Substation Expansion Tracker: MISO
The substations MISO's transmission owners describe as new, or as getting a larger yard, in the projects of the 2025 MISO Transmission Expansion Plan, with the project name that marks each one.
Why this exists
Every December the Midcontinent Independent System Operator's Board approves that year's Transmission Expansion Plan. Its Appendix A is the list of projects the transmission owners are cleared to build; the MTEP25 report names load growth as the largest driver of the 2025 plan. The plan is published as a PDF report that prints, for each transmission owner, a table of its Appendix A projects with a name, a category, an in-service date and an estimated cost.
This section reads those tables. It keeps a page for every project whose name describes a new named substation, switching station or breaker station ("New Vulcan 138/34 kV Substation", "Fort Mountain 161 kV: Build New Substation"), and for every one whose name describes a larger yard at a station that is already there ("Expand Wheeler Creek 138 kV Station").
Source: MTEP25 Report (2025 MISO Transmission Expansion Plan), approved by the MISO Board of Directors December 11, 2025; 428 of its 432 Appendix A projects are printed by name. Retrieved 2026-11-21; stations reviewed by hand 2026-11-21.
Generation interconnection requests in the same footprint: MISO queue (annual snapshot).
Described as new
Every MTEP25 project whose printed name describes a new named substation, switching station or breaker station, by MISO planning region. The state is the one printed in the transmission owner’s name; owners that serve several states give none.
| Substation | Owner | State | kV | In service (as printed) | Cost | Project, as printed |
|---|---|---|---|---|---|---|
| Moonshine Solar Bootleg Central | Ameren Illinois | IL | 138 | 12/1/2025 | $8.0M | “New Moonshine Solar Bootleg 138 kV switching station (J1382)” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 25018, p.57 |
| Wakefield Central | Ameren Illinois | IL | 138 | 12/1/2027 | $10.7M | “New Wakefield 138 kV switching station” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50299, p.57 |
| Brownsburg East Central | Indianapolis Power & Light Company | IN | 138 | 12/31/2025 | $8.6M | “New Brownsburg East 138 kV Substation” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50502, p.79 |
| Pond Creek Central | Indianapolis Power & Light Company | IN | 345/138 | In the map image only | — | “New Pond Creek 345 : 138 kV Substation” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50722, p.78 |
| Ralston Central | Indianapolis Power & Light Company | IN | 138 | 3/1/2031 | $24.0M | “New Ralston 138 kV Substation Eagle Valley Reinforcement” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50315, p.79 |
| Blanchette Central | Ameren Missouri | MO | 138 | 6/1/2029 | $7.0M | “New Blanchette 138 kV Ring Bus” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 25496, p.58 |
| Central Central | Ameren Missouri | MO | 138 | 12/1/2028 | $1.0M | “New Central 138 kV Substation Load Addition” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50615, p.59 |
| Lumberjack Central | Ameren Missouri | MO | 345 | 12/1/2027 | $38.5M | “New 345 kV Lumberjack substation for Load Connection” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50617, p.59 |
| Rootbeer Central | Ameren Missouri | MO | 345 | 12/1/2026 | $2.0M | “New Rootbeer 345 kV Substation Load Addition” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50616, p.59 |
| Tibbe Central | Ameren Missouri | MO | 138/34.5 | 12/1/2029 | $33.0M | “New Tibbe 138/34.5 kV Substation” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50256, p.59 |
| Vulcan Central | Ameren Missouri | MO | 138/34 | 6/1/2030 | $12.0M | “New Vulcan 138/34 kV Substation” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50226, p.58 |
| Edinburg Central | Prairie Power, Inc. | Not printed | 69 | 12/1/2030 | $3.4M | “New Edinburg 69 kV Breaker Station” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50413, p.82 |
| Ellettsville Central | Hoosier Energy REC, Inc. | Not printed | 345 | 1/1/2035 | $20.0M | “New Ellettsville 345 kV Station” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50491, p.68 |
| Henton Central | Prairie Power, Inc. | Not printed | 69 | 12/1/2029 | $3.4M | “New Henton 69 kV Breaker Station” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50414, p.82 |
| Marble Hill Central | Hoosier Energy REC, Inc. | Not printed | 345 | 10/1/2027 | $20.5M | “New Marble Hill 345 kV Station and Load” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50614, p.68 |
