Champlain Substation

Champlain Substation. Presented by PEPCO in PJM planning materials (PEPCO zone, DC).

$590Mcost estimate as printed p. 4
7/1/2029projected in service p. 4
Engineeringstatus as printed p. 4

Profile

Champlain Substation is a PEPCO supplemental project, need number PEP-2025-003, to replace the retired Champlain substation in Washington D.C. with a 230 kV and 69 kV gas-insulated substation and three 230/69 kV transformers. (p. 3, p. 1, p. 4) PEPCO presented the need to PJM's Transmission Expansion Advisory Committee on June 5, 2025 and the solution on September 9, 2025, at a total estimated transmission cost of $590 million and a projected in-service date of July 1, 2029; it lists the project status as Engineering. (p. 3, p. 3, p. 1, p. 4) The problem statement lists 11 oil-filled cables under the Potomac River with frequent operational issues (approximately 45 years old), reliability and maintenance issues at the I Street substation (over 40 years old), aging 69 kV feeders to Georgetown and F Street (nearing 50 years old), aging 34 kV feeders to L Street, and a lack of alternative supply capacity in downtown Washington DC. (p. 3) PEPCO lists the drivers as equipment material condition, performance and risk; operational flexibility and efficiency; and infrastructure resilience. (p. 3) Per the slide, Champlain would provide a 69 kV source for a new network into downtown DC that resupplies Georgetown, F Street and L Street substations and retires the 11 oil-filled cables, and would enable retirement of the I Street substation; two 500 MVA phase shifters at Takoma substation are required for flow control once Champlain is in service. (p. 4) The alternative considered, resupplying F Street and Georgetown from Takoma over four new 69 kV cables and L Street over four more, was estimated at more than $1.6 billion. (p. 4)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Champlain 230/69 kV GIS substationReplace the retired Champlain substation with a 230kV GIS breaker-and-a-half bus, a 69kV GIS breaker-and-a-half bus and (3) 230kV/69kV transformersp. 4
Takoma phase shifters(2) 500 MVA phase shifters at Takoma substation, required for flow control once Champlain is in service; N-1-1 overloads would be present without themp. 4
New downtown 69 kV networkA 69kV source for a new 69kV network into downtown DC to resupply Georgetown, F street and L street substations and retire 11 oil filled cablesp. 4
Downtown 230 kV networkUses capacity from Pepco's downtown 230kV Network (s0838, s0839 and s0840)p. 4
I Street retirementEnables I street substation retirementp. 4

Details as printed

Need presented, June 2025Need meeting 06/05/2025p. 3
Project driversEquipment Material Condition, Performance and Risk; Operational Flexibility and Efficiency; Infrastructure Resiliencep. 3
Problem statement11 oil filled cables under the Potomac river with frequent operational issues (approx 45 years old); "I" Street Substation reliability and maintenance issues (over 40 years old); aging 69 kV feeders to Georgetown and "F" Street (nearing 50 years old); aging 34kV feeders to "L" Street near end of useful life (45 years); lack of alternative supply capacity in downtown Washington DCp. 3
Alternative consideredResupply F Street and Georgetown from Takoma via four new 69kV XLPE cables and L Street via four more; total estimated cost in excess of $1.6Bp. 4
ModelRTEP 2029p. 4

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
June 5, 2025Item 07 - PEPCO Supplemental Projects PDFPEPCO Transmission Zone M-3 Process PEPCO not printednot printedNeed Meeting 06/05/2025
September 9, 2025Item 11 - PEPCO Supplemental Projects PDFChamplain Substation $590M7/1/2029Engineering

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.