Pike, Mingo, McDowell & Buchanan 69kV
Pike County, KY and Mingo & McDowell Counties, WV Buchanan County, VA. Presented by AEP in PJM planning materials (AEP zone, KY, WV, VA).
Profile
AEP submitted this program for Pike County, Kentucky, Mingo and McDowell counties, West Virginia and Buchanan County, Virginia for inclusion in its 2024 Local Plan, with a submission date of 2/20/2024, a total estimated transmission cost of $182.56 million and a projected in-service date of 6/1/2030. (p. 1, p. 21, p. 23, p. 24, p. 20) One solution answers seven needs: six on equipment condition, covering old 46 kV and 69 kV lines and the Barrenshe, Sprigg and Hurley stations, and one customer service request from AEP Distribution for a new Tug Fork delivery point to serve initially 5 MVA. (p. 21, p. 9, p. 18, p. 10, p. 12) The three lines named in the needs list original install dates from 1925 to 1930, and the Jim Branch - Wharncliffe 46 kV line's permanent outages caused 2.62 million minutes of interruption for 11,744 customers at Panther and Hardy. (p. 14, p. 10, p. 12) The plan builds new 69 kV lines from Coleman through Peter Creek to Wharncliffe and from Wharncliffe through Tug Fork to Lester Fork, upgrades Wharncliffe to 69 kV, and rebuilds Sprigg as a four-breaker 138 kV ring bus. (p. 21, p. 22) New distribution stations at Peter Creek, Bear Creek, Tug Fork and Lester Fork would replace Barrenshe, Grapevine, Hardy, Panther and Hurley, and AEP says the project retires roughly 40 miles of 46 kV line and replaces it with 31 miles. (p. 23, p. 24) The needs were first presented in 2022 and 2023 and the solution in August 2023; the 2024 deck prints the total as $178.66 M followed by $182.56 M, and the Sprigg Station item as $1.1 M followed by $5M. (p. 9, p. 19, p. 23, p. 22, p. 21) AEP lists the project status as Scoping; an AEP deck from September 2026, on a different need, still refers to the future Peter Creek station replacing Barrenshe. (p. 24, p. 12)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Coleman - Peter Creek 69kV line | New 69kV line with OPGW, Coleman to Peter Creek, 5.8 miles; estimated $19.2 M | p. 21 |
| Peter Creek - Wharncliffe 69kV line | New 69kV line with OPGW from the KY/WV state line to Wharncliffe via Bear Creek, with switching structures Devil Anse and Briar Mt.; 12.7 miles; estimated $44.7 M | p. 21 |
| Tug Fork - Wharncliffe 69kV line | New single circuit 69kV line with OPGW, Wharncliffe to Tug Fork, 5.9 miles; estimated $24.3 M | p. 21 |
| Lester Fork - Tug Fork 69kV line | New single circuit 69kV line with OPGW, Lester Fork to Tug Fork across the VA/WV border, 8.0 miles, greenfield ROW; estimated $33.9 M | p. 21 |
| Wharncliffe Station | Upgrade Wharncliffe station to 69kV: 11.5 MVAR capacitor bank, 69/46kV 50 MVA transformer; estimated $5.9 M | p. 21 |
| Sprigg - Wharncliffe 46kV removal | Remove about 18.3 miles of Sprigg - Wharncliffe 46kV line in WV and the Grapevine switching structure; estimated $14.2 M | p. 22 |
| Jim Branch - Wharncliffe 46kV removal | Remove about 19.7 miles of Jim Branch - Wharncliffe 46kV line; estimated $15.3 M | p. 22 |
| Sprigg Station | Rebuild Sprigg as a four 138kV circuit breaker ring bus station | p. 22 |
| Peter Creek Station (distribution cost) | New distribution station replacing Barrenshe | p. 23 |
| Bear Creek Station (distribution cost) | New distribution station replacing Grapevine | p. 23 |
| Tug Fork Station (distribution cost) | New distribution station replacing Hardy and Panther | p. 23 |
| Lester Fork Station (distribution cost) | New distribution station replacing Hurley | p. 23 |