| Merom Central | Hoosier Energy REC, Inc. | Not printed | 345 | 7/1/2026 | $12.8M | “New Merom 345 kV Substation Load Addition” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50599, p.68 |
| Richland Central | Duke Energy Corporation | Not printed | 69 | 10/18/2030 | $11.7M | “New WVPA Richland 69 kV ring bus” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50345, p.66 |
| Scotland Central | Hoosier Energy REC, Inc. | Not printed | 345/69 | 12/1/2029 | $38.0M | “New Scotland 345/69 kV Substation” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50698, p.68 |
| Shadow Lake Central | Duke Energy Corporation | Not printed | 138/12 | 6/1/2026 | $3.0M | “New HE Shadow Lake 138/12 kV Sub” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50285, p.66 |
| Wabash Industrial Central | Duke Energy Corporation | Not printed | 69/12 | 10/16/2026 | $3.0M | “New Wabash Industrial 69/12 kV Sub” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50289, p.66 |
| Fort Mountain South | Entergy Arkansas LLC | AR | 161 | 3/31/2026 | $5.7M | “Fort Mountain 161 kV: Build New Substation” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50581, p.114 |
| Admiral South | Entergy Louisiana LLC | LA | 138 | 9/1/2025 | $54.4M | “Admiral 138 kV New Substation and Transmission Line” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50196, p.123 |
| Bluepoint South | Entergy Louisiana LLC | LA | 230 | 8/1/2027 | $59.6M | “Bluepoint 230 kV New Substation and line Cut-ins” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50546, p.123 |
| Green Acres South | Entergy Mississippi LLC | MS | 500/230 | 12/1/2029 | $312.0M | “Green Acres 500/230 kV New Substation” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50602, p.127 |
| Rhodair South | Entergy Texas, Inc. | TX | 230 | 8/26/2025 | $85.0M | “Rhodair 230 kV New Substation and Transmission Lines” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50199, p.137 |
| South China South | Entergy Texas, Inc. | TX | 138 | 5/12/2025 | $5.8M | “South China 138 kV New Substation” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50209, p.137 |
| War Eagle South | Entergy Texas, Inc. | TX | 138 | In the map image only | — | “War Eagle 138 kV: Construct New Substation and Lines” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50360, p.136 |
| Avon Area West | Xcel Energy | Not printed | — | 12/31/2027 | $10.0M | “Install Avon Area Substation” The source describes building it — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50458, p.178 |
| Beloit Area West | American Transmission Company | Not printed | — | 6/30/2027 | $9.0M | “Beloit Area DIC, New Substation” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50145, p.148 |
| Central SS West | American Transmission Company | Not printed | — | 4/1/2026 | $3.2M | “Central SS, DIC, New Substation” The source calls it new — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50613, p.149 |
| East Mankato Area West | Xcel Energy | Not printed | — | 12/31/2027 | $6.7M | “Install East Mankato Area Substation” The source describes building it — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50435, p.178 |
| Pine Island West | Xcel Energy | Not printed | — | 12/30/2026 | $8.9M | “Install Pine Island Island Area Substation” The source describes building it — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50433, p.178 |
Expanded at an existing substation
A project whose printed name describes a larger yard or a new voltage level at a station that is already there. Highest voltage first.
| Substation | Owner | Expansion | kV | As printed |
|---|---|---|---|---|
| Remsen Township | MidAmerican Energy Company | New or expanded yard | 345 | “Remsen Township 345 kV Substation Expansion for J1590” — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50254, p.163 |
| Rock Creek | ITC Midwest | New or expanded yard | 345 | “Rock Creek 345 kV Substation Expansion and Rock Creek - Quad Cities #2 345 kV line” — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50213, p.158 |
| Wheeler Creek | Hoosier Energy REC, Inc. | New or expanded yard | 138 | “Expand Wheeler Creek 138 kV Station” — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50492, p.68 |
| Mount Pleasant | American Transmission Company | New or expanded yard | — | “Racine County, DIC, Mount Pleasant Substation Expansion” — MTEP25 Report (2025 MISO Transmission Expansion Plan), project 50166, p.148 |
Read but not listed
Projects whose names mention a new station but do not describe a named one as new. They get no page.
