Minotola substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 5 with terminal status (shown grayed).

5 PJM queue filings name Minotola as the point of interconnection, all in NJ.

Target commercial operation dates as filed run from Apr 2012 to Apr 2025 (5 filings).

0active projects
0active MW
5total filed
Queue IDProjectkVMWResourceStatusTarget COD
AB1-169A Minotola 138 kV 138 550 Gas Withdrawn Jun 2020
AH1-067 Minotola 12.47 kV 12.5 4.2 Solar Withdrawn Dec 2023
X1-044 Minotola 12kV 12 3.8 Solar Withdrawn Apr 2012
W4-027 Minotola 2 Solar Facility 12 3 Solar Withdrawn Jun 2018
AE1-061 Panther Branch Storage 12 2.8 Battery Withdrawn Apr 2025

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Atlantic County, NJ

All 93 PJM queue filings in Atlantic County, NJ, including 6 more substations.

Other PJM queue substations in Gloucester County, NJ

All 88 PJM queue filings in Gloucester County, NJ.

Other PJM queue substations in Cumberland County, NJ

All 94 PJM queue filings in Cumberland County, NJ.