02Nevada

Substation Expansion Tracker: Nevada

The substations Nevada's transmission owners describe as new, or as getting a new voltage or a larger yard, in the progress reports they file with the Western Electricity Coordinating Council, with the words that mark each one.

Why this exists

Nevada is not in a regional transmission organization, so there is no TEAC deck or TPIT workbook to read. What every transmission owner in the western United States does file is an Annual Progress Report to the Western Electricity Coordinating Council's Studies Subcommittee, each spring. The report describes the utility's planned transmission projects in a paragraph each, and it names the substations those projects build or change.

This section reads the reports of NV Energy, which serves most of the state, and GridLiance West, which owns the 230 kV system in Valley Electric Association's territory around Pahrump and Beatty. It keeps a page for every named substation they describe as new, and for every existing one described as getting a new voltage level or a larger yard.

14substations described as new
9expansions at existing substations
3progress reports read
2026-03-13latest report dated

Source: WECC Annual Progress Reports filed with the WECC Studies Subcommittee: NV Energy 2026 Annual Progress Report (dated March 4, 2026); NV Energy 2025 Annual Progress Report (dated February 3, 2025); GridLiance West 2026 Annual Progress Report (dated March 13, 2026). Retrieved 2026-11-21; records reviewed by hand 2026-11-21.

Generation interconnection requests in the same footprint: NV Energy queue (annual snapshot).

Described as new

Every named substation or switching station the reports describe as new or proposed, with the words that mark it.

SubstationUtilitykVIn service (as printed)Described as new
Johnnie CornerGridLiance West2305/2028“Build a new Johnnie Corner 230 kV station and loop into the Pahrump - Innovation 230 kV line.”
The source calls it new — GridLiance West 2026 Annual Progress Report, p.3
EsmeraldaNV Energy525May 2027 (Greenlink West, as printed)“construction of the new Sagebrush (f.k.a., Amargosa) 525 kV collector station, Esmeralda 525 kV collector station”
The source calls it new — NV Energy 2026 Annual Progress Report, p.8
HG IIINV Energy230October 2028“HG III is a new 230/12kV substation, energized by the Prospector 230 kV line”
The source calls it new — NV Energy 2026 Annual Progress Report, p.6
LanderNV Energy525/230December 2028 (Greenlink North, as printed)“construction of the new Lander 525/230 kV collector substations along the line”
The source calls it new — NV Energy 2026 Annual Progress Report, p.3
LanternNV Energy345December 2026“The new Lantern 345 kV substation will be a new generation collector substation”
The source calls it new — NV Energy 2026 Annual Progress Report, p.1
Lazy 5NV Energy120January 2029“Lazy 5 120 kV Substation This new 120 kV substation includes the installation of two 120/24 kV 60 MVA transformers”
The source calls it new — NV Energy 2026 Annual Progress Report, p.2
PeavineNV Energy120December 2026“The new Peavine 120 kV substation project relieves load”
The source calls it new — NV Energy 2026 Annual Progress Report, p.4
Redwood
see note
NV Energy1202027 (ultimate load addition, as printed)“This includes new Redwood 120 kV substation”
The source calls it new — NV Energy 2026 Annual Progress Report, p.2
SagebrushNV Energy525May 2027 (Greenlink West, as printed)“construction of the new Sagebrush (f.k.a., Amargosa) 525 kV collector station”
The source calls it new — NV Energy 2026 Annual Progress Report, p.8
Sand DuneNV Energy230June 2030“Sand Dune 230 kV Switching Station This project is being proposed to support the commercial and industrial customers in the Apex area.”
The source calls it proposed — NV Energy 2026 Annual Progress Report, p.9
SapphireNV Energy230January 2028“Sapphire 230/12 kV Substation This project is being proposed to support the fast load growth in the Apex area of North Las Vegas.”
The source calls it proposed — NV Energy 2026 Annual Progress Report, p.7
ShafferNV Energy345September 2029“interconnect a 30MW of load at new NV Energy Point of Interconnection at 345kV 'Shaffer' substation”
The source calls it new — NV Energy 2026 Annual Progress Report, p.3
Spring CanyonNV Energy230March 2030“Spring Canyon 230/12 kV Substation This project is being proposed to support the growing commercial and industrial center in southern Henderson, specifically in the El Dorado Valley.”
The source calls it proposed — NV Energy 2026 Annual Progress Report, p.9
WinstonNV Energy138January 2028“The construction of a new Winston substation will contain new 138 kV power circuit breakers in a ring bus formation”
The source calls it new — NV Energy 2026 Annual Progress Report, p.6

Expanded at an existing substation

A new voltage level or a larger yard at a station that is already there. Highest voltage first.

