Eagle Point substation interconnection queue
2 active projects totalling 72.9 MW in the PJM queue, plus 3 with terminal status (shown greyed).
2active projects
72.9active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| A16 | Eagle Point 230 kV | 230 | 800 | Gas | Withdrawn |
| Y2-105 | Eagle Point | 230 | 50 | Gas | In Service |
| W3-125 | Eagle Point 230kV | 230 | 27.9 | Gas | Withdrawn |
| H26 | Eagle Point 230kV | 230 | 25 | Gas | Withdrawn |
| X1-039 | Eagle Point | 230 | 22.9 | Gas | In Service |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.