Keeney-Steele substation interconnection queue
1 active project totaling 55.1 MW in the PJM queue, plus 2 with terminal status (shown grayed).
Target commercial operation dates as filed run from Jan 2005 to Sep 2026 (3 filings).
1active projects
55.1active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AF2-360 | Keeney-Steele 230 kV | 230 | 75 | Solar | Withdrawn | Dec 2023 |
| AB2-037 | Cherrywood Solar I | 230 | 55.1 | Solar | Partially in Service - Under Construction | Sep 2026 |
| G00_MTX2B | Keeney-Steele 230kV | 230 | 0 | Not reported | Withdrawn | Jan 2005 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Allegany County, MD
- Cumberland: 2 active, 97.5 MW of 10 filed
- Frostburg: 3 active, 19.6 MW of 6 filed
- Dans Mountain: 1 active, 14 MW of 3 filed
- Bedington-Harmony Jct: none active of 2 filed
- New Hope: none active of 2 filed
- Sandy Springs-High Ridge: none active of 2 filed
Other PJM queue substations in Caroline County, MD
- Steele: none active of 2 filed