Substation Scout

Milford substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 4 with terminal status (shown greyed).

0active projects
0active MW
4total filed
Queue IDProjectkVMWResourceStatus
R38 Milford 230kV 230 110 Offshore Wind Withdrawn
W1-082 Milford Solar n/r 7.6 Solar Withdrawn
T153 Milford 34.5kV 34.5 1.1 Hydro Withdrawn
Y3-054 Milford Solar 138 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.