2 active projects totaling 2.3 MW in the PJM queue, plus 1 with terminal status (shown grayed).

3 PJM queue filings name Flemington as the point of interconnection, all in Hunterdon County, NJ.

Target commercial operation dates as filed run from Mar 2012 to Jun 2017 (3 filings).

2active projects
2.3active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
W3-150 Flemington 34.5kV 34.5 3.8 Solar Withdrawn Mar 2012
X2-075 Junction Road Solar Farm n/r 2.3 Solar In Service Jun 2017
W2-050 Flemington Solar Farm n/r 0 Solar In Service Apr 2016

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Flemington (JCPL, 1 mention).

Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.

Other PJM queue substations in Hunterdon County, NJ

All 89 PJM queue filings in Hunterdon County, NJ.