Indian River substation interconnection queue

2 active projects totalling 1,455.2 MW in the PJM queue, plus 8 with terminal status (shown greyed).

2active projects
1,455.2active MW
10total filed
Queue IDProjectkVMWResourceStatus
C01-1130 Indian River 230 kV 230 1,450.2 Gas Active
G29 Indian River 138kV 138 750 Gas Withdrawn
Q42 Indian River n/r 630 Coal Withdrawn
AH1-384 Indian River 230kV 230 380.7 Offshore Wind Withdrawn
AH1-277 Indian River 230kV 230 279 Offshore Wind Withdrawn
AG2-271 Indian River 230 kV 230 150 Battery Withdrawn
AH2-077 Indian River 230 kV 230 150 Battery Withdrawn
C01-1365 Indian River 230 kV 230 95.5 Wind Withdrawn
R72 Indian River Units 3-4 230 18 Coal Deactivated
R73 Indian River Units #3 & #4 138 5 Coal In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.