Substation Scout

Venator Station

Venator Station. Presented by AEP in PJM planning materials (AEP zone, KY).

$324.2 Mcost estimate as printed p. 14
10/22/2028projected in service p. 14
Scopingstatus as printed p. 14

Profile

AEP presented Venator Station to PJM's Transmission Expansion Advisory Committee for its December 2026 meeting, at a transmission cost estimate of $324.2 million and a projected in-service date of October 22, 2028. (p. 1, p. 11, p. 14) The driver listed is customer service: a customer has requested new service for 1,000 MW in Boyd County, Kentucky by the fourth quarter of 2028. (p. 11) AEP first presented the need at the July 2026 meeting under the heading Hanging Rock, OH/Baker, KY, with the same problem statement; that deck printed no cost or solution. (p. 3, p. 11) The plan is a new Venator Station with four 765 kV circuit breakers and two 765/345 kV 2250 MVA transformers, estimated at $285 million, tied in by two 765 kV extensions of about 0.7 and 1.1 miles from the existing Baker - Hanging Rock 765 kV line. (p. 12) Two 345 kV customer feeds of about 2.8 and 2.7 miles would run from Venator Station to the customer delivery point, each estimated at $15.75 million. (p. 12, p. 13) AEP says no other viable transmission alternatives were identified, because the underlying 138 kV network cannot serve this load without EHV support. (p. 14) AEP lists the project status as Scoping. (p. 14)

Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.

What the plan includes

ComponentAs printedSource
Venator 765 kV stationFour 765 kV circuit breakers (breaker and a half, operated as a ring bus), two 765/345 kV 2250 MVA transformers with a shared switchable spare; estimated $285 Mp. 12
Venator 765 kV Extension No. 1About 0.7 miles of 765 kV line from the existing Baker - Hanging Rock 765 kV line; estimated $3.85 Mp. 12
Venator 765 kV Extension No. 2About 1.1 miles of 765 kV line from the existing Baker - Hanging Rock 765 kV line; estimated $3.85 Mp. 12
Customer Feed No. 1About 2.8 miles of 345 kV between Venator Station and the customer delivery point (its cost is printed at the top of the next slide)p. 12
Customer Feed No. 2About 2.7 miles of 345 kV between Venator Station and the customer delivery point; estimated $15.75 Mp. 13

Details as printed

Previously presentedNeed Meeting TEAC - 07/07/2026p. 11
Need meeting, July 2026Need presented as "Hanging Rock, OH/Baker, KY", Need Meeting 07/07/2026p. 3
Project driverCustomer Servicep. 11
Customer request, Boyd County1000 MW in Boyd County, Kentucky by Q4 of 2028p. 11
Alternatives consideredNo other viable transmission alternatives identified; the underlying 138 kV network cannot serve this load without EHV supportp. 14
Model2030 RTEPp. 14

History in PJM materials

Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.

MeetingDocumentTitle as printedCostIn serviceStatus / stage
July 7, 2026Item 10 - AEP Supplemental Projects PDFHanging Rock, OH/Baker, KY not printednot printedNeed Meeting 07/07/2026
December 1, 2026Item 03 - AEP Supplemental Projects - PresentationVenator Station $324.2 M10/22/2028Scoping

Substations in the PJM rows for this project

Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.

Not printed

Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first