Hunterdon, NJ interconnection queue

26 active projects totalling 863.1 MW in the PJM queue, plus 63 with terminal status (shown greyed).

26active projects
863.1active MW
89total filed
Queue IDProjectkVMWResourceStatus
AB1-154 Gilbert 230kV 230 1,028 Gas Withdrawn
AD2-171 Branchburg-Alburtis 500kV 500 700 Gas Withdrawn
C01-1875 East Flemington 230 kV 230 500 Battery Active
C01-1911 Pleasant Valley 230 kV 230 300 Battery Active
AI1-187 Glen Gardner 230 kV 230 280 Battery Withdrawn
A46 Gilbert 115 kV 115 100 Gas Withdrawn
AF1-105 Holly Glen 34.5 20 Battery Withdrawn
AF1-108 East Flemington 34.5 kV 34.5 20 Hybrid Withdrawn
AG1-487 Gilbert Solar and BESS 230 20 Hybrid Withdrawn
AF1-196 Gilbert Station 4x1 Combined Cycle (Unit 4, Unit 5, Unit 6, Unit 7, and Unit 8) 230 14.5 Gas In Service
X1-088 Flemington Solar Farm n/r 9 Solar Withdrawn
AG1-495 Ridge Road Solar Farm 34.5 8.3 Solar Engineering and Procurement
W1-082 Milford Solar n/r 7.6 Solar Withdrawn
W4-100 Exxon-NewYork Life 34.5kV 34.5 7.6 Solar Withdrawn
W2-083 Perotti Solar Farm 34.5 6.5 Solar Withdrawn
W3-149 Route 519 Solar Farm 34.5 6.4 Solar Withdrawn
W3-084 Clinton-Round Valley 34.5kV 34.5 6.3 Solar Withdrawn
W2-016 Barbertown-Point Breeze Solar Farm 34.5 5.7 Solar In Service
W4-026 Baptistown-Frenchtown 34.5kV 34.5 5.3 Solar Withdrawn
AH2-202 Hunterdon 34.5 kV 34.5 5 Hybrid Withdrawn
AI2-210 Ringoes-US Bronze 34kV 34 4.6 Solar Withdrawn
W3-081 Baptistown-Frenchtown 34.5kV 34.5 4.2 Solar Withdrawn
AD2-026 Quakertown Solar Farm 34.5 4.1 Solar In Service
AE1-156 Quakertown Solar Farm 34.5 4.1 Solar In Service
AB2-001 Flemington Solar Farm 34 3.8 Solar In Service
W1-076 Keller Solar Farm n/r 3.8 Solar Withdrawn
W2-064 Ringoes Solar Farm 34.5 3.8 Solar Withdrawn
W2-085 Gombasi Solar Farm 34.5 3.8 Solar Withdrawn
W2-086 Baptistown-East Flemington 34.5kV 34.5 3.8 Solar Withdrawn
W3-107 Garboski I Solar Farm 34.5 3.8 Solar Withdrawn
W3-147 Baptistown-Frenchtown #2 34.5kV 34.5 3.8 Solar Withdrawn
W3-150 Flemington 34.5kV 34.5 3.8 Solar Withdrawn
X1-069 Frenchtown n/r 3.8 Solar Withdrawn
X1-079 Baptistown-Frenchtown #2 34kV 34 3.8 Solar Withdrawn
AF2-139 Holland Solar Farm 34.5 3.7 Solar In Service
X1-004 Asbury n/r 3.6 Solar Withdrawn
AF2-192 Barbertown Solar 34.5 3.4 Solar Withdrawn
AD2-006 Gilbert-Morris Park 34.5 kV 34.5 3.2 Solar Withdrawn
AD2-037 Gilbert-Morris Park 34.5 kV 34.5 3.2 Solar Withdrawn
AD2-070 Milford Solar Farm 34.5 3.2 Solar In Service
W3-029 Ringoes Solar Farm 34.5 3.2 Solar In Service
