Mantua substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 4 with terminal status (shown grayed).
4 PJM queue filings name Mantua as the point of interconnection, all in Gloucester County, NJ.
Target commercial operation dates as filed run from Dec 2016 to Dec 2021 (4 filings).
0active projects
0active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AG2-036 | Mantua 12 kV | 12 | 5.1 | Solar | Withdrawn | Dec 2021 |
| AB2-105 | Mantua 12kV | 12 | 0 | Gas | Withdrawn | Dec 2016 |
| AC1-196 | Mantua 12kV | 12 | 0 | Gas | Withdrawn | Jun 2017 |
| AC2-139 | The Home Depot Store # 0974 | 12 | 0 | Gas | Withdrawn | Dec 2018 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Gloucester County, NJ
- Kearny: 8 active, 931 MW of 12 filed
- Mickleton: 4 active, 729.7 MW of 12 filed
- Bridgeport: 2 active, 519 MW of 4 filed
- Clayton: 2 active, 153 MW of 3 filed
- Eagle Point: 2 active, 72.9 MW of 5 filed
- Mickelton: 1 active, 44 MW of 2 filed
- Gloucester: 3 active, 7.1 MW of 8 filed
- Monroe: 1 active, 4.9 MW of 2 filed
- Beaverbrook: 2 active, 2.3 MW of 3 filed
- Deptford: 1 active, 1.9 MW of 6 filed
- Runnemede: 2 active, 1.3 MW of 2 filed
- Romeoville: 2 active, 0.8 MW of 2 filed
- Williamstown: 1 active, 0.6 MW of 6 filed
- Minotola: none active of 5 filed
- Thorofare: 1 active, 0 MW of 4 filed
- Clayton-Williamstown: none active of 3 filed
- Beckett: none active of 2 filed
- Harrison Township: none active of 2 filed
- Nortonville: none active of 2 filed
Site Scanner