Substation Scout

MAAC PPL Cluster

MAAC PPL Cluster. Presented by PJM in PJM planning materials (PPL zone).

$565.4Mcost estimate as printed p. 28
6/1/2030projected in service p. 28
Recommended Readstatus as printed p. 28

Profile

The MAAC PPL Cluster is the solution PJM selected in its 2025 Window 1 for overloads in the Susquehanna and Juniata area of the PPL zone: PPL's proposal 2025-W1-558 plus one component from PPL's proposal 2025-W1-853, a third 500/230 kV transformer at Kelayres. (p. 28, p. 27, p. 42) PJM presented it as a recommended solution to its Transmission Expansion Advisory Committee on December 8, 2025, at an estimated total cost of $565.4 million and a projected in-service date of June 1, 2030, the same figures shown at the November first read. (p. 1, p. 28, p. 54) It is a portfolio of eight PPL components: the largest are a loop of the Susquehanna - Sunbury 500 kV line into the new Kelayres station with 13 miles of additional line ($227.42 million) and a rebuild of the Juniata - Sunbury 500 kV line ($162.89 million); the rest are 230 kV reconductoring and station work at Monroe, Jenkins, Montour, Glen Brook and Susquehanna. (p. 49) PJM's evaluation says proposal 558 alone ($536.38 million) left a couple of overloads under an additional 3.5 GW of PPL load, and that adding the Kelayres transformer addresses all thermal and voltage violations in the 2030 and 2032 base cases. (p. 48, p. 51, p. 52) PJM also wrote that the 500 kV Juniata - Sunbury - Kelayres path adds no regional transfer benefit and mainly focuses on sourcing PPL data center load. (p. 39) A follow-on item, B4029.18, replaces six 230 kV breakers at Susquehanna that the short circuit study found over duty with the cluster in the model; its estimate rose from $4.50 million to $7.39 million at the May 8, 2026 TEAC. (p. 17, p. 18, p. 13, p. 1) PPL's May 2026 supplemental slides also show two reconductoring items from a customer project moved under baseline IDs B4029.5 and B4029.13. (p. 1, p. 4, p. 5)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Kelayres 500 kV loop-in (proposal 317)Loop the Susquehanna - Sunbury 500 kV line into the new Kelayres station, with an additional 13 miles of line; $227.42Mp. 49
Susquehanna - Tomhicken 230 kV (proposal 824)Reconductor the Susquehanna - Tomhicken 230 kV 1 & 2 lines; $29.73Mp. 49
Monroe station (proposal 688)Reconfigure Monroe 230 kV and 138 kV and add a 2nd 230/138 kV transformer; $39.21Mp. 49
Juniata - Sunbury 500 kV (proposal 16)Rebuild the existing Juniata - Sunbury 500 kV line; $162.89Mp. 49
Montour - Glen Brook 230 kV (proposal 958)Reconductor/rebuild the Montour - Glen Brook 230 kV 1 & 2 line, about 6 miles; $39.65Mp. 49
Jenkins station (proposal 647)Reconfigure the Jenkins 230/69 kV substation; $10.17Mp. 49
Glen Brook - Susquehanna T10 230 kV (proposal 588)Reconductor Glen Brook - Susquehanna T10 1 & 2 and build a new 230 kV line Susquehanna T10 - Susquehanna (2.7 miles); $27.31Mp. 49
Kelayres third transformer (from proposal 853)Add a third 500/230 kV transformer at the new Kelayres station; $29.02Mp. 49

Details as printed

Proposing entityPPL (proposal 558)p. 42
Selected solutionSelected solution: 2025-W1-558 plus one component from 2025-W1-853 (a third 500/230 kV transformer at Kelayres)p. 28
CriteriaBaseline Load Growth Deliverability & Reliabilityp. 27
Problem statementMultiple overloads in the Susquehanna and Juniata area of PPL in the 2030 RTEP analysis, posted as part of 2025 Window 1p. 27
First read, November 2025First read: estimated total cost $565.4M, projected in service 6/1/2030p. 54
Portfolio 2 alone, costPPL Portfolio 2 (proposal 558) alone totaled $536.38Mp. 48
Portfolio 2 alone, PJM evaluationPortfolio 2 addresses the 2030 and 2032 violations and most violations from an additional 3.5 GW of PPL load, except a couple of remaining overloadsp. 51
Selected combination, PJM evaluationWith the Kelayres third transformer added, the combination addresses all thermal and voltage violations in the 2030 and 2032 base and mitigates violations from an additional 3.5 GW of PPL loadp. 52
PJM on the 500 kV pathPJM: the PPL 500 kV Juniata - Sunbury - Kelayres path adds no regional transfer benefit and mainly focuses on sourcing PPL data center loadp. 39
Follow-on breaker work, cost changeSusquehanna breaker replacements (B4029.18): estimated cost $4.50M revised to $7.39Mp. 13
Follow-on breaker work, January 2026Replace six 230KV breakers at Susquehanna with 63kA breakers (B4029.18)p. 17
Follow-on breaker work, January 2026 estimateEstimated cost $4.5 M; required and projected in service 6/1/2030p. 18
Cost change presentedPJM Reliability Analysis Update, TEAC May 8, 2026p. 1
PPL supplemental deckPPL Supplemental Projects, TEAC 05/08/2026p. 1
Scope moved from a supplemental projectPPL supplemental project moved its Susquehanna - Tomhicken reconductor (~10 miles, $12 M) under baseline B4029.5p. 4
Scope moved from a supplemental projectPPL supplemental moved its Glen Brook - Susquehanna T10 reconductor (~0.6 mile, $1 M) under baseline B4029.13p. 5

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
September 9, 2025Item 16 - Reliability Analysis Update PDF2025-W1-558 not printednot printed
November 4, 2025Item 14 - Reliability Analysis Update PDFMAAC PPL Cluster $565.4M6/1/2030First Read
December 8, 2025Item 11 - Reliability Analysis Update PDFPPL Transmission Zone: Baseline MAAC PPL Cluster $565.4M6/1/2030Recommended Read
January 6, 2026Item 09 - Reliability Analysis Update PDFPPL Cluster $4.5 M6/1/2030Recommended Solution
May 8, 2026Item 10 - Reliability Analysis Update PDFPPL Transmission Zone: Baseline $7.39Mnot printedRecommended Solution

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first