in PJM planning materials (Dayton zone, OH).

$589.8Mcost estimate as printed p. 13
01/2031projected in service p. 13
Engineeringstatus as printed p. 13

Profile

AES Ohio presented this program in PJM's Dayton transmission zone under need numbers Dayton-2025-001 and Dayton-2025-002, and submitted it for inclusion in the local plan on September 15, 2026 at a total estimated transmission cost of $589.8 million and a projected in-service date of January 2031. (p. 10, p. 12, p. 13) The project driver is customer requests: one near AES Ohio's Fayette Substation in Jeffersonville, Ohio, rising from 35 MW in September 2026 to 1.5 GW by January 2031, and one near its Clinton Substation near Wilmington, Ohio, rising from 35 MW in January 2028 to 500 MW by January 2030. (p. 12, p. 3, p. 4) The selected solution expands the Fayette and Clinton 345 kV substations, reconfigures the Atlanta 345kV substation, and builds an approximately 25-mile double circuit 345 kV line from Atlanta to Fayette, the largest item at $220.7 million, and an approximately 27-mile single circuit from Clinton to Fayette at $187 million. (p. 12, p. 5) Customer service lines from Fayette and Clinton and the relocation of two existing 345 kV lines make up the rest, listed as supplemental projects s3898.1 through s3898.9. (p. 12, p. 13) The solution was first presented in April 2025 at $480 million with status Conceptual; a July 2026 update raised the total to $589.8 million, moved the Atlanta - Fayette line from September 2030 to April 2029 and the Clinton - Fayette line from December 2031 to January 2030, and changed the status to Engineering. (p. 5, p. 6, p. 5, p. 6, p. 13) AES Ohio's notes attribute the cost change to real estate and the schedule changes to project capability rather than a customer request, and say engineering studies of voltage stability led it to replace a planned static VAR compensator with a capacitor and STATCOM combination. (p. 6, p. 13)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Fayette 345 kV substationExpand to breaker-and-a-half; 300-MVAR capacitor; estimated $51.9M (s3898.1)p. 12
Atlanta 345 kV substationReconfigure to breaker-and-a-half; estimated $24.3M (s3898.2)p. 12
Atlanta - Fayette 1 & 2 345 kV lineNew ~25-mile 345 kV double circuit; projected ISD 04/13/2029; estimated $220.7M (s3898.3)p. 12
Fayette customer service lines 1-4Four ~0.5-mile 345 kV feeds to the customer substations; estimated $9 M (s3898.4)p. 12
Clinton 345 kV substationExpand for the new line, 2 customer feeds, a 300-MVAR capacitor and a 150-MVAR STATCOM; estimated $65.4M (s3898.5)p. 12
Clinton - Fayette 345 kV lineNew ~27-mile 345 kV single circuit; projected ISD 01/18/2030; estimated $187 M (s3898.6)p. 12
Clinton customer service lines 1 & 2Two ~2-mile 345 kV feeds to the customer substation; estimated $20 M (s3898.7)p. 13
Clinton - Clay 345 kV relocationRelocate the existing line; estimated $3.2 M (s3898.8)p. 13
Clinton - Greene 345 kV relocationRelocate the existing line; estimated $8.3M (s3898.9)p. 13

Details as printed

Supplemental project IDss3898.1 - .9p. 13
Project driverCustomer Requestp. 12
Customer request, Fayette (Jeffersonville)35 MW by 9/2026, 480 MW by 9/2028, 1.5 GW by 1/2031, near Fayette Substation in Jeffersonville, OHp. 3
Customer request, Clinton (Wilmington)35 MW by 1/2028, 100 MW by 4/2028, 300 MW by 1/2029, 500 MW by 1/2030, near Clinton Substation near Wilmington, OHp. 4
Need presentedNeed Meeting 2/04/2025p. 3
Solution presentedSolution Meeting, 04/01/2025p. 5
Original estimate$480 M, projected in service 01/2031, status Conceptualp. 6
Solution updateSolution Meeting 7/7/2026 (update)p. 5
Cost update$480 M updated to $589.8 M; status Conceptual updated to Engineeringp. 6
Reason for cost changeCost changes attributed to real estatep. 6
Reason for schedule changeSchedule changes based on project capability, not at the request of the customerp. 6
Reason for scope changeEngineering studies on voltage stability changed the planned SVC to a capacitor and STATCOM combinationp. 13
Atlanta - Fayette line, July 2026 updateAtlanta - Fayette line: projected ISD 9/1/2030 moved to 04/13/2029; estimate $192 M updated to $220.7Mp. 5
Clinton - Fayette line, July 2026 updateClinton - Fayette line: projected ISD 12/1/2031 moved to 01/18/2030; estimate $100M updated to $187 Mp. 5
Alternative consideredA second Clinton - Fayette circuit was not selected; a Static VAR Compensator at Clinton was more cost effectivep. 13
Alternative consideredA single Atlanta - Fayette circuit was not selected; it would need significant reactive support and causes overloads on the nearby AEP systemp. 13

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
February 4, 2025Item 07 - Dayton Supplemental Projects PDF not printed1/2031Need Meeting 2/04/2025
February 4, 2025Item 07 - Dayton Supplemental Projects PDF not printed1/2030Need Meeting 2/04/2025
April 1, 2025Item 06 - Dayton Supplemental Projects PDF $480 M01/2031Conceptual
May 6, 2025Item 05 - Dayton Supplemental Projects PDFDayton Transmission Zone M-3 Process $480 M01/2031Conceptual
July 7, 2026item 11 - Dayton Supplemental Projects PDFDayton Transmission Zone M-3 Process $589.8 M01/2031Engineering
October 6, 2026Informational Only - Dayton Local Plan Submission of the supplemental projects for 2026 PDFDayton Transmission Zone M-3 Process $589.8 M01/2031Engineering
Date not printedDayton&nbsp PDFDayton Transmission Zone M-3 Process Jeffersonville, Wilmington, OH $589.8 M01/2031Engineering

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first