MAAC PPL Cluster
MAAC PPL Cluster. Presented by PJM in PJM planning materials (PPL zone).
Profile
The MAAC PPL Cluster is the solution PJM selected in its 2025 Window 1 for overloads in the Susquehanna and Juniata area of the PPL zone: PPL's proposal 2025-W1-558 plus one component from PPL's proposal 2025-W1-853, a third 500/230 kV transformer at Kelayres. (p. 28, p. 27, p. 42) PJM presented it as a recommended solution to its Transmission Expansion Advisory Committee on December 8, 2025, at an estimated total cost of $565.4 million and a projected in-service date of June 1, 2030, the same figures shown at the November first read. (p. 1, p. 28, p. 54) It is a portfolio of eight PPL components: the largest are a loop of the Susquehanna - Sunbury 500 kV line into the new Kelayres station with 13 miles of additional line ($227.42 million) and a rebuild of the Juniata - Sunbury 500 kV line ($162.89 million); the rest are 230 kV reconductoring and station work at Monroe, Jenkins, Montour, Glen Brook and Susquehanna. (p. 49) PJM's evaluation says proposal 558 alone ($536.38 million) left a couple of overloads under an additional 3.5 GW of PPL load, and that adding the Kelayres transformer addresses all thermal and voltage violations in the 2030 and 2032 base cases. (p. 48, p. 51, p. 52) PJM also wrote that the 500 kV Juniata - Sunbury - Kelayres path adds no regional transfer benefit and mainly focuses on sourcing PPL data center load. (p. 39) A follow-on item, B4029.18, replaces six 230 kV breakers at Susquehanna that the short circuit study found over duty with the cluster in the model; its estimate rose from $4.50 million to $7.39 million at the May 8, 2026 TEAC. (p. 17, p. 18, p. 13, p. 1) PPL's May 2026 supplemental slides also show two reconductoring items from a customer project moved under baseline IDs B4029.5 and B4029.13. (p. 1, p. 4, p. 5)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Kelayres 500 kV loop-in (proposal 317) | Loop the Susquehanna - Sunbury 500 kV line into the new Kelayres station, with an additional 13 miles of line; $227.42M | p. 49 |
| Susquehanna - Tomhicken 230 kV (proposal 824) | Reconductor the Susquehanna - Tomhicken 230 kV 1 & 2 lines; $29.73M | p. 49 |
| Monroe station (proposal 688) | Reconfigure Monroe 230 kV and 138 kV and add a 2nd 230/138 kV transformer; $39.21M | p. 49 |
| Juniata - Sunbury 500 kV (proposal 16) | Rebuild the existing Juniata - Sunbury 500 kV line; $162.89M | p. 49 |
| Montour - Glen Brook 230 kV (proposal 958) | Reconductor/rebuild the Montour - Glen Brook 230 kV 1 & 2 line, about 6 miles; $39.65M | p. 49 |
| Jenkins station (proposal 647) | Reconfigure the Jenkins 230/69 kV substation; $10.17M | p. 49 |
| Glen Brook - Susquehanna T10 230 kV (proposal 588) | Reconductor Glen Brook - Susquehanna T10 1 & 2 and build a new 230 kV line Susquehanna T10 - Susquehanna (2.7 miles); $27.31M | p. 49 |
| Kelayres third transformer (from proposal 853) | Add a third 500/230 kV transformer at the new Kelayres station; $29.02M | p. 49 |
Details as printed
| Proposing entity | PPL (proposal 558) | p. 42 |
|---|---|---|
| Selected solution | Selected solution: 2025-W1-558 plus one component from 2025-W1-853 (a third 500/230 kV transformer at Kelayres) | p. 28 |
| Criteria | Baseline Load Growth Deliverability & Reliability | p. 27 |
| Problem statement | Multiple overloads in the Susquehanna and Juniata area of PPL in the 2030 RTEP analysis, posted as part of 2025 Window 1 | p. 27 |
| First read, November 2025 | First read: estimated total cost $565.4M, projected in service 6/1/2030 | p. 54 |
