Allegany, MD interconnection queue

6 active projects totalling 190.6 MW in the PJM queue, plus 17 with terminal status (shown greyed).

6active projects
190.6active MW
23total filed
Queue IDProjectkVMWResourceStatus
C01-1874 Ridgeley - Frostburg 138 kV 138 150 Battery Active
AE1-077 Sandy Springs-High Ridge 230 kV 230 100 Not reported Withdrawn
AG2-308 Cumberland 138 kV 138 100 Battery Withdrawn
AF2-360 Keeney-Steele 230 kV 230 75 Solar Withdrawn
AH1-621 Steele-Milford 230kV 230 72 Solar Withdrawn
AG2-615 Carlos Junction-Garrett 138 kV 138 62.6 Solar Withdrawn
AH1-342 Carlos Junction 138 kV II 138 50 Hybrid Withdrawn
AI2-490 Frostburg 138 kV 138 31.9 Wind Withdrawn
AF1-044 Wye Mills-Longwood 69 kV 69 18.9 Solar Withdrawn
AI2-353 Carlos Jct. – Ridgeley 138 kV 138 16 Wind Withdrawn
S14 Dans Mountain n/r 14 Wind In Service
AE2-309 Jade Meadow 34.5 11.9 Solar In Service
AE2-289 Frostburg 138 kV 138 11.8 Wind Active
AD1-018 Pigtoe Bobcat Solar 34 7.6 Solar Withdrawn
Z2-038 Dan's Mountain Solar Project 138 7.6 Solar Withdrawn
AE2-030 Frostburg 138kV 138 7.6 Solar Withdrawn
AB2-038 Frostburg 138kV 138 2.9 Wind In Service
AG2-409 Granite 115 kV 115 0 Not reported Withdrawn
AH2-019 Not reported n/r 0 Solar Withdrawn
AH2-052 New Hope 12.47 kV 12.5 0 Solar Withdrawn
C01-1026 Hancock 12.47 kV 12.5 0 Battery Active
C01-1892 Carlos Jct - Cresaptown 34.5 kV 34.5 0 Gas Withdrawn
V2-007 Bedington-Harmony Jct 138kV 138 0 Not reported Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.