| Project, as printed | Owner | Why not listed |
|---|---|---|
| New BREC Bon Harbor-OMU Sub ‘M’ 69 kV Interconnection (project 50396, p.62) | BREC | A new 69 kV interconnection between two named stations; neither station is described as new. |
| New Pleasant Acres Substation Feed 2 138 kV line (project 50503, p.79) | IPL | “New” is on a 138 kV line feeding the substation, not on the substation. |
| Bryan to Runny 138 kV New Line and Substation (project 50359, p.135) | ETI | The name does not say which station, Bryan or Runny, is the new one. |
| J1529 POI New 69 kV Interconnection Substation and 69 kV Line Taps (project 50192, p.163) | MEC | Named only by a MISO queue position; no station name or place is printed. |
| J1530 POI New 69 kV Interconnection Substation and 69 kV Line Taps (project 50193, p.163) | MEC | Named only by a MISO queue position; no station name or place is printed. |
| J1532 POI New 69 kV Interconnection Substation and 69 kV Line Taps (project 50194, p.163) | MEC | Named only by a MISO queue position; no station name or place is printed. |
What an entry is
An entry is a station name as the project name prints it. The report is read with a fixed parser, not a language model, and each station is a short hand record that names the project and the station. Every time this section is rebuilt, each record is checked against the project row in the archived report, and the project name is graded again: a name that is no longer printed, or no longer reads as new, stops the build. So does any project in the report whose name reads as a new or expanded station that no record covers, so a station cannot drop out without someone deciding it should.
A substation is described as new only where the project name says so. A project named for a station without saying it is new ("Benoit 230 kV Station", "Thunder Substation") is not counted, even where its category is load growth. Projects that name a new station without naming which one ("J1529 POI New 69 kV Interconnection Substation") are listed under "Read but not listed", with the reason. A new transformer, breaker or line terminal at an existing station is not counted as an expansion.
States and counties
The report has no state or county column. Where the transmission owner's own name prints a state ("Ameren Missouri", "Entergy Texas", "Northern Indiana Public Service Company"), the entry carries that state; for owners that serve several states (American Transmission Company, Hoosier Energy, Xcel Energy, ITC Midwest, MidAmerican), it is left blank rather than guessed. A county is shown only where a source prints it for the station. Until one is found, a substation does not appear in the Site Scanner report's list of planned substations by county.
What this does not say
The report is MISO's planning document, and the in-service dates and costs are the ones it prints for each project, as estimated in 2025. The report prints the names of 428 of the 432 projects in Appendix A, so a few are not read here. Approval in Appendix A means a project is cleared to proceed; it is not a construction schedule, and some projects are later cancelled or changed. Nothing here says what a project will do for a site.
Source
The MTEP25 Report, approved by the MISO Board of Directors on December 11, 2025, as posted by MISO. The report is public; this site is not affiliated with or reviewed by MISO or any transmission owner.
Before relying on any of this
- The MTEP report prints no state or county column. A state shown here is the one printed in the transmission owner’s name (“Ameren Missouri”, “Entergy Texas”); for owners that serve several states it is left blank, as is a county no source prints for the station.
- The report prints 428 of the 432 projects in its Appendix A by name; a project it does not print is not read here, and a substation built under a project whose name does not describe a new station is not listed.
- An in-service date and a cost are the ones the report prints (cost in millions of dollars, as estimated), not a construction schedule.
- A few projects are printed only as a heading over a map image (baseline reliability projects such as Pond Creek and War Eagle); their in-service date and cost appear in the image, not the report’s text, and are not shown here.