Venator Station
Venator Station. Presented by AEP in PJM planning materials (AEP zone, KY).
Profile
AEP presented Venator Station to PJM's Transmission Expansion Advisory Committee for its December 2026 meeting, at a transmission cost estimate of $324.2 million and a projected in-service date of October 22, 2028. (p. 1, p. 11, p. 14) The driver listed is customer service: a customer has requested new service for 1,000 MW in Boyd County, Kentucky by the fourth quarter of 2028. (p. 11) AEP first presented the need at the July 2026 meeting under the heading Hanging Rock, OH/Baker, KY, with the same problem statement; that deck printed no cost or solution. (p. 3, p. 11) The plan is a new Venator Station with four 765 kV circuit breakers and two 765/345 kV 2250 MVA transformers, estimated at $285 million, tied in by two 765 kV extensions of about 0.7 and 1.1 miles from the existing Baker - Hanging Rock 765 kV line. (p. 12) Two 345 kV customer feeds of about 2.8 and 2.7 miles would run from Venator Station to the customer delivery point, each estimated at $15.75 million. (p. 12, p. 13) AEP says no other viable transmission alternatives were identified, because the underlying 138 kV network cannot serve this load without EHV support. (p. 14) AEP lists the project status as Scoping. (p. 14)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Venator 765 kV station | Four 765 kV circuit breakers (breaker and a half, operated as a ring bus), two 765/345 kV 2250 MVA transformers with a shared switchable spare; estimated $285 M | p. 12 |
| Venator 765 kV Extension No. 1 | About 0.7 miles of 765 kV line from the existing Baker - Hanging Rock 765 kV line; estimated $3.85 M | p. 12 |
| Venator 765 kV Extension No. 2 | About 1.1 miles of 765 kV line from the existing Baker - Hanging Rock 765 kV line; estimated $3.85 M | p. 12 |
| Customer Feed No. 1 | About 2.8 miles of 345 kV between Venator Station and the customer delivery point (its cost is printed at the top of the next slide) | p. 12 |
| Customer Feed No. 2 | About 2.7 miles of 345 kV between Venator Station and the customer delivery point; estimated $15.75 M | p. 13 |
Details as printed
| Previously presented | Need Meeting TEAC - 07/07/2026 | p. 11 |
|---|---|---|
| Need meeting, July 2026 | Need presented as "Hanging Rock, OH/Baker, KY", Need Meeting 07/07/2026 | p. 3 |
| Project driver | Customer Service | p. 11 |
| Customer request, Boyd County | 1000 MW in Boyd County, Kentucky by Q4 of 2028 | p. 11 |
| Alternatives considered | No other viable transmission alternatives identified; the underlying 138 kV network cannot serve this load without EHV support | p. 14 |
| Model | 2030 RTEP | p. 14 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| July 7, 2026 | Item 10 - AEP Supplemental Projects PDF | Hanging Rock, OH/Baker, KY | not printed | not printed | Need Meeting 07/07/2026 |
| December 1, 2026 | Item 03 - AEP Supplemental Projects - Presentation | Venator Station | $324.2 M | 10/22/2028 | Scoping |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Baker (AEP)
- Hanging Rock (AEP)
- Venator Station (AEP)
Not printed
- The deck names the customer only as a customer; it does not say what the load is.
- The deck does not print a county or state for Venator Station itself; Kentucky comes from the customer request in Boyd County. Ohio is printed only for the existing Hanging Rock station in the July 2026 heading and is not listed.
- The July 2026 need deck prints no cost, in-service date or status.
- No news article found that names Venator Station or ties this PJM need to a named project; none is listed.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.