Hawks substation interconnection queue

1 active project totalling 1.1 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
1.1active MW
3total filed
Queue IDProjectkVMWResourceStatus
AI2-208 Hawks 12.5 kV 12.5 1.6 Solar Withdrawn
W4-097 Wetteland Solar Farm 12.5 1.1 Solar In Service
Z2-093 Hawks 12kV 12 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.