New Buffalo
New Buffalo, PA. Presented by PPL in PJM planning materials (PPL zone, PA).
Profile
PPL presented this customer service project to PJM's Transmission Expansion Advisory Committee as a solution in January 2025, at a transmission cost estimate of $242 million and a projected in-service date of May 30, 2028. (p. 1, p. 4, p. 29) The need, first presented in November 2024, is a customer request to serve a facility from a 138kV source in New Buffalo, Pennsylvania, with a total load of approximately 1,000 MW by 2031 and a requested in-service date of May 2027. (p. 3) PPL lists an initial load of 200MW at in-service in 2027 and 400 MW projected for 2028. (p. 3) The plan centers on a new New Buffalo 500-138kV substation ($148 million, with four 500-138kV transformers), cut into the existing Juniata - Alburtis 500kV line, with that line rebuilt to double circuit for 9.6 miles from Juniata to New Buffalo at $83 million. (p. 29) Six 138kV lines would extend from the new substation to the customer facility, estimated at $3 million. (p. 29) PPL lists one alternative, a 500kV and 230kV design with a new 230kV yard, at an estimated $274M. (p. 29) PPL's 2025 local plan submission lists the project as supplemental ID s3571 with the same $242 million estimate and May 30, 2028 date, and gives the status as Conceptual. (p. 28, p. 29)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| New Buffalo 500-138kV substation (s3571.1) | New 500-138kV substation with a four bay BAAH 500kV yard, four 500-138kV transformers, a six bay BAAH 138kV yard and one 138kV capacitor bank; estimated $148 M | p. 29 |
| Juniata - Alburtis 500kV bifurcation (s3571.2) | Bifurcate the Juniata - Alburtis 500kV line into the New Buffalo substation, extending lines approximately 0.6 miles; estimated $8 M | p. 29 |
| Juniata - New Buffalo 500kV line rebuild (s3571.3) | Rebuild the existing JUNI-ALBU 500kV line to double circuit for 9.6 miles from Juniata to New Buffalo; estimated $83 M | p. 29 |
| Customer 138kV taps (s3571.4) | Extend six 138kV lines to the customer facility; estimated $3 M | p. 29 |
Details as printed
| Supplemental ID | s3571 | p. 29 |
|---|---|---|
| Solution presented | Solution Meeting TEAC - 01/07/2025 | p. 4 |
| Need presented | Need Meeting TEAC - 11/06/2024 | p. 3 |
| Project driver | Customer Service | p. 28 |
| Customer request, New Buffalo | Facility served from a 138kV source in New Buffalo, PA; approximately 1,000 MW total (2031); requested in service 05/2027 | p. 3 |
| Load ramp | 200MW initial in-service 2027; 400 MW projected 2028 | p. 3 |
| Alternative considered | 500kV & 230kV option: five bay 230kV yard (NEBU) with four 230-138kV transformers and a three bay 500kV yard with two 500-230kV transformers, breaking the JUNI-DAUP 230kV line and rebuilding the JUNI-NEBU 230kV section to double circuit; estimated $274M | p. 29 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| November 6, 2024 | Item 08 - PPL Supplemental Projects PDF | New Buffalo, PA | not printed | 05/2027 | Need Meeting TEAC - 11/06/2024 |
| January 7, 2025 | Item 07 - PPL Supplemental Projects PDF | PPL Transmission Zone: Supplemental | $242 M | 05/30/2028 | Conceptual |
| October 8, 2025 | Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2025 PDF | New Buffalo, PA | $242 M | 05/30/2028 | Conceptual |
| Date not printed | PPL  PDF | New Buffalo, PA | $242 M | 05/30/2028 | Conceptual |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- New Buffalo (PPL): described as new
- Alburtis (PPL)
- Juniata (PPL): expansion described
Not printed
- The decks name the customer only as a customer; they do not say what the facility is.
- No county is printed; New Buffalo, PA is the only location given for the customer site.
- The November 2024 need meeting printed no cost or solution; the January 2025 solution and the 2025 local plan print the same $242 M estimate and 05/30/2028 date.
- The load ramp printed stops at 2028 (400 MW); no figure is printed for the years between 2028 and the 2031 total.
- No later deck in the archive mentions New Buffalo or PPL-2024-0017; the 2026 local plan does not list it.
- PPL-2024-0016 is printed under the same New Buffalo, PA heading in the November 2024 deck, but it is a Blooming Grove transformer replacement ($6.3 M), so it is not a member.
- No news coverage naming the New Buffalo substation or PPL-2024-0017 was found as of 2026-11-27.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.