Maryland Piedmont Reliability Project (MPRP): Chanceford - Doubs 500 kV
Chanceford – Doubs 500 kV line. Presented by PJM in PJM planning materials (PPL, BGE zone, PA, MD).
Profile
This is the new 500 kV line PJM recommended on December 5, 2023 in its 2022 Window 3 East cluster, running from a new Otter Creek (Chanceford) switching station to Doubs substation and built in segments by PPL, BGE and PSEG across PA and MD. (p. 1, p. 18, p. 19, p. 58, p. 19) PSEG's segment (2022-W3-637) is a new line of about 70 miles from the Conastone demarcation point to Doubs that bypasses Conastone station, at a proposed cost of $447.5 million; PPL's part (2022-W3-374) was a new switching station and about 17 miles of line toward Conastone, at $134.2 million. (p. 58, p. 57) The December 2023 slides print a required and projected in-service date of June 1, 2027. (p. 58, p. 1) On July 8, 2025 PJM restated PPL's scope as the Chanceford switchyard, about 12.5 miles of line toward the PA/MD border and a 1.0-mile tie to the TMI-Peach Bottom right-of-way, total unchanged at $148.15 million, and split final tie-in and commissioning into b3800.54 ($0.2 million) so PPL's segment can be completed ahead of the others. (p. 1, p. 19) PJM's 2024 Window 1 recommended solution 2024-W1-551, presented January 7, 2025, removes the Chanceford-Doubs termination at Doubs and connects the line through a 0.6 mile 500 kV bypass around the substation, at $13.97 million (b4000.13), with a required date of June 1, 2032. (p. 1, p. 66) At the October 6, 2026 TEAC, BGE's segment from the MD border to the PSEG demarcation point (b3800.4) was re-estimated at $33.73 million, up from $11.11 million; no updated cost for the PSEG segment appears in the archived PJM documents. (p. 1, p. 19)
Written by Scout, Substation Scout's research agent, from the cited pages only, and checked by script: every quote must be on its page and every number in this profile must appear in a cited quote. Reviewed November 27, 2026.
What the plan includes
| Component | As printed | Source |
|---|---|---|
| Otter Creek (Chanceford) 500 kV switching station, PPL (b3800.1) | New switching station, two bay three breaker configuration, $32.76M | p. 19 |
| Chanceford - PA/MD border line, PPL (b3800.3) | New 500 kV line of about 12.5 miles toward the PA/MD border, rebuilding the existing Otter Creek - Conastone 230 kV line as double-circuit 500 kV; $102.8M revised to $102.6M | p. 19 |
| Tie to the TMI - Peach Bottom right-of-way, PPL (b3800.53) | Double-circuit 500 kV line of about 1.0 miles from the TMI-Peach Bottom right-of-way to Chanceford, $12.59M | p. 19 |
| Otter Creek - Conastone demarcation line, PPL (2023 description) | New 500 kV line from Otter Creek toward the Conastone demarcation point, about 17 miles | p. 57 |
| Conastone demarcation point - Doubs line, PSEG | New 500 kV line from the Conastone demarcation point to Doubs, about 70 miles | p. 58 |
| Conastone bypass | The line ties into the PPL Otter Creek - Conastone line and bypasses Conastone station | p. 58 |
| Doubs 500 kV station, PSEG | Reconfigure Doubs 500 kV and upgrade terminal equipment for the new line | p. 58 |
Details as printed
| Proposal, PSEG | PSEG proposal 2022-W3-637, East cluster | p. 58 |
|---|---|---|
| Proposal, PPL | PPL proposal 2022-W3-374, East cluster | p. 57 |
| PPL portion, December 2023 | Baseline B3800.1 – B3800.6, $134.2 M | p. 57 |
| Shared PPL/BGE line | The existing Otter Creek - Conastone line is owned by PPL and BGE, who share responsibility for the rebuild | p. 57 |
| PPL update meeting | TEAC July 8, 2025 | p. 1 |
| PPL portion, July 2025 | Total estimated cost $148.15 M, unchanged | p. 19 |
| PPL portion, required date | Required 6/1/2027, unchanged | p. 19 |
| PPL tie-in split out (b3800.54) | New sub-project b3800.54: final tie-ins and commissioning for Chanceford-Doubs line energization once all segments in PA & MD are complete, $0.2M | p. 19 |
| Reason for PPL update | Intended to improve project-on-project coordination and allow a potentially earlier completion of PPL's segment | p. 19 |
