Substation Scout

Pleasantville substation interconnection queue

1 active project totalling 1.4 MW in the PJM queue, plus 4 with terminal status (shown greyed).

1active projects
1.4active MW
5total filed
Queue IDProjectkVMWResourceStatus
P35 Pleasantville /AC LF Unit 2 n/r 2 Gas Deactivated
R07 AC Landfill Energy Units 1-3 n/r 2 Gas Deactivated
V2-005 Pleasantville 12kV 12 1.9 Gas Withdrawn
L02 Pleasantville / AC LF Unit 1 12 1.4 Gas In Service
AH1-638 Pleasantville 12.47kV 12.5 0.7 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.