Substation Scout

Roxbury substation interconnection queue

1 active project totaling 5.1 MW in the PJM queue, plus 2 with terminal status (shown grayed).

Target commercial operation dates as filed run from Jul 2010 to Nov 2028 (3 filings).

1active projects
5.1active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AF2-229 Gobbler Knob 23 10.9 Solar Withdrawn Nov 2028
W1-045 Roxbury Solar Project 23 5.1 Solar In Service Dec 2019
V4-004 Roxbury 12.5kV 12.5 3.8 Solar Withdrawn Jul 2010

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Tracked changes at this substation

2 changes to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.

DetectedQueue IDChangeMWStatus was → now
2026-10-26AF2-229Status changen/a Pending Termination → Withdrawn
2026-09-21AF2-229Terminal status10.9 Engineering and Procurement → Pending Termination

Other PJM queue substations in Cumberland County, PA

All 30 PJM queue filings in Cumberland County, PA.

Other PJM queue substations in Franklin County, PA

All 80 PJM queue filings in Franklin County, PA.

Other PJM queue substations in Morris County, NJ

All 22 PJM queue filings in Morris County, NJ.