Clayton-Williamstown substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).

3 PJM queue filings name Clayton-Williamstown as the point of interconnection, all in Gloucester County, NJ.

Target commercial operation dates as filed run from Jun 2022 to Dec 2026 (3 filings).

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AE2-039 Clayton-Williamstown 69 kV 69 28.7 Solar Withdrawn Jun 2022
AE2-334 Gloucester Solar I 69 26.4 Solar Withdrawn Dec 2026
AG1-103 Gloucester Solar I 69 0 Battery Withdrawn Dec 2026

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Gloucester County, NJ

All 88 PJM queue filings in Gloucester County, NJ.