V3-070 Lilac Site 34.5 3 Solar In Service
X1-101 Clinton-Round Valley 34.5kV 34.5 3 Solar Withdrawn
X4-043 Allerton Road Solar Farm n/r 3 Solar Withdrawn
AG1-496 East Flemington 34.5 kV 34.5 2.8 Solar Withdrawn
W4-093 Dotoli Solar Farm 34.5 2.6 Solar Withdrawn
W3-148 Baptistown 12kV 12 2.3 Solar Withdrawn
X2-075 Junction Road Solar Farm n/r 2.3 Solar In Service
AG2-460 East Flemington-Lebanon 34.5 kV II 34.5 2 Battery Withdrawn
AI2-208 Hawks 12.5 kV 12.5 1.6 Solar Withdrawn
X2-036 Whitehouse n/r 1.5 Solar Withdrawn
AE1-063 Buckeye-Ringoes 34.5 kV 34.5 1.3 Solar Withdrawn
AE2-096 East Flemington-Frenchtown Solar 34.5 kV 34.5 1.2 Solar Withdrawn
V4-069 Frenchtown 1 Solar 34.5 1.1 Solar In Service
V4-070 Frenchtown 2 Solar 12.5 1.1 Solar In Service
T153 Milford 34.5kV 34.5 1.1 Hydro Withdrawn
W2-061 Everitt Solar Farm 12 1.1 Solar In Service
W4-097 Wetteland Solar Farm 12.5 1.1 Solar In Service
AF1-195 Gilbert Station Unit 9 230 1 Gas In Service
X1-104 Baptistown-Frenchtown 34.5kV 34.5 0.9 Solar Withdrawn
W2-076 West Amwell Mason Supply Solar Farm n/r 0.8 Solar Withdrawn
W2-080 Fisher Solar Farm 12 0.8 Solar In Service
Y1-072 Lebanon Solar 12 0.8 Solar In Service
W3-108 Garboski I Solar Farm 34.5 0.4 Solar Withdrawn
AF1-257 Hawks 2 12 kV 12 0.2 Solar In Service
AB1-010 Quakertown n/r 0 Battery Withdrawn
AB2-048 Clinton Energy Storage System 12 0 Battery Withdrawn
AB2-094 Warren Glen Switch Point 34kV 34 0 Battery Withdrawn
AB2-127 Gilbert 34.5kV 34.5 0 Battery Withdrawn
AD2-209 Cherryville 12.5 kV 12.5 0 Battery Withdrawn
AD2-213 Justin Court Energy Storage 34.5 0 Battery In Service
AE2-197 Not reported n/r 0 Solar Withdrawn
AE2-201 Not reported n/r 0 Solar Withdrawn
AE2-202 Not reported n/r 0 Solar Withdrawn
AG2-536 Buckeye - Ringoes 34.5 kV 34.5 0 Battery Withdrawn
AG2-537 Ringoes-Copper Hill Solar 34.5 kV 34.5 0 Battery Withdrawn
S16 Gilbert-Glen Gardner 230kV 230 0 Not reported Withdrawn
V3-071 Frenchtown SP 12.5 0 Solar Withdrawn
V4-001 Lebanon Solar 34.5 0 Solar In Service
W1-132 Paunch Solar n/r 0 Solar In Service
W2-050 Flemington Solar Farm n/r 0 Solar In Service
W3-003 Quakertown Solar Farm #1 34.5 0 Solar In Service
W4-031 Pattenburg Quarry Solar Farm 12.5 0 Solar Withdrawn
W4-032 West Portal 4.8kV n/r 0 Solar Withdrawn
W4-053 Green Power West Amwell Solar Farm n/r 0 Solar Withdrawn
W4-079 Lebanon n/r 0 Solar Withdrawn
X2-054 Quakertown Solar Farm #2 n/r 0 Solar Withdrawn
X2-078 Ringoes n/r 0 Solar Withdrawn
Z2-093 Hawks 12kV 12 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.