Substation Scout

Allen substation interconnection queue

3 active projects totalling 122 MW in the PJM queue, plus 7 with terminal status (shown greyed).

3active projects
122active MW
10total filed
Queue IDProjectkVMWResourceStatus
AG1-365 Flatrock Creek Solar II 345 60 Solar Engineering and Procurement
AG2-400 Allen 345 kV 345 60 Solar Withdrawn
AF2-224 Flatrock Creek Solar I 345 42 Solar Engineering and Procurement
AI2-116 Allen 345kV 345 24 Solar Withdrawn
AG1-366 Flatrock Creek Storage I 345 20 Battery Engineering and Procurement
AG2-402 Allen 345 kV 345 20 Battery Withdrawn
AG2-408 Allen 345 kV 345 18 Solar Withdrawn
AG2-024 Allen 13.2 kV 13.2 2.1 Solar Withdrawn
AH1-022 Allen 13.2 kV 13.2 2 Solar Withdrawn
AF2-101 PA Cumberland Diehl 13.2 1.8 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.