1 active project totaling 55.1 MW in the PJM queue, plus 2 with terminal status (shown grayed).

Target commercial operation dates as filed run from Jan 2005 to Sep 2026 (3 filings).

1active projects
55.1active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
AF2-360 Keeney-Steele 230 kV 230 75 Solar Withdrawn Dec 2023
AB2-037 Cherrywood Solar I 230 55.1 Solar Partially in Service - Under Construction Sep 2026
G00_MTX2B Keeney-Steele 230kV 230 0 Not reported Withdrawn Jan 2005

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Allegany County, MD

All 23 PJM queue filings in Allegany County, MD.

Other PJM queue substations in Caroline County, MD

All 18 PJM queue filings in Caroline County, MD.