Kent-Harrington substation interconnection queue

2 active projects totaling 8 MW in the PJM queue.

2 PJM queue filings name Kent-Harrington as the point of interconnection, all in DE.

Target commercial operation dates as filed run from Dec 2006 to Aug 2007 (2 filings).

2active projects
8active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
N16 Central Landfill Units 1-4 69 4 Gas In Service Dec 2006
T12 Central LF Units 1-4 69 4 Gas In Service Aug 2007

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.