Substation Expansion Tracker: Arizona

The substations Arizona's utilities describe as new in the ten-year transmission plans they file with the Corporation Commission, with the words that mark each one.

Why this exists

Most of Arizona is outside any regional transmission organization, so there is no TEAC deck or TPIT workbook to read. What Arizona has instead is a state law, A.R.S. 40-360.02, that requires anyone planning a line of 115 kV or more to file a ten-year plan with the Arizona Corporation Commission each January. The utilities file theirs in one docket, and each plan names the substations its lines will start, pass through or end at, including stations not built yet.

This section reads the plans of APS, TEP, UNS Electric, SRP and AEPCO and keeps a page for every named substation they describe as new.

36substations described as new
5utility plans read
10new, with a county printed
2026-01-30plans filed

Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.

Generation interconnection requests in the same footprint: APS queue (annual snapshot).

Described as new

Every named substation the plans describe as new or planned, with the words that mark it. 10 have a county printed for them; those come first.

SubstationUtilityCountyIn service (as printed)Described as new
BiancoAPSPinal2028“The future Bianco substation, located east of Bianco Road and between Clayton Road and SR 84 in Casa Grande”
The source calls it proposed — APS 2026-2035 Ten Year Transmission Plan, p.31
Franco WashTEPPima2027“Planned Franco Wash 138-kV Switchyard”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.47
Patriot
see note
TEPPimaPhase 1: 12/11/2023; Phase 2: 07/18/2024“Planned Patriot 138-kV Substation”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.46
PortTEPPima2028“Planned Port 138-kV Substation”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.46
Santa RitaTEPPima2028“Planned Santa Rita 138-kV Substation”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.52
VineTEPPima2027“Planned Vine Substation”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.49
GatewayUNSESanta CruzTBD“the future Gateway substation which will be the site of a DC converter station”
The source calls it proposed — UNS Electric 2026-2035 Ten-Year Transmission Plan, p.39
HarshawUNSESanta Cruz2027“Planned Harshaw Substation”
The source calls it proposed — UNS Electric 2026-2035 Ten-Year Transmission Plan, p.23
Mineral ParkUNSEMohave2031“parallel to SR 93 to the planned Mineral Park Substation.”
The source calls it proposed — UNS Electric 2026-2035 Ten-Year Transmission Plan, p.18
Rio RicoUNSESanta Cruz2027“Planned Rio Rico 138-kV Switchyard”
The source calls it proposed — UNS Electric 2026-2035 Ten-Year Transmission Plan, p.24
Cochise
see note
AEPCONot printedJanuary 2026“Cochise 230 kV Substation : New 230 kV substation to accommodate renewable generation in the vicinity of the AEPCO' s Apache Generating Station. (January 2026)”
The source calls it new — Arizona G&T Cooperatives 2026-2035 Ten Year Plan, p.8
Mohave ValleyAEPCONot printedOctober 2026“Mohave Valley 69 kV Substation (f/k/a Phase 1 of Mohave Energy Center 69 kV Substation): New 69 kV substation to accommodate new generation and interconnection in the Mohave Electric Cooperative, Inc. (MEC) 69 kV transmission area. (October 2026)”
The source calls it new — Arizona G&T Cooperatives 2026-2035 Ten Year Plan, p.8
RedingtonAEPCONot printedJune 2027“a new 1 15 kV switching station called Redington, to be built adjacent to the existing APS San Manuel Substation. (June 2027)”
The source calls it new — Arizona G&T Cooperatives 2026-2035 Ten Year Plan, p.8
Desert SunAPSNot printed2030“The proposed Desert Sun substation will be located east of the Solana Generating Station and west of the Town of Gila Bend.”
