WVPA: substations in PJM planning materials

12 substation names presented in WVPA zone documents.

SubstationDescribed askV as printedProjectsMentionsLast mentioned
AEP-Marathon Existing 69kV 1 2 2024-10-08
AES-Marathon Existing Not printed 1 2 2024-10-08
Berne Not stated 69 kV 1 2 2024-10-08
Burr Oak New 4-69 kV, 69 kV 1 2 2024-10-08
Elderberry Substation Existing 345kV 1 4 2025-10-08
Macedon Not stated Not printed 1 1 2024-10-08
Marathon Existing 69 kV 1 2 2024-10-08
Mt Zion New 69/12kV 1 2 2024-10-08
Portland Not stated 69 kV 1 2 2024-10-08
Salamonia Not stated Not printed 1 1 Not reported
Stillwell substation Not stated Not printed 1 4 2025-10-08
Trinity Existing Not printed 1 2 2024-10-08