Kammer - Juniata 765 kV
MAAC Regional Cluster Solution - NextEra/Exelon Proposal 2025-W1-237. Presented by PJM in PJM planning materials (AEP, APS, PENELEC, PPL zone).
Profile
PJM staff presented NextEra/Exelon proposal 2025-W1-237 to the Transmission Expansion Advisory Committee as the recommended MAAC Regional Cluster solution on January 6, 2026, at an estimated total cost of $1,789.39 million and a projected in-service date of June 1, 2032. (p. 1, p. 58, p. 21, p. 23) The proposal builds a 765 kV line from the existing Kammer substation 114 miles to a new 765/500 kV Buttermilk Falls substation, then 108 miles to a new 765/500 kV Mountain Stone substation that connects to Juniata. (p. 61) PJM's problem statement says that in its 2032 analysis multiple 500 kV lines sourcing the Mid-Atlantic region are overloaded and voltage collapse is observed for several regional facilities. (p. 21) The December 8, 2025 deck lists PPL zonal load for 2030 up approximately 5 GW between the 2024 and 2025 forecasts, primarily driven by data center demand, about 3.5 GW of additional PPL load not in the forecast, and a scenario removing 7.5 GW of NJOSW. (p. 1, p. 31) PJM weighed it against FirstEnergy (MAIT) 500 kV proposals between Keystone and Susquehanna and recommended proposal 237, saying it offers about 2 GW more import to the Mid-Atlantic than proposal 826 and preserves existing 500 kV capacity. (p. 34, p. 50) At the first read on December 8, 2025 the total was $1,738.59 million with a projected in-service date of June 1, 2031; the January 2026 table updates several components with input from the incumbent transmission owners. (p. 1, p. 125, p. 52, p. 1, p. 58) On October 6, 2026, PJM, describing 2025-W1-237 as approved, reported PPL scope changes: the Juniata work rose from $9.95 million to $131.53 million for a new 500 kV station next to the existing one, and the Sunbury work from $4.98 million to $30 million. (p. 1, p. 13, p. 14, p. 15)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Kammer - Buttermilk Falls 765 kV line | $694.72M estimated, $718.20M independent | p. 58 |
| Buttermilk Falls - Mountain Stone 765 kV line | $633.35M estimated, $680.40M independent | p. 58 |
| Mountain Stone - Juniata 500 kV | $5.32M estimated, $6.84M independent | p. 58 |
| Mountain Stone 765 kV substation (new) | $166.94M estimated, $134.01M independent | p. 58 |
| Buttermilk Falls 765 kV substation (new) | $170.29M estimated, $178.88M independent | p. 58 |
| Kammer substation upgrade | $16.80M estimated (updated), $14.56M independent | p. 58 |
| New Juniata 500 kV station (b4036.15) | New station adjacent to the existing Juniata station; new estimated total cost $131.53M | p. 14 |
| Sunbury 500 kV substation (b4036.17) | Reconfigure to breaker-and-a-half; new estimated total cost $30M | p. 15 |
| Conemaugh circuit breaker upgrades | $22.24M estimated (updated), $20.92M independent | p. 58 |
| Keystone - Conemaugh 500 kV loop-in at Buttermilk Falls (PENELEC) | Establish Keystone - Buttermilk Falls; $11.20M estimated | p. 58 |
Details as printed
| Proposing entity | NextEra/Exelon | p. 58 |
|---|---|---|
| Process stage, January 2026 | Recommended Solution (second read) | p. 21 |
| Independent cost estimate | $1,797.32M independent cost estimate, against $1,789.39M proposed | p. 61 |
| January 2026 update | Costs and scope updated from the original proposal 237 with input from the incumbent transmission owners | p. 58 |
| Pending PPL scope | PPL is working on additional scope to terminate the 500 kV lines from the new Mountain Stone station, which will add cost | p. 23 |
| First read meeting | Transmission Expansion Advisory Committee, December 8, 2025 | p. 1 |
| Cost at first read | $1,738.59M proposed, $1,797.32M independent estimate | p. 125 |
| First read total and date | $1738.6M, projected in service 6/1/2031 | p. 52 |
| Route as proposed | One 765 kV line from Kammer: 114 miles to a new 765/500 kV Buttermilk Falls substation (looped into Keystone - Conemaugh 500 kV), then 108 miles to a new 765/500 kV Mountain Stone substation connecting to Juniata 500 | p. 61 |
| New line miles as submitted | Proposed ISD 6/1/2031; new line miles by column: 222, 1.2, 223.2 total EHV, 223.2 greenfield | p. 49 |
| Problem statement | In the 2032 RTEP analysis, multiple 500 kV lines sourcing the Mid-Atlantic region are overloaded and voltage collapse is observed for several regional facilities | p. 21 |
