Substation Scout

Lebanon substation interconnection queue

1 active project totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatus
C01-1093 Lebanon 34.5 kV 34.5 22.5 Battery Withdrawn
V4-001 Lebanon Solar 34.5 0 Solar In Service
W4-079 Lebanon n/r 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.