| Portfolio 2 alone, cost | PPL Portfolio 2 (proposal 558) alone totaled $536.38M | p. 48 |
| Portfolio 2 alone, PJM evaluation | Portfolio 2 addresses the 2030 and 2032 violations and most violations from an additional 3.5 GW of PPL load, except a couple of remaining overloads | p. 51 |
| Selected combination, PJM evaluation | With the Kelayres third transformer added, the combination addresses all thermal and voltage violations in the 2030 and 2032 base and mitigates violations from an additional 3.5 GW of PPL load | p. 52 |
| PJM on the 500 kV path | PJM: the PPL 500 kV Juniata - Sunbury - Kelayres path adds no regional transfer benefit and mainly focuses on sourcing PPL data center load | p. 39 |
| Follow-on breaker work, cost change | Susquehanna breaker replacements (B4029.18): estimated cost $4.50M revised to $7.39M | p. 13 |
| Follow-on breaker work, January 2026 | Replace six 230KV breakers at Susquehanna with 63kA breakers (B4029.18) | p. 17 |
| Follow-on breaker work, January 2026 estimate | Estimated cost $4.5 M; required and projected in service 6/1/2030 | p. 18 |
| Cost change presented | PJM Reliability Analysis Update, TEAC May 8, 2026 | p. 1 |
| PPL supplemental deck | PPL Supplemental Projects, TEAC 05/08/2026 | p. 1 |
| Scope moved from a supplemental project | PPL supplemental project moved its Susquehanna - Tomhicken reconductor (~10 miles, $12 M) under baseline B4029.5 | p. 4 |
| Scope moved from a supplemental project | PPL supplemental moved its Glen Brook - Susquehanna T10 reconductor (~0.6 mile, $1 M) under baseline B4029.13 | p. 5 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| September 9, 2025 | Item 16 - Reliability Analysis Update PDF | 2025-W1-558 | not printed | not printed | |
| November 4, 2025 | Item 14 - Reliability Analysis Update PDF | MAAC PPL Cluster | $565.4M | 6/1/2030 | First Read |
| December 8, 2025 | Item 11 - Reliability Analysis Update PDF | PPL Transmission Zone: Baseline MAAC PPL Cluster | $565.4M | 6/1/2030 | Recommended Read |
| January 6, 2026 | Item 09 - Reliability Analysis Update PDF | PPL Cluster | $4.5 M | 6/1/2030 | Recommended Solution |
| May 8, 2026 | Item 10 - Reliability Analysis Update PDF | PPL Transmission Zone: Baseline | $7.39M | not printed | Recommended Solution |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Kelayres (PPL): described as new
- Tomhicken (PPL): described as new
- Glen Brook (PPL)
- Jenkins (PPL): expansion described
- Juniata (PPL): expansion described
- Monroe (PPL)
- Montour (PPL)
- Sunbury (PPL)
- Susquehanna (PPL): expansion described
- Susquehanna T10 (PPL): expansion described
Not printed
- No state or county is printed on the cluster slides; the only Pennsylvania reference found (Hazleton, PA) is on PPL's May 2026 slide for a separate customer project (PPL-2025-0010), so states is left empty.
- The archived decks do not print a PJM Board approval date for 2025-W1-558; the latest printed stage is Recommended Read (December 8, 2025), and later decks call it the selected solution.
- No cost or in-service change for the $565.4M cluster total appears after December 2025; the only printed cost change is on follow-on item B4029.18.
- The decks do not say whether Kelayres is greenfield for this portfolio; an earlier PPL portfolio (proposal 158) describes the Kelayres low side as an expansion of Slykerville from the M3 project.
- No news article about this program specifically was found; Utility Dive's February 17, 2026 report on the PJM Board's $11.8 billion approval gives a PPL total (about $580 million) without naming this cluster, so it is not listed.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.