The source calls it proposed — APS 2026-2035 Ten Year Transmission Plan, p.45
HazenAPSNot printed2030“the location of the future Hazen 230/69kV substation”
The source calls it proposed — APS 2026-2035 Ten Year Transmission Plan, p.43
IndependenceAPSNot printed2030“A new 230kV line will be extended east from the future Independence substation”
The source calls it proposed — APS 2026-2035 Ten Year Transmission Plan, p.42
Outer CircleAPSNot printed2027“this new 230/69kV source substation will reduce loading constraints”
The source calls it new — APS 2026-2035 Ten Year Transmission Plan, p.28
Parkway
see note
APSNot printedNot printed“the future Parkway substation”
The source calls it proposed — APS 2026-2035 Ten Year Transmission Plan, p.25
Raptor
see note
APSNot printed2026“The future Raptor switchyard will connect into the line along this alignment.”
The source calls it proposed — APS 2026-2035 Ten Year Transmission Plan, p.25
Sabre
see note
APSNot printed2026“The future Sabre switchyard will tie into the line along Olive Avenue near the 147th Avenue alignment.”
The source calls it proposed — APS 2026-2035 Ten Year Transmission Plan, p.25
WaferAPSNot printed2028“The 500kV lines will be brought overhead into the new substation and the 230kV lines will be brought into the substation underground.”
The source calls it new — APS 2026-2035 Ten Year Transmission Plan, p.33
WatermelonAPSNot printed2030“traverse east to the proposed Watermelon substation.”
The source calls it proposed — APS 2026-2035 Ten Year Transmission Plan, p.45
East PlantSRPNot printedTBD“New 230 kV Switchyard near the existing Oak Flat 115 kV Substation, tentatively named "East Plant Switchyard"”
The source calls it new — SRP 2026-2035 Ten Year Plan, p.29
HodgkinSRPNot printed2028 (230 kv); TBD (500 kv)“New Hodgkin 500/230 kV Substation”
The source calls it new — SRP 2026-2035 Ten Year Plan, p.23
Sidewinder
see note
SRPNot printed2023: Switchyard and UG 230 kV Santan - Scott Line Components“New SY-33 230 kV Switchyard (named Sidewinder)”
The source calls it new — SRP 2026-2035 Ten Year Plan, p.27
TailingsSRPNot printedTBD“New 115 kV Switchyard at Customer's Tailings Storage Facility (TSF), tentatively named "Tailings Switchyard"”
The source calls it new — SRP 2026-2035 Ten Year Plan, p.30
West PlantSRPNot printedTBD“New 230 kV Switchyard near the existing Goldfield - Silver King 230 kV line, tentatively named "West Plant Switchyard"”
The source calls it new — SRP 2026-2035 Ten Year Plan, p.29
Copper WorldTEPNot printed2028“Planned Copper World Switchyard”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.53
CoronaTEPNot printed2032“Planned Corona 138-kV Substation”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.63
Craycroft-BarrilTEPNot printed2032“Planned Craycroft-Barril 138-kV Substation (to be constructed”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.64
GrierTEPNot printed2028“Planned Grier 138-kV Substation”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.54
Owl Head RanchTEPNot printed2028“Planned Owl Head Ranch 138-kV Switchyard”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.55
South HoughtonTEPNot printed2027“Planned South Houghton Switchyard”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.50
Tucson EstatesTEPNot printed2029“Planned Tucson Estates 138-kV Substation”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.58
Wilmot ParkTEPNot printed2033“Planned Wilmot Park 138-kV Substation”
The source calls it proposed — TEP 2026-2035 Ten-Year Transmission Plan, p.66
KipperUNSENot printed2026“Planned Kipper 138-kV Substation”
The source calls it proposed — UNS Electric 2026-2035 Ten-Year Transmission Plan, p.22

