Clayton-Williamstown substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 3 with terminal status (shown greyed).

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatus
AE2-039 Clayton-Williamstown 69 kV 69 28.7 Solar Withdrawn
AE2-334 Gloucester Solar I 69 26.4 Solar Withdrawn
AG1-103 Gloucester Solar I 69 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.