Kammer - Juniata 765 kV

MAAC Regional Cluster Solution - NextEra/Exelon Proposal 2025-W1-237. Presented by PJM in PJM planning materials (AEP, APS, PENELEC, PPL zone).

$1,789.39Mcost estimate as printed p. 23
6/1/2032projected in service p. 23
Approvedstatus as printed p. 13

Profile

PJM staff presented NextEra/Exelon proposal 2025-W1-237 to the Transmission Expansion Advisory Committee as the recommended MAAC Regional Cluster solution on January 6, 2026, at an estimated total cost of $1,789.39 million and a projected in-service date of June 1, 2032. (p. 1, p. 58, p. 21, p. 23) The proposal builds a 765 kV line from the existing Kammer substation 114 miles to a new 765/500 kV Buttermilk Falls substation, then 108 miles to a new 765/500 kV Mountain Stone substation that connects to Juniata. (p. 61) PJM's problem statement says that in its 2032 analysis multiple 500 kV lines sourcing the Mid-Atlantic region are overloaded and voltage collapse is observed for several regional facilities. (p. 21) The December 8, 2025 deck lists PPL zonal load for 2030 up approximately 5 GW between the 2024 and 2025 forecasts, primarily driven by data center demand, about 3.5 GW of additional PPL load not in the forecast, and a scenario removing 7.5 GW of NJOSW. (p. 1, p. 31) PJM weighed it against FirstEnergy (MAIT) 500 kV proposals between Keystone and Susquehanna and recommended proposal 237, saying it offers about 2 GW more import to the Mid-Atlantic than proposal 826 and preserves existing 500 kV capacity. (p. 34, p. 50) At the first read on December 8, 2025 the total was $1,738.59 million with a projected in-service date of June 1, 2031; the January 2026 table updates several components with input from the incumbent transmission owners. (p. 1, p. 125, p. 52, p. 1, p. 58) On October 6, 2026, PJM, describing 2025-W1-237 as approved, reported PPL scope changes: the Juniata work rose from $9.95 million to $131.53 million for a new 500 kV station next to the existing one, and the Sunbury work from $4.98 million to $30 million. (p. 1, p. 13, p. 14, p. 15)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Kammer - Buttermilk Falls 765 kV line$694.72M estimated, $718.20M independentp. 58
Buttermilk Falls - Mountain Stone 765 kV line$633.35M estimated, $680.40M independentp. 58
Mountain Stone - Juniata 500 kV$5.32M estimated, $6.84M independentp. 58
Mountain Stone 765 kV substation (new)$166.94M estimated, $134.01M independentp. 58
Buttermilk Falls 765 kV substation (new)$170.29M estimated, $178.88M independentp. 58
Kammer substation upgrade$16.80M estimated (updated), $14.56M independentp. 58
New Juniata 500 kV station (b4036.15)New station adjacent to the existing Juniata station; new estimated total cost $131.53Mp. 14
Sunbury 500 kV substation (b4036.17)Reconfigure to breaker-and-a-half; new estimated total cost $30Mp. 15
Conemaugh circuit breaker upgrades$22.24M estimated (updated), $20.92M independentp. 58
Keystone - Conemaugh 500 kV loop-in at Buttermilk Falls (PENELEC)Establish Keystone - Buttermilk Falls; $11.20M estimatedp. 58

Details as printed

Proposing entityNextEra/Exelonp. 58
Process stage, January 2026Recommended Solution (second read)p. 21
Independent cost estimate$1,797.32M independent cost estimate, against $1,789.39M proposedp. 61
January 2026 updateCosts and scope updated from the original proposal 237 with input from the incumbent transmission ownersp. 58
Pending PPL scopePPL is working on additional scope to terminate the 500 kV lines from the new Mountain Stone station, which will add costp. 23
First read meetingTransmission Expansion Advisory Committee, December 8, 2025p. 1
Cost at first read$1,738.59M proposed, $1,797.32M independent estimatep. 125
First read total and date$1738.6M, projected in service 6/1/2031p. 52
Route as proposedOne 765 kV line from Kammer: 114 miles to a new 765/500 kV Buttermilk Falls substation (looped into Keystone - Conemaugh 500 kV), then 108 miles to a new 765/500 kV Mountain Stone substation connecting to Juniata 500p. 61
New line miles as submittedProposed ISD 6/1/2031; new line miles by column: 222, 1.2, 223.2 total EHV, 223.2 greenfieldp. 49
Problem statementIn the 2032 RTEP analysis, multiple 500 kV lines sourcing the Mid-Atlantic region are overloaded and voltage collapse is observed for several regional facilitiesp. 21
PPL load growthPPL zonal load for 2030 up approximately 5 GW from the 2024 to the 2025 load forecastp. 31
Load driverLoad growth primarily driven by data center demandp. 31
Additional PPL loadPPL submitted about 3.5 GW more not included in the 2025 load forecastp. 31
NJOSW delay scenarioRemoving the 7.5 GW NJOSW from service increases the transfer need to the Mid-Atlantic regionp. 31
Competing proposalsCompeting proposals #493, #578, #826 and #838 by MAIT (FirstEnergy)p. 34
Main alternativeEvaluation of the MAIT proposals focused on 826 ($1.15 billion), the least expensivep. 38
Proposal 687Longer NextEra/Exelon proposal #687 was not considered; the extension beyond Juniata could be advanced separatelyp. 38
SelectionPJM is recommending proposal #237 for developmentp. 50
Reason givenAbout 2 GW more import to Mid-Atlantic than proposal #826; preserves existing 500 kV capacityp. 50
Scope change meetingTransmission Expansion Advisory Committee, October 6, 2026p. 1
Juniata review (PPL)PPL's review of the NextEra scope found broader work than anticipated: a new station adjacent to the existing onep. 14
Reason for Juniata changeBringing the 765/500 kV transformer leads into the existing Juniata 500 kV buses would exceed their capabilityp. 14
b4036.15 beforeOld scope: two new 500 kV breakers at Juniata; old estimated total cost $9.95Mp. 13
b4036.17 beforeOld estimated total cost $4.98Mp. 15

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
September 9, 2025Item 16 - Reliability Analysis Update PDF2025-W1-237 not printednot printed
December 8, 2025Item 11 - Reliability Analysis Update PDFMAAC Regional Cluster: Baseline $1738.6M6/1/2031First Read
January 6, 2026Item 09 - Reliability Analysis Update PDFMAAC Regional Cluster: Baseline $1789.39M6/1/2032Recommended Solution
October 6, 2026Item 16 - Reliability Analysis Update - Presentation PDFB4036.15 Scope Change: Baseline $131.53M6/1/2032
October 6, 2026Item 16 - Reliability Analysis Update - Presentation PDFB4036.17 Scope Change: Baseline $30M6/1/2032

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

In the news

Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.