| 2024 Window 1 change at Doubs, preferred (2024-W1-551) | Re-route the Chanceford - Doubs line into the Doubs - Goose Creek corridor, creating a Chanceford - Goose Creek 500 kV line | p. 79 |
| 2024 Window 1 recommendation meeting | TEAC January 7, 2025 | p. 1 |
| 2024 Window 1 change at Doubs, recommended (b4000.13) | Recommended Solution 2024-W1-551 removes the Chanceford-Doubs termination at Doubs and connects the line through a 0.6 mile 500 kV bypass around Doubs, $13.97M (b4000.13) | p. 66 |
| 2024 Window 1 change at Doubs, dates | Required and projected 6/1/2032 | p. 66 |
| Cost update meeting | TEAC October 6, 2026 | p. 1 |
| BGE segment, MD border to PSEG demarcation point (b3800.4) | b3800.4: $11.11M original, $33.73M updated, change $22.62M; includes a rebuild of about 1.6 miles of the Otter Creek-Conastone 230 kV line | p. 19 |
| BGE segment, note | b3800.4 original cost provided by PPL submittal 2022-W3-374 | p. 19 |
History in PJM materials
Every PJM document that presented a part of this project, oldest first, with the cost and date printed in it. Values are shown only where they passed the check against the PDF text.
| Meeting | Document | Title as printed | Cost | In service | Status / stage |
|---|---|---|---|---|---|
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | Recommended Solutions to Address Clusters - East | $134.2 M | 6/1/2027 | |
| December 5, 2023 | Item 15 - Reliability Analysis Update 2022 Window 3 | Recommended Solutions to Address Clusters - East | $447.5 M | 6/1/2027 | |
| July 8, 2025 | Item 11 - Reliability Analysis Update PDF | 2022 W3 Chanceford-Doubs Project Update | $148.15 M | 6/1/2027 |
Substations in the PJM rows for this project
Every station named in the PJM planning rows tracked for this project, with its utility zone. Where a row is a whole proposal package, this includes stations in other parts of that package. Each links to its Substation Expansion Tracker page.
- Chanceford (PPL): described as new
- Otter Creek (PJM system-wide): described as new
- Otter Creek (PPL): described as new
- Conastone (PJM system-wide)
- Conastone (PPL)
- Doubs (PJM system-wide)
- Doubs (PPL)
- Peach Bottom (PJM system-wide)
- Peach Bottom (PPL)
- TMI (PJM system-wide)
- TMI (PPL)
In the news
Third-party coverage, listed for reference. Substation Scout does not verify what these articles report.
- Review for Piedmont power line will take until at least February 2027, Maryland regulators say, Maryland Matters (via Yahoo News), September 12, 2025. Maryland Matters reported that the Maryland Public Service Commission set a schedule under which a ruling on PSEG's Certificate of Public Convenience and Necessity for the 67-mile Maryland Piedmont Reliability Project through Baltimore, Carroll and Frederick counties cannot come before February 2027, while PSEG had asked for a decision by March 2026 to meet PJM's June 2027 date.
- MPRP state approval schedule released, pushing project completion into 2029, WBFF FOX45 Baltimore (from The Baltimore Sun), August 31, 2026. FOX45, citing The Baltimore Sun, reported that the Public Service Commission approved a revised procedural schedule with a target final order in July 2027, putting completion of the line more than a year past PJM's requested June 2027 in-service date, after disputes over survey access to landowners' property.
Not printed
- The name "Maryland Piedmont Reliability Project" (MPRP) does not appear in the archived PJM pages; it is used in the news items only.
- No county is printed on the cited PJM pages; the counties in the news items are the outlets'.
- No updated cost or in-service date for the PSEG segment (B3800.7 – B3800.8, B3800.43) is printed in the archived documents after December 2023.
- No combined cost for all segments is printed; PSEG, PPL and BGE segments are priced separately and are not summed here.
- The PSEG segment's transmission zone is not printed; zone lists only PPL and BGE, the owners printed for the other segments.
- BGE's b3800.4 is not a separate tracked row; it is cited from the October 2026 cost table.
Costs and dates are the presenting utility's or PJM's estimates as printed, not a forecast. A project can change scope, cost or schedule at any later meeting.