Expanded at an existing substation

SubstationUtilityExpansionAs described
Lago del OroTEPNew voltage level“Planned Lago del Oro 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.62
NaranjaTEPNew voltage level“Planned Naranja 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.57
OlsenTEPNew voltage level“Future Olsen 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.74

Planned but not named

28 planned stations carry a placeholder or no name in the plans (“TS30”, “New 500 kV Substation”). They are not given pages, because nothing here could say which station a later document means.

As printedUtilityWhy not listed
Apache Generation 230 kV Ring Bus p.8AEPCO"New 230 kV substation to accommodate additional generation at Apache Substation" is new work at the existing Apache substation (grades at-site, not new); expansionBasis() does not grade it either
Marana Substation Rebuild p.8AEPCOrebuild of the existing Marana 115 kV substation to breaker-and-a-half; not new, and expansionBasis() does not grade it
TS10 p.48APSplaceholder name (Q-B default: not listed); Table 5, Sun Valley-TS10-TS11 230kV Line, TBD
TS11 p.48APSplaceholder name; Table 5, TS35-TS11-Sun Valley and Sun Valley-TS10-TS11 230kV Lines, TBD
TS14 p.49APSplaceholder name; Table 5, TS14 230kV Lines, TBD
TS17 p.36APSplaceholder name; intermediate point on Pinnacle Peak to Ocotillo rebuilds (in-service TBD); also Table 5 p.49
TS25 p.29APSplaceholder name, OCR prints TS2S (Table 2 p.11 prints TS25); intermediate point on Helios to Milligan 230kV Line (in-service TBD)
TS30 p.48APSplaceholder name; Delaney to TS30 to TS36 to Quartzsite lines and TS30 500kV Lines (p.49), TBD
TS31 p.30APSplaceholder name, though printed "the new TS31 substation" (in-service 2028, Bagdad 230kV Transmission Line, CEC 238, high-load customer)
TS32 p.49APSplaceholder name; Table 5, TS32 230kV Lines, TBD
TS35 p.48APSplaceholder name; TS35-TS11-Sun Valley 230kV Line and TS35 500kV and 230kV Lines (p.49), TBD
TS36 p.48APSplaceholder name; Delaney to TS30 to TS36 to Quartzsite lines, TBD
TS37 p.49APSplaceholder name; TS37 500kV Lines and TS37 500/69kV Transformer Addition (p.18), TBD
TS39 p.25APSplaceholder name; switchyard on the Contrail 230kV Lines (in-service TBD)
Mead Phoenix Project Q01 p.30APSqueue-number label rather than a station name, and no printed wording grades new (only "(in-service 2028)" and "will tap the Mead-Perkins 500kV line")
Helios p.29APSnamed (formerly TS33, p.14) but no printed wording grades new: "Helios substation (in-service 2027)" is a date and "will be cut into the existing Sundance - Faul 230kV line" grades at-site
Diamond p.26APSnamed, but no printed wording grades new: "(in-service 2026)" and "will be located in Avondale"; the only "new" on the sheet is the double-circuit line
Komatke p.40APSonly "Komatke substation (in-service TBD)"; p.15 says the Komatke 230/69kV Substation project was removed from the Plan, while Table 2 (p.9) keeps a Komatke 230kV series reactor for 2027
Texas Hill p.18APS"Texas Hill 500kV Switchyard and Lines with a TBD in-service year" is listed as a new project in the plan, which grades model-only; no project sheet
New 500 kV switchyard (Coolidge Expansion Project) p.22SRPunnamed: "New 500 kV gen-tie and switchyard at existing Coolidge Generating Station"
New 500/230 kV Substation, Stanfield p.3SRPunnamed (Marigold Energy Center; the August 2026 supplement replaces p.28's "New 500 kV Substation, Stanfield, AZ"; exact location TBD)
New 230 kV Substations, Stanfield (two collector substations) p.3SRPunnamed (Marigold Energy Center; the supplement lists two, near SW/O N Stanfield Rd & W Korsten Rd and SW/O Fuqua Rd & W Highway 84, where p.28 listed one; exact locations TBD)
Diamondback p.27SRPcustomer-owned 230/13.8 kV substation the plan says the customer has constructed; the wording does not describe it as new
Nexus p.27SRPcustomer-owned 230/13.8 kV substation the customer "is currently constructing"; the wording does not grade as new (model-only)
Ball (RS-17) 230 kV Loop-in p.13SRPPotential Project with a TBD in-service date; the plan does not describe a new substation
Pfister (RS-24) 230 kV Loop-in p.13SRPPotential Project with a TBD in-service date; the plan does not describe a new substation
TEPTDA p.61TEPplaceholder name (Q-B default: not listed). Printed "Planned TEPTDA 138-kV Substation", Drexel - Midvale loop-in, in service 2030.
UNSTDB p.27UNSEplaceholder name (Q-B default: not listed). Printed "Planned UNSTDB 138-kV Substation", Santa Cruz Reliability Project Phase 3, in service 2031, approximately 0.5 miles west of the Valencia substation.

What an entry is

An entry is a substation name as the plans print it, one entry for the whole state. The plans are scanned images with a machine-read text layer, and that layer sometimes misspells a name; where it does, the page shows both spellings.

Each of the five utilities lays out its plan differently, so the records are made by hand once a year rather than by a parser. Each record quotes the filing and gives the page. Every time this section is rebuilt, each quote is checked again against the filed document, and a quote that is no longer on its page stops the build. A substation is described as new only where the quote says so: "New Hodgkin 500/230 kV Substation", "the future Independence substation", or a TEP or UNS Electric station listed as "Planned". A plan line that only gives an in-service year is not enough. Where a planned station carries the name of a substation the utility already runs at a lower voltage (TEP's 46 kV Naranja, Olsen and Lago Del Oro), it is listed as an expansion at that station rather than as new, and its page names the existing station and where it is mapped.

Some planned stations carry a placeholder instead of a name ("TS30", "New 500 kV Substation"). Those are listed on this page but get no page of their own.

Counties

No plan prints a county column. A county is shown only where a source prints one for that station: the plan's own text, or the description of a Line Siting Committee case, which often says where a line's endpoints are ("each located within Pima County"). A county is never worked out from a township and range, a town name or a section heading.

What this does not say

The plans are the utilities' own planning documents. An in-service year is the year the plan prints, not a construction schedule. The plans are line-centric, so a substation appears where a line connects to it, and the reason for a project is the utility's own description. Nothing here says what a project will do for a site.

Source

The 2026-2035 ten-year plans of Arizona Public Service, Tucson Electric Power, UNS Electric, Salt River Project and Arizona Electric Power Cooperative, filed January 2026 in Arizona Corporation Commission docket E-99999A-25-0006 (the Fourteenth Biennial Transmission Assessment). The plans are public filings; this site is not affiliated with or reviewed by any of these utilities or the Commission.