Substation Scout

Big Bass 230kV Switchyard

Big Bass, PA. Presented by PPL in PJM planning materials (PPL zone, PA).

$186.875 Mcost estimate as printed p. 59
05/30/2028projected in service p. 59
Conceptualstatus as printed p. 59

Profile

PPL presented this customer service project to PJM's Transmission Expansion Advisory Committee as a solution in September 2025, at a transmission cost estimate of $186.875 million and a projected in-service date of May 30, 2028. (p. 1, p. 10, p. 9, p. 59) The need, first presented in July 2025 under the title Pocono Area, is a customer request to serve a facility from a 230kV source in Gouldsboro, Pennsylvania, with a total load of approximately 1,500 MW by 2030 and a requested in-service date of May 2027. (p. 3, p. 52) PPL lists the load ramping from 300MW at initial in-service in 2027 to 700MW in 2028 and 1,500MW in 2030. (p. 52) The plan centers on a new six bay Big Bass 230kV switchyard with two 125MVAR capacitor banks ($50 million), cut into the Acahela - Pocono 230kV line (~0.25 miles, $3 million), with six 230kV lead lines of about 0.2 miles to the customer's two substations ($8 million). (p. 27) It adds second circuits on existing single circuit, future double circuit lines: Jenkins - Acahela (15 miles, $18.75 million), Acahela - Big Bass (12.9 miles, $16.125 million), Big Bass - Pocono (7.25 miles, $9.1 million) and Paupack - Pocono (21.75 miles, $27.5 million). (p. 27) It also adds subconductors on the 500kV designed sections of the Lackawanna - Callender Gap (~3 miles, $7.75 million) and Callender Gap - Paupack (~17.1 miles, $31.1 million) 230kV lines, plus bay and breaker work at Jenkins, Acahela, Pocono, Paupack and Lackawanna. (p. 27) PPL submitted the project for its 2026 Local Plan in May 2026 and again, under the title Big Bass 230kV Switchyard, on September 17, 2026, with the same $186.875 million estimate and May 30, 2028 in-service date; the status is listed as Conceptual. (p. 26, p. 52, p. 53, p. 59) PPL lists one alternative, which included a new 500-230kV yard and ~21 miles of greenfield double circuit 230kV line, at an estimated ~$255 million; the same customer later requested a third 230kV delivery point with an additional 700MW of load, which PPL presented as the separate Tamarack project. (p. 59, p. 5)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Big Bass 230kV switchyardSix bay BAAH 230kV switchyard with two 125MVAR capacitor banks; estimated $50 Mp. 27
Big Bass 230kV customer lead linesThree 230kV lead lines of approximately 0.2 miles to each of the customer's two substations (six lines total); estimated $8 Mp. 27
Jenkins 230kV substationBuild out bay #2 with one new 230kV breaker and two MODs; estimated $1.25 Mp. 27
Jenkins - Palooka 230kV lineRe-terminate from bay 3 to bay 2 at Jenkins; estimated $1 Mp. 27
New Jenkins - Acahela 230kV lineSecond circuit on existing single circuit, future double circuit sections between Jenkins and Acahela (15 miles); estimated $18.75 Mp. 27
Acahela 230kV substationNew DBDB (BAAH ultimate) bay and build-out of bay #3; estimated $3.75 Mp. 27
Acahela - Pocono 230kV lineBifurcate into the new Big Bass 230kV switchyard (~0.25 miles); estimated $3 Mp. 27
New Acahela - Big Bass #2 230kV lineSecond circuit between Acahela and Big Bass (12.9 miles); estimated $16.125 Mp. 27
New Big Bass - Pocono #2 230kV lineSecond circuit between Big Bass and Pocono (7.25 miles); estimated $9.1 Mp. 27
Pocono 230kV substationNew DBDB (BAAH ultimate) bay and build-out of bay #3; estimated $3.75 Mp. 27
New Paupack - Pocono #2 230kV lineSecond circuit between Paupack and Pocono (21.75 miles); estimated $27.5 Mp. 27
Paupack 230kV substationBuild out bay #2 with one new 230kV breaker; replace four MODs in bay 3; estimated $2.9 Mp. 27
Lackawanna - Callender Gap 230kV lineAdd two subconductors per phase in the 500kV designed section (~3 miles) and rebuild the ~0.5 mile 230kV designed section; estimated $7.75 Mp. 27
Lackawanna 230kV substationReplace two 230kV breakers and four MODs in bay #3; estimated $2.9 Mp. 27
Callender Gap - Paupack 230kV lineAdd two subconductors per phase in the 500kV designed section (~17.1 miles) and reconductor the ~0.9 mile 230kV designed section; estimated $31.1 Mp. 27

Details as printed

First local plan submissionSubmission of Supplemental Project for inclusion in the Local Plan 05/08/2026, under the title Big Bass, PAp. 26
Need presentedNeed Meeting 07/08/2025, under the title Pocono Areap. 3
Solution presentedSolution Meeting TEAC - 09/09/2025; the solution slide is titled Tresckow, PAp. 10
Project driverCustomer Servicep. 9
Customer request, GouldsboroFacility served from a 230kV source in Gouldsboro, PA; approximately 1,500 MW total (2030); requested in service 05/2027p. 52
Load ramp300MW initial in-service 2027; 700MW projected 2028; 1,500MW projected 2030p. 52
Alternative consideredBifurcate the ACAH-POCO 230kV line and install a new 230kV switchyard; rebuild Blooming Grove 230kV yard to BAAH and install a new 500-230kV yard with two transformers; extend ~21 miles of greenfield double circuit 230kV to the new switchyard; estimated ~$255 Millionp. 59
Same customer, third delivery point (Tamarack)The customer associated with PPL-2025-0012 later requested a third 230kV delivery point with an additional 700MW of load (need PPL-2026-0056, Tamarack 500-230kV Substation)p. 5

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
July 8, 2025Item 06 - PPL Supplemental Projects PDFPPL Transmission Zone M-3 Process Pocono Area not printed05/2027Need Meeting 07/08/2025
September 9, 2025Item 09 - PPL Supplemental Projects PDFBig Bass, PA $186.875 M05/30/2028Solution Meeting TEAC - 09/09/2025
October 6, 2026Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 PDFBig Bass, PA $186.875 M05/30/2028Conceptual
Date not printedPPL&nbsp PDFBig Bass, PA $186.875 M05/30/2028Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.