Champlain Substation
Champlain Substation. Presented by PEPCO in PJM planning materials (PEPCO zone, DC).
Profile
Champlain Substation is a PEPCO supplemental project, need number PEP-2025-003, to replace the retired Champlain substation in Washington D.C. with a 230 kV and 69 kV gas-insulated substation and three 230/69 kV transformers. (p. 3, p. 1, p. 4) PEPCO presented the need to PJM's Transmission Expansion Advisory Committee on June 5, 2025 and the solution on September 9, 2025, at a total estimated transmission cost of $590 million and a projected in-service date of July 1, 2029; it lists the project status as Engineering. (p. 3, p. 3, p. 1, p. 4) The problem statement lists 11 oil-filled cables under the Potomac River with frequent operational issues (approximately 45 years old), reliability and maintenance issues at the I Street substation (over 40 years old), aging 69 kV feeders to Georgetown and F Street (nearing 50 years old), aging 34 kV feeders to L Street, and a lack of alternative supply capacity in downtown Washington DC. (p. 3) PEPCO lists the drivers as equipment material condition, performance and risk; operational flexibility and efficiency; and infrastructure resilience. (p. 3) Per the slide, Champlain would provide a 69 kV source for a new network into downtown DC that resupplies Georgetown, F Street and L Street substations and retires the 11 oil-filled cables, and would enable retirement of the I Street substation; two 500 MVA phase shifters at Takoma substation are required for flow control once Champlain is in service. (p. 4) The alternative considered, resupplying F Street and Georgetown from Takoma over four new 69 kV cables and L Street over four more, was estimated at more than $1.6 billion. (p. 4)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Champlain 230/69 kV GIS substation | Replace the retired Champlain substation with a 230kV GIS breaker-and-a-half bus, a 69kV GIS breaker-and-a-half bus and (3) 230kV/69kV transformers | p. 4 |
| Takoma phase shifters | (2) 500 MVA phase shifters at Takoma substation, required for flow control once Champlain is in service; N-1-1 overloads would be present without them | p. 4 |
| New downtown 69 kV network | A 69kV source for a new 69kV network into downtown DC to resupply Georgetown, F street and L street substations and retire 11 oil filled cables | p. 4 |
| Downtown 230 kV network | Uses capacity from Pepco's downtown 230kV Network (s0838, s0839 and s0840) | p. 4 |
| I Street retirement | Enables I street substation retirement | p. 4 |
Details as printed
| Need presented, June 2025 | Need meeting 06/05/2025 | p. 3 |
|---|---|---|
| Project drivers | Equipment Material Condition, Performance and Risk; Operational Flexibility and Efficiency; Infrastructure Resilience | p. 3 |
| Problem statement | 11 oil filled cables under the Potomac river with frequent operational issues (approx 45 years old); "I" Street Substation reliability and maintenance issues (over 40 years old); aging 69 kV feeders to Georgetown and "F" Street (nearing 50 years old); aging 34kV feeders to "L" Street near end of useful life (45 years); lack of alternative supply capacity in downtown Washington DC | p. 3 |
| Alternative considered | Resupply F Street and Georgetown from Takoma via four new 69kV XLPE cables and L Street via four more; total estimated cost in excess of $1.6B | p. 4 |
| Model | RTEP 2029 | p. 4 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| June 5, 2025 | Item 07 - PEPCO Supplemental Projects PDF | PEPCO Transmission Zone M-3 Process PEPCO | not printed | not printed | Need Meeting 06/05/2025 |
| September 9, 2025 | Item 11 - PEPCO Supplemental Projects PDF | Champlain Substation | $590M | 7/1/2029 | Engineering |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
Not printed
- No cost or in-service change appears in the archived decks; the only cost, date and status are on the September 9, 2025 solution slide. No later PJM deck in the archive mentions Champlain or PEP-2025-003, and no supplemental project (s) number is printed for it.
- The slides print Washington D.C. but no street address or ward; the DC PSC Capital Grid page places the Champlain substation in Adams Morgan, which is not printed in the decks.
- The slides do not say when or why the existing Champlain substation was retired.
- The PJM slides do not tie Champlain to any 2025 RTEP Window 1 project, including the Exelon/PEPCO Cluster (Dickerson).
- No news article about this specific PJM project was found that could be opened; search results were Pepco fact sheets, DC PSC pages (utility or regulator pages, not news) and a 2017 Utility Dive article about the separate Mt. Vernon substation, so none are listed.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.