ComEd MISO Tranche 2.1

MISO Tranche 2.1 Request. Presented by ComEd in PJM planning materials (ComEd zone, Illinois).

$908.7Mcost estimate as printed p. 7
6/1/2034projected in service p. 7
Conceptualstatus as printed p. 7

Profile

ComEd listed the MISO Tranche 2.1 Request in its 2026 Local Plan submission of supplemental projects as project s3843, at an estimated transmission cost of $908.7 million and a projected in-service date of June 1, 2034. (p. 7, p. 1) The driver is listed as an external utility request: ComEd says MISO's draft MTEP24 Appendix A for its Long Range Transmission Planning Tranche 2.1 portfolio identified work in the ComEd zone needed to accommodate the MISO projects, and assigned that work to PJM transmission owners. (p. 6) MISO asked for two new 765kV lines out of ComEd's Collins 765kV substation and an expansion of Collins to take them; the selected solution adds bus positions, two 300 MVAR line reactors and two spare reactors at Collins, a line toward the Illinois/Wisconsin state border, and a line segment toward a new MISO Woodford County 765kV substation. (p. 6, p. 7) It also cuts the Powerton-Katydid and Powerton-Nevada 345kV lines into Woodford County, replaces oil circuit breakers at Powerton, Zion and Des Plaines, and mitigates a sag limit on the Zion-Paris 345kV line. (p. 7) The cost shown is MISO's Appendix A figure, and the slides say the costs will be allocated 100% to MISO customers. (p. 7) The estimate was $874.2 million at the March 2025 solutions meeting and $908.7 million at the November 2025 meeting, whose slide adds the breaker replacements and the Zion-Paris sag work that the March 2025 slide does not list. (p. 8, p. 10, p. 6, p. 7) At the December 2024 need meeting MISO's requested in-service date was June 1, 2033; from March 2025 on it is June 1, 2034, and ComEd lists the project status as Conceptual. (p. 3, p. 7, p. 6, p. 7)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Collins 765kV substationExpand and reconfigure: bus positions for two new 765kV lines, two 300 MVAR line reactors with dedicated breakers, two single-phase spare 765kV reactorsp. 7
Collins - Illinois/Wisconsin border 765kV lineNew 765kV line from Collins to an interconnection point with MISO near the Illinois/Wisconsin state borderp. 7
Collins - Woodford County 765kV line segmentSegment of a new 765kV line from Collins to a new 765kV Woodford County substation; MISO interconnection point to be determinedp. 7
Powerton 345kV line cut-insCut the Powerton-Katydid and Powerton-Nevada 345kV lines into the new Woodford County substation (MISO)p. 7
Powerton 345kV breakerReplace BT 5-6 oil circuit breaker; 2000 A, 40 kA to 3000 A, 63 kAp. 7
Zion 345kV breakersReplace BT 5-6 and BT 17-18 oil circuit breakers; 2000 A, 50 kA to 3000 A, 63 kAp. 7
Des Plaines 345kV breakersReplace six oil circuit breakers (BT 1-5, BT 2-5, BT 2-3, L4620, L4621, L12006); 2000 A, 40 kA to 3000 A, 63 kAp. 7
Zion - Paris 345kV lineMitigate sag limit on the Zion-Paris (ATC) 345 kV line and replace the line trap at Zionp. 7
Remote end work, Lakeview (MISO)Remote end coordination for cutting the Paris-Zion and Pleasant Prairie-Zion 345kV lines into Lakeview substation (MISO)p. 7
Remote end work, BabcockRemote end coordination for cutting the Olive-University Park and Olive-Green Acres 345kV lines into Babcock substationp. 7

Details as printed

Supplemental project IDs3843p. 7
Previously presentedSolutions meetings 3/4/2025 and 11/4/2025; need meeting 12/3/2024p. 6
Project driverOther (external public utilities and/or government requests)p. 6
Problem statementMISO's draft MTEP24 Appendix A for the LRTP Tranche 2.1 Portfolio identified work in PJM impacting the ComEd zone, assigned to PJM Transmission Ownersp. 6
MISO requestMISO requested two new 765kV lines from Collins and an expansion of Collins to accommodate themp. 6
Requested in-service, need meetingMISO requested in-service 6/1/2033p. 3
Requested in-service, solutions meetingMISO requested in-service 6/1/2034p. 7
Estimate, March 2025$874.2M (MISO Appendix A cost)p. 8
Estimate, November 2025$874.2M revised to $908.7Mp. 10
Cost noteMISO Appendix A cost; costs, including any projects from the no-harm analysis, allocated 100% to MISO customersp. 7
ModelMISO MTEP 2032p. 7

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
December 3, 2024Item 07 - ComEd Supplemental Projects PDFComEd Transmission Zone M-3 Process not printed6/1/2033Need Meeting 12/3/2024
March 4, 2025Item 11 - ComEd Supplemental Projects PDFMISO Tranche 2.1 Request $874.2M*6/1/2034Conceptual
November 4, 2025Item 11 - ComEd Supplemental Projects PDFMISO Tranche 2.1 Request $908.7M6/1/2034Conceptual
October 6, 2026Informational Only - ComEd Local Plan Submission of Supplemental Projects for 2026 PDFMISO Tranche 2.1 Request $908.7M6/1/2034Conceptual
Date not printedComed&nbsp PDFMISO Tranche 2.1 Request $908.7M6/1/2034Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.