Frostburg substation interconnection queue

3 active projects totaling 19.6 MW in the PJM queue, plus 3 with terminal status (shown grayed).

Target commercial operation dates as filed run from Dec 2014 to Dec 2023 (6 filings).

3active projects
19.6active MW
6total filed
Queue IDProjectkVMWResourceStatusTarget COD
AI2-490 Frostburg 138 kV 138 31.9 Wind Withdrawn Dec 2023
AE2-289 Frostburg 138 kV 138 11.8 Wind Active Dec 2021
AE2-030 Frostburg 138kV 138 7.6 Solar Withdrawn Aug 2020
Z2-013 Twin Ridges Wind Farm 138 4.9 Wind In Service Dec 2014
AB2-041 Mason Dixon Wind Farm 138 3.7 Wind Withdrawn Dec 2020
AB2-038 Frostburg 138kV 138 2.9 Wind In Service Dec 2020

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Allegany County, MD

All 23 PJM queue filings in Allegany County, MD.

Other PJM queue substations in Somerset County, PA

All 107 PJM queue filings in Somerset County, PA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first