Substation Scout

New Buffalo

New Buffalo, PA. Presented by PPL in PJM planning materials (PPL zone, PA).

$242 Mcost estimate as printed p. 29
05/30/2028projected in service p. 29
Conceptualstatus as printed p. 29

Profile

PPL presented this customer service project to PJM's Transmission Expansion Advisory Committee as a solution in January 2025, at a transmission cost estimate of $242 million and a projected in-service date of May 30, 2028. (p. 1, p. 4, p. 29) The need, first presented in November 2024, is a customer request to serve a facility from a 138kV source in New Buffalo, Pennsylvania, with a total load of approximately 1,000 MW by 2031 and a requested in-service date of May 2027. (p. 3) PPL lists an initial load of 200MW at in-service in 2027 and 400 MW projected for 2028. (p. 3) The plan centers on a new New Buffalo 500-138kV substation ($148 million, with four 500-138kV transformers), cut into the existing Juniata - Alburtis 500kV line, with that line rebuilt to double circuit for 9.6 miles from Juniata to New Buffalo at $83 million. (p. 29) Six 138kV lines would extend from the new substation to the customer facility, estimated at $3 million. (p. 29) PPL lists one alternative, a 500kV and 230kV design with a new 230kV yard, at an estimated $274M. (p. 29) PPL's 2025 local plan submission lists the project as supplemental ID s3571 with the same $242 million estimate and May 30, 2028 date, and gives the status as Conceptual. (p. 28, p. 29)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
New Buffalo 500-138kV substation (s3571.1)New 500-138kV substation with a four bay BAAH 500kV yard, four 500-138kV transformers, a six bay BAAH 138kV yard and one 138kV capacitor bank; estimated $148 Mp. 29
Juniata - Alburtis 500kV bifurcation (s3571.2)Bifurcate the Juniata - Alburtis 500kV line into the New Buffalo substation, extending lines approximately 0.6 miles; estimated $8 Mp. 29
Juniata - New Buffalo 500kV line rebuild (s3571.3)Rebuild the existing JUNI-ALBU 500kV line to double circuit for 9.6 miles from Juniata to New Buffalo; estimated $83 Mp. 29
Customer 138kV taps (s3571.4)Extend six 138kV lines to the customer facility; estimated $3 Mp. 29

Details as printed

Supplemental IDs3571p. 29
Solution presentedSolution Meeting TEAC - 01/07/2025p. 4
Need presentedNeed Meeting TEAC - 11/06/2024p. 3
Project driverCustomer Servicep. 28
Customer request, New BuffaloFacility served from a 138kV source in New Buffalo, PA; approximately 1,000 MW total (2031); requested in service 05/2027p. 3
Load ramp200MW initial in-service 2027; 400 MW projected 2028p. 3
Alternative considered500kV & 230kV option: five bay 230kV yard (NEBU) with four 230-138kV transformers and a three bay 500kV yard with two 500-230kV transformers, breaking the JUNI-DAUP 230kV line and rebuilding the JUNI-NEBU 230kV section to double circuit; estimated $274Mp. 29

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
November 6, 2024Item 08 - PPL Supplemental Projects PDFNew Buffalo, PA not printed05/2027Need Meeting TEAC - 11/06/2024
January 7, 2025Item 07 - PPL Supplemental Projects PDFPPL Transmission Zone: Supplemental $242 M05/30/2028Conceptual
October 8, 2025Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2025 PDFNew Buffalo, PA $242 M05/30/2028Conceptual
Date not printedPPL&nbsp PDFNew Buffalo, PA $242 M05/30/2028Conceptual

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first