ComEd MISO Tranche 2.1
MISO Tranche 2.1 Request. Presented by ComEd in PJM planning materials (ComEd zone, Illinois).
Profile
ComEd listed the MISO Tranche 2.1 Request in its 2026 Local Plan submission of supplemental projects as project s3843, at an estimated transmission cost of $908.7 million and a projected in-service date of June 1, 2034. (p. 7, p. 1) The driver is listed as an external utility request: ComEd says MISO's draft MTEP24 Appendix A for its Long Range Transmission Planning Tranche 2.1 portfolio identified work in the ComEd zone needed to accommodate the MISO projects, and assigned that work to PJM transmission owners. (p. 6) MISO asked for two new 765kV lines out of ComEd's Collins 765kV substation and an expansion of Collins to take them; the selected solution adds bus positions, two 300 MVAR line reactors and two spare reactors at Collins, a line toward the Illinois/Wisconsin state border, and a line segment toward a new MISO Woodford County 765kV substation. (p. 6, p. 7) It also cuts the Powerton-Katydid and Powerton-Nevada 345kV lines into Woodford County, replaces oil circuit breakers at Powerton, Zion and Des Plaines, and mitigates a sag limit on the Zion-Paris 345kV line. (p. 7) The cost shown is MISO's Appendix A figure, and the slides say the costs will be allocated 100% to MISO customers. (p. 7) The estimate was $874.2 million at the March 2025 solutions meeting and $908.7 million at the November 2025 meeting, whose slide adds the breaker replacements and the Zion-Paris sag work that the March 2025 slide does not list. (p. 8, p. 10, p. 6, p. 7) At the December 2024 need meeting MISO's requested in-service date was June 1, 2033; from March 2025 on it is June 1, 2034, and ComEd lists the project status as Conceptual. (p. 3, p. 7, p. 6, p. 7)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Collins 765kV substation | Expand and reconfigure: bus positions for two new 765kV lines, two 300 MVAR line reactors with dedicated breakers, two single-phase spare 765kV reactors | p. 7 |
| Collins - Illinois/Wisconsin border 765kV line | New 765kV line from Collins to an interconnection point with MISO near the Illinois/Wisconsin state border | p. 7 |
| Collins - Woodford County 765kV line segment | Segment of a new 765kV line from Collins to a new 765kV Woodford County substation; MISO interconnection point to be determined | p. 7 |
| Powerton 345kV line cut-ins | Cut the Powerton-Katydid and Powerton-Nevada 345kV lines into the new Woodford County substation (MISO) | p. 7 |
| Powerton 345kV breaker | Replace BT 5-6 oil circuit breaker; 2000 A, 40 kA to 3000 A, 63 kA | p. 7 |
| Zion 345kV breakers | Replace BT 5-6 and BT 17-18 oil circuit breakers; 2000 A, 50 kA to 3000 A, 63 kA | p. 7 |
| Des Plaines 345kV breakers | Replace six oil circuit breakers (BT 1-5, BT 2-5, BT 2-3, L4620, L4621, L12006); 2000 A, 40 kA to 3000 A, 63 kA | p. 7 |
| Zion - Paris 345kV line | Mitigate sag limit on the Zion-Paris (ATC) 345 kV line and replace the line trap at Zion | p. 7 |
| Remote end work, Lakeview (MISO) | Remote end coordination for cutting the Paris-Zion and Pleasant Prairie-Zion 345kV lines into Lakeview substation (MISO) | p. 7 |
| Remote end work, Babcock | Remote end coordination for cutting the Olive-University Park and Olive-Green Acres 345kV lines into Babcock substation | p. 7 |
Details as printed
| Supplemental project ID | s3843 | p. 7 |
|---|---|---|
| Previously presented | Solutions meetings 3/4/2025 and 11/4/2025; need meeting 12/3/2024 | p. 6 |
| Project driver | Other (external public utilities and/or government requests) | p. 6 |
| Problem statement | MISO's draft MTEP24 Appendix A for the LRTP Tranche 2.1 Portfolio identified work in PJM impacting the ComEd zone, assigned to PJM Transmission Owners | p. 6 |
| MISO request | MISO requested two new 765kV lines from Collins and an expansion of Collins to accommodate them | p. 6 |
| Requested in-service, need meeting | MISO requested in-service 6/1/2033 | p. 3 |
| Requested in-service, solutions meeting | MISO requested in-service 6/1/2034 | p. 7 |
| Estimate, March 2025 | $874.2M (MISO Appendix A cost) | p. 8 |
| Estimate, November 2025 | $874.2M revised to $908.7M | p. 10 |
| Cost note | MISO Appendix A cost; costs, including any projects from the no-harm analysis, allocated 100% to MISO customers | p. 7 |
| Model | MISO MTEP 2032 | p. 7 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 3, 2024 | Item 07 - ComEd Supplemental Projects PDF | ComEd Transmission Zone M-3 Process | not printed | 6/1/2033 | Need Meeting 12/3/2024 |
| March 4, 2025 | Item 11 - ComEd Supplemental Projects PDF | MISO Tranche 2.1 Request | $874.2M* | 6/1/2034 | Conceptual |
| November 4, 2025 | Item 11 - ComEd Supplemental Projects PDF | MISO Tranche 2.1 Request | $908.7M | 6/1/2034 | Conceptual |
| October 6, 2026 | Informational Only - ComEd Local Plan Submission of Supplemental Projects for 2026 PDF | MISO Tranche 2.1 Request | $908.7M | 6/1/2034 | Conceptual |
| Date not printed | Comed  PDF | MISO Tranche 2.1 Request | $908.7M | 6/1/2034 | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Woodford County (COMED): described as new
- Babcock (COMED)
- Collins (COMED): expansion described
- Des Plaines (COMED)
- Green Acres (COMED)
- Katydid (COMED)
- Lakeview (COMED)
- Nevada (COMED)
- Olive (COMED)
- Paris (COMED)
- Pleasant Prairie (COMED)
- Powerton (COMED)
- University Park (COMED)
- Zion (COMED)
Not printed
- No news article about ComEd's part of this work (Collins expansion, s3843) was found; coverage found is about MISO's competitive Tranche 2.1 projects (WIIL, STIW, BECI) and their developers, which these slides do not name.
- The slides print no county for Collins or Woodford County, and no line mileage.
- Wisconsin appears only as the state border near the MISO interconnection point and as a map label; no ComEd work is placed in Wisconsin.
- The December 2024 need slide gives no cost estimate.
- No per-component cost breakdown is printed; the only figure is the MISO Appendix A total.
- The slides do not say what changed the estimate from $874.2M to $908.7M.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.