| PPL load growth | PPL zonal load for 2030 up approximately 5 GW from the 2024 to the 2025 load forecast | p. 31 |
| Load driver | Load growth primarily driven by data center demand | p. 31 |
| Additional PPL load | PPL submitted about 3.5 GW more not included in the 2025 load forecast | p. 31 |
| NJOSW delay scenario | Removing the 7.5 GW NJOSW from service increases the transfer need to the Mid-Atlantic region | p. 31 |
| Competing proposals | Competing proposals #493, #578, #826 and #838 by MAIT (FirstEnergy) | p. 34 |
| Main alternative | Evaluation of the MAIT proposals focused on 826 ($1.15 billion), the least expensive | p. 38 |
| Proposal 687 | Longer NextEra/Exelon proposal #687 was not considered; the extension beyond Juniata could be advanced separately | p. 38 |
| Selection | PJM is recommending proposal #237 for development | p. 50 |
| Reason given | About 2 GW more import to Mid-Atlantic than proposal #826; preserves existing 500 kV capacity | p. 50 |
| Scope change meeting | Transmission Expansion Advisory Committee, October 6, 2026 | p. 1 |
| Juniata review (PPL) | PPL's review of the NextEra scope found broader work than anticipated: a new station adjacent to the existing one | p. 14 |
| Reason for Juniata change | Bringing the 765/500 kV transformer leads into the existing Juniata 500 kV buses would exceed their capability | p. 14 |
| b4036.15 before | Old scope: two new 500 kV breakers at Juniata; old estimated total cost $9.95M | p. 13 |
| b4036.17 before | Old estimated total cost $4.98M | p. 15 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| September 9, 2025 | Item 16 - Reliability Analysis Update PDF | 2025-W1-237 | not printed | not printed | |
| December 8, 2025 | Item 11 - Reliability Analysis Update PDF | MAAC Regional Cluster: Baseline | $1738.6M | 6/1/2031 | First Read |
| January 6, 2026 | Item 09 - Reliability Analysis Update PDF | MAAC Regional Cluster: Baseline | $1789.39M | 6/1/2032 | Recommended Solution |
| October 6, 2026 | Item 16 - Reliability Analysis Update - Presentation PDF | B4036.15 Scope Change: Baseline | $131.53M | 6/1/2032 | |
| October 6, 2026 | Item 16 - Reliability Analysis Update - Presentation PDF | B4036.17 Scope Change: Baseline | $30M | 6/1/2032 |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Juniata (PJM system-wide): described as new
- Mountain Stone (PJM system-wide): described as new
- Belmont (PJM system-wide)
- Buttermilk Falls (PJM system-wide)
- Conemaugh (PJM system-wide)
- Kammer (PJM system-wide)
- Keystone (PJM system-wide)
- Mountaineer (PJM system-wide)
- South Bend (PJM system-wide)
- Sunbury (PJM system-wide)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- PJM board approves $11.8B transmission expansion plan, Utility Dive, February 17, 2026. Utility Dive reported that the PJM board approved a transmission plan including a $1.7 billion NextEra-Exelon line across central Pennsylvania, slated to operate by June 2031 and opposed by Pennsylvania's Office of Consumer Advocate, which argued that less expensive alternatives existed.
- $1.7 billion power project would cross Greene, Fayette counties, Observer-Reporter, April 2, 2026. The Observer-Reporter reported that the roughly 220-mile line would run from the Kammer substation in Marshall County, W.Va., to the Juniata substation in Perry County, Pa., through Greene, Fayette and eight other Pennsylvania counties, that no route had been set, and that the state Consumer Advocate and Public Utility Commission had raised questions about the project.
Not printed
- No state or county is printed for any station or line in the cited PJM decks; the West Virginia and Pennsylvania locations come only from the Observer-Reporter article.
- The October 6, 2026 deck reports the Juniata and Sunbury scope changes but prints no revised total for the program; the latest printed total is $1,789.39M (January 6, 2026).
- The cost of PPL's additional scope to terminate the Mountain Stone 500 kV lines is not printed.
- No PJM Board approval date is printed in the archived documents; the October 2026 deck says only that PJM approved the proposal.
- The decks do not name the data center customers behind the PPL load growth.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.