| Lester Fork - Wharncliffe Fiber | Fiber transitions at Tug Fork, Wharncliffe and Lester Fork and OPGW on 2.3 miles of reused line; estimated $5.1 M | p. 23 |
Details as printed
| Previously presented | Solutions Meeting 8/18/2023; Need Meeting 2/18/2022 | p. 9 |
|---|---|---|
| Need meeting, Tug Fork delivery point | Need Meeting 4/22/2022 (Tug Fork delivery point need) | p. 18 |
| Need meeting, Hurley station | Need Meeting 4/21/2023 (Hurley station need) | p. 19 |
| Supplemental project ID | s3147.1-.41 | p. 24 |
| Project driver | Equipment Condition/Performance/Risk | p. 9 |
| Customer service need, Tug Fork | Customer Service: AEP Distribution requested a new delivery point (Tug Fork) to serve initially 5 MVA | p. 18 |
| Need, Barrenshe station | Barrenshe station lies in the 100 year flood plain; expansion at the existing site is extremely difficult | p. 9 |
| Need, Coleman - Sprigg 69 kV | Coleman - Sprigg 69 kV: installed 1926 | p. 10 |
| Need, Sprigg - Wharncliffe 46 kV | Sprigg - Wharncliffe 46 kV: installed 1929 | p. 12 |
| Need, Jim Branch - Wharncliffe 46 kV | Installed 1925 and 1930, ~25 mi, 162 structures | p. 14 |
| Outages, Jim Branch - Wharncliffe | Permanent outages caused 2.62M minutes of interruption for 11,744 customers at Panther and Hardy | p. 14 |
| Need, Sprigg station | Sprigg station: 82 electromechanical and 3 static relays | p. 16 |
| Need, Hurley station | Hurley station: in the 100-year floodplain, flooded most recently in 2021 | p. 19 |
| Ancillary benefits | Retires roughly 40 miles of legacy 46kV lines and replaces them with 31 miles; looped service for the customer served from the old Hurley station | p. 24 |
| Sprigg Station cost as printed | Sprigg Station rebuild printed as $1.1 M followed by $5M | p. 22 |
| Later mention, September 2026 | A later AEP deck, on a different need, refers to the future Peter Creek station that is replacing the existing Barrenshe station | p. 12 |
| Later deck | SRRTEP-W - 09/18/2026 - AEP | p. 12 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| October 8, 2024 | Informational Only - AEP Local Plan submission of supplemental projects 2024 PDF | Pike County, KY, Mingo & McDowell Counties, WV, Buchanan County, VA | $182.56 M | 6/1/2030 | Scoping |
| Date not printed | AEP  PDF | Pike County, KY and Mingo & McDowell Counties, WV Buchanan County, VA | $182.56 M | 6/1/2030 | Scoping |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Bear Creek (AEP): described as new
- Lester Fork (AEP): described as new
- Peter Creek (AEP): described as new
- Tug Fork (AEP): described as new
- Barrenshe (AEP)
- Bens Creek (AEP)
- Briar Mountain (AEP)
- Briar Mt. (AEP)
- Coleman (AEP)
- Devil Anse (AEP)
- Grapevine (AEP)
- Hardy (AEP)
- Hurley (AEP)
- Jim Branch (AEP)
- Lester Creek (AEP)
- Looney Creek (AEP)
- Panther (AEP)
- Rapoca (AEP)
- Sprigg (AEP)
- Wharncliffe (AEP): expansion described
Not printed
- The deck does not say which of the two printed totals ($178.66 M, $182.56 M) is current; the text layer carries both with no strike-through marker. The record uses the second, as with the Sprigg Station item ($1.1 M, then $5M).
- No archived PJM deck after the 2024 Local Plan prints a cost, in-service date or status for s3147; the September 2026 mention of Peter Creek is under a different need (AEP-2026-AP003).
- The 2022 need meetings and the 8/18/2023 solution meeting decks are not in the archive.
- The deck names no customer other than AEP Distribution.
- No news article about this program could be found and opened; none is listed.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.