SubstationUtilityExpansionkVAs described
NorthwestNV EnergyNew or expanded yard525“expansion of the existing Northwest 525 kV substation” — NV Energy 2026 Annual Progress Report, p.8
Robinson SummitNV EnergyNew or expanded yard525“The project also includes an expansion of the existing Robinson Summit 525/230 kV substation” — NV Energy 2026 Annual Progress Report, p.3
Trout CanyonGridLiance WestNew voltage level500“Install a new Trout Canyon 500 kV bus and three 500/230 kV transformers at Trout Canyon.” — GridLiance West 2026 Annual Progress Report, p.2
Walker RiverNV EnergyNew voltage level500“Fort Churchill substation upgrades : New 500 kV, 345 kV and 230 kV switchyards will be built, including new transformers: 2x500/345kV (600MVA), 2x345/230kV (300MVA), and 2x345/120kV (280MVA).” — NV Energy 2026 Annual Progress Report, p.8
Comstock MeadowsNV EnergyNew voltage level345“This project comprises of 345 kV addition at Comstock Meadow substation with addition of two (2) 345/120kV transformers to accommodate rapid load growth in the Reno TRIC area.” — NV Energy 2026 Annual Progress Report, p.3
BeattyGridLiance WestNew voltage level230“Expand existing Beatty, Lathrop, Valley Switch and Vista 138 kV substations to 230 kV” — GridLiance West 2026 Annual Progress Report, p.3
LathropGridLiance WestNew voltage level230“Expand existing Beatty, Lathrop, Valley Switch and Vista 138 kV substations to 230 kV” — GridLiance West 2026 Annual Progress Report, p.3
Valley SwitchGridLiance WestNew voltage level230“Expand existing Beatty, Lathrop, Valley Switch and Vista 138 kV substations to 230 kV” — GridLiance West 2026 Annual Progress Report, p.3
VistaGridLiance WestNew voltage level230“Expand existing Beatty, Lathrop, Valley Switch and Vista 138 kV substations to 230 kV” — GridLiance West 2026 Annual Progress Report, p.3

Read but not listed

Stations the reports name whose wording does not describe them as new or as a new yard or voltage. They get no page.

As printedReportWhy not listed
Sloan Canyon 500/230 kV transformer and 500 kV loop-inGridLiance West 2026 Annual Progress ReportPrinted as a transformer and a line loop-in, not as a new yard or substation; equipment additions are not graded as expansions.
Newton 120 kV switching stationNV Energy 2026 Annual Progress ReportNamed in the TRIC - Newton project, but the wording does not describe it as new ("comprised of the Newton 120 kV switching station").
Project Quasar 138 kV switching stationNV Energy 2026 Annual Progress ReportA 75 MW customer served from Pecos by a new Pecos - Quasar 138 kV line; the wording does not describe a Quasar substation as new.
Buckeye 120 kV substation rebuild (Stockyard in the 2025 report)NV Energy 2026 Annual Progress ReportA rebuild of an existing station in a new bus configuration, not a new substation or a new voltage.
Audette 230 kV switchyard (Switch Phase 1&2)NV Energy 2025 Annual Progress ReportIn the 2025 report only, in service May 2025 as printed, and not listed in 2026. Its wording (“the construction of a 230kV switchyard”) names a project and does not grade as new.

What an entry is

An entry is a substation name as the reports print it, one entry for the whole state. The reports are written as prose, so the records are made by hand once a year rather than by a parser. Each record quotes the report and gives the page. Every time this section is rebuilt, each quote is checked again against the archived report, and a quote that is no longer on its page stops the build.

A substation is described as new only where the quote says so ("The new Lantern 345 kV substation", "HG III is a new 230/12kV substation") or calls the station proposed ("Sapphire 230/12 kV Substation. This project is being proposed"). An expansion needs the quote to describe a new voltage level or a larger yard at a station that is already there, and where the new voltage is not obvious from the quote, the page cites where the same report shows the station at another voltage. A new transformer, phase shifter or breaker on its own is not counted. Stations the reports name without describing them as new are listed on the section page under "Read but not listed", with the reason.

Counties

The progress reports print no county for a substation. They sometimes name a town or an area ("the Apex area of North Las Vegas", "Spanish Springs", "near Ely"), and a county is never worked out from those. Until a source that prints a county for a station is found, such as a Public Utilities Commission of Nevada permit application under the Utility Environmental Protection Act, the county is left blank, and these stations do not yet appear in the Site Scanner report's list of planned substations by county.

What this does not say

The reports are the utilities' own planning documents. An in-service date is the one the report prints, not a construction schedule, and several have moved from one year's report to the next. WECC asks mainly for transmission over 200 kV and generation of 200 MW or more, so a smaller substation may be planned without appearing here. The reason given for a project is the utility's own description. Nothing here says what a project will do for a site.

Source

The 2026 Annual Progress Reports of NV Energy (dated March 4, 2026) and GridLiance West (dated March 13, 2026), and NV Energy's 2025 report for comparison, as posted by WECC. The reports are public; this site is not affiliated with or reviewed by WECC or either utility.

Before relying on any of this