Franklin #2 substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name Franklin #2 as the point of interconnection, all in NJ.
Target commercial operation dates as filed run from Dec 2012 to Jun 2015 (2 filings).
0active projects
0active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| X1-088 | Flemington Solar Farm | n/r | 9 | Solar | Withdrawn | Dec 2012 |
| X3-011 | Beidelman Solar Farm | n/r | 1.9 | Solar | Withdrawn | Jun 2015 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Other PJM queue substations in Hunterdon County, NJ
- Clinton: 3 active, 949.4 MW of 5 filed
- Pleasant Valley: 3 active, 800 MW of 5 filed
- East Flemington: 1 active, 500 MW of 3 filed
- Frenchtown: 3 active, 7.9 MW of 6 filed
- Ringoes-US Bronze: 1 active, 3.8 MW of 2 filed
- Gilbert-Morris Park: 1 active, 3.2 MW of 4 filed
- Buckeye-Ringoes: 1 active, 3.2 MW of 2 filed
- Flemington: 2 active, 2.3 MW of 3 filed
- Ringoes: 1 active, 1.1 MW of 4 filed
- Hawks: 1 active, 1.1 MW of 3 filed
- Glen Gardner: 1 active, 0.8 MW of 3 filed
- Franklin: none active of 7 filed
- Gilbert: none active of 5 filed
- Baptistown-Frenchtown: none active of 4 filed
- Milford: none active of 4 filed
- Lebanon: 1 active, 0 MW of 3 filed
- Baptistown-Frenchtown #2: none active of 2 filed
- Clinton-Round Valley: none active of 2 filed
- Frenchtown-Rosemont: none active of 2 filed
- Rocktown 4.8kV: none active of 2 filed
Other PJM queue substations in Warren County, NJ
- Pequest River: 3 active, 165.9 MW of 5 filed
- Pohatcong: 1 active, 80 MW of 2 filed
- Washington: 3 active, 53.3 MW of 3 filed
- Kittatinny: 1 active, 20 MW of 3 filed
- Phillipsburg: 2 active, 4.1 MW of 8 filed
- Washington-Mobile Chemical: 1 active, 3.8 MW of 2 filed
- Stewartsville: 1 active, 3.6 MW of 2 filed
- Broadway-Stewartsville: 2 active, 3.3 MW of 2 filed
- Gilbert-Morris Park: 1 active, 3.2 MW of 4 filed
- Foul Rift: 1 active, 0.8 MW of 2 filed
- Columbia: 1 active, 0.5 MW of 4 filed
- Belvidere: 1 active, 0 MW of 5 filed
- Mansfield: none active of 4 filed
- Morris Park: none active of 4 filed
- Andover-Kittatinny: none active of 3 filed
- Broadway: none active of 3 filed
- Newburgh: none active of 3 filed
- Flanders: none active of 2 filed
- Hackettstown: none active of 2 filed
- Lopatcong: none active of 2 filed
All 113 PJM queue filings in Warren County, NJ, including 4 more substations.