Cumberland substation interconnection queue
4 active projects totalling 388.9 MW in the PJM queue, plus 6 with terminal status (shown greyed).
4active projects
388.9active MW
10total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| C01-2119 | Cumberland 230 kV | 230 | 280 | Battery | Active |
| AB2-102 | Cumberland | 230 | 225 | Gas | Withdrawn |
| AG2-308 | Cumberland 138 kV | 138 | 100 | Battery | Withdrawn |
| AF1-081 | Cumberland 230 kV | 230 | 96 | Solar | Withdrawn |
| P06 | Cumberland 2 | 230 | 88.1 | Gas | In Service |
| AF2-022 | Cumberland 138 kV | 138 | 50 | Battery | Withdrawn |
| AE2-205 | Cumberland 230 kV | 230 | 46.8 | Solar | Withdrawn |
| AG2-297 | Cumberland 230 kV | 230 | 11.4 | Solar | Active |
| T54 | Cumberland Unit 1 | 138 | 9.4 | Gas | In Service |
| AG2-071 | Cumberland 12 kV | 12 | 1.8 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.