South Houghton
In the Tucson Electric Power ten-year transmission plan filed with the Arizona Corporation Commission.
Described as new. The quoted wording calls this substation proposed or future. “Planned South Houghton Switchyard” — TEP 2026-2035 Ten-Year Transmission Plan, p.50
Also mentioned: “To loop-in planned South Houghton switchyard into the TEP” — TEP 2026-2035 Ten-Year Transmission Plan, p.50 · “Planned South Houghton 138-kV Switchyard” — TEP 2026-2035 Ten-Year Transmission Plan, p.65
No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.
Location
Pima County, AZ
County of the road it is named for. No source prints a location. The county is that of the road the substation is named for, which lies in one county and fits the lines the plan connects to it. No point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. Not in OSM or HIFLD by name; no CEC (the plan says no certificate is necessary) and no TEP project page found. The plan places it on the Vail - East Loop line about 3.5 miles from Vail Substation (Sec. 4 T16S R15E), but the endpoint distance alone does not fix a point.
County: South Houghton Road lies in Pima County. The plan's Vail - East Loop 138 kV line, which South Houghton loops in about 3.5 miles from Vail Substation, runs to Irvington and Houghton Roads and then north along Houghton Road; Houghton Road lies wholly in Pima County.
Sources: Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.50 · Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.51 · Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.65 · OpenStreetMap: name search for Houghton roads and substations (OSM base 2026-11-21). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
The project in the plan
| Project | Where in the plan | Line siting case |
|---|---|---|
| Planned South Houghton 138-kV Switchyard Loop-In Project | p.50 | Not printed |
Generation interconnection requests filed in Pima, AZ: APS queue, 2 active of 2. Same county, not the same substation.
Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.
Before relying on any of this
- No Arizona ten-year plan prints a county for a substation. A county shown here is printed for that station in the plan or in a Line Siting Committee docket; otherwise it is left blank.
- The plans are scanned images with an OCR text layer. Quotes are copied from that layer; where it misspells a name, the page says so.
- An in-service date is the year the plan prints, not a construction schedule.