Substation Scout

Buckeye-Ringoes substation interconnection queue

1 active project totalling 3.2 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
3.2active MW
2total filed
Queue IDProjectkVMWResourceStatus
W3-029 Ringoes Solar Farm 34.5 3.2 Solar In Service
AE1-063 Buckeye-Ringoes 34.5 kV 34.5 1.3 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.