Substation Scout

Lebanon substation interconnection queue

1 active project totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

Target commercial operation dates as filed run from Oct 2011 to Jun 2028 (3 filings).

Transmission owner as filed: Dominion (1 filing).

1active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1093 Lebanon 34.5 kV 34.5 22.5 Battery Withdrawn Jun 2028
V4-001 Lebanon Solar 34.5 0 Solar In Service Dec 2011
W4-079 Lebanon n/r 0 Solar Withdrawn Oct 2011

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in James City, VA

All 8 PJM queue filings in James City, VA.

Other PJM queue substations in Hunterdon County, NJ

All 89 PJM queue filings in Hunterdon County, NJ.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first