Nelson-Indian River substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 3 with terminal status (shown grayed).
3 PJM queue filings name Nelson-Indian River as the point of interconnection, all in Sussex County, DE.
Target commercial operation date as filed: Oct 2028 (3 filings).
Transmission owner as filed: DPL (3 filings).
0active projects
0active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AH1-586 | Nelson-Indian River 138kV | 138 | 45 | Battery | Withdrawn | Oct 2028 |
| AH1-584 | Nelson-Indian River 138kV | 138 | 30 | Solar | Withdrawn | Oct 2028 |
| AH1-585 | Nelson-Indian River 138kV | 138 | 30 | Solar | Withdrawn | Oct 2028 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Sussex County, DE
- Nelson: 7 active, 1,057.4 MW of 14 filed
- Indian River I: 2 active, 66.3 MW of 4 filed
- Milton: 1 active, 43.5 MW of 4 filed
- Laurel-Sussex: 2 active, 8 MW of 3 filed
- Indian River: 1 active, 5 MW of 10 filed
- Laurel: none active of 5 filed
- Indian River II: none active of 4 filed
- Milford: none active of 4 filed
- Sussex County: none active of 4 filed
- Millsboro: none active of 3 filed
- Bethany: none active of 2 filed
- Conaway - North Seaford: none active of 2 filed
- Millsboro II: none active of 2 filed