Corona
In the Tucson Electric Power ten-year transmission plan filed with the Arizona Corporation Commission.
Described as new. The quoted wording calls this substation proposed or future. “Planned Corona 138-kV Substation” — TEP 2026-2035 Ten-Year Transmission Plan, p.63
Also mentioned: “Required to connect the planned Corona 138/13.8-kV” — TEP 2026-2035 Ten-Year Transmission Plan, p.63
No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.
Location
Pima County, AZ
County of the road it is named for. No source prints a location. The county is that of the road the substation is named for, which lies in one county and fits the lines the plan connects to it. No point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. No CEC ("Is Certificate Necessary: TBD") and no TEP project page; not in OSM or HIFLD by name.
County: Corona Road lies in Pima County. The plan drops the Irvington - Sonoran 138 kV line #1 about 1 mile into Corona; Corona Road (south Tucson, near Tucson International Airport) lies between Irvington and Sonoran substations. The only other Corona-named roads nearby are short local streets; none lies outside Pima County.
Sources: Tucson Electric Power, Ten Year Plan 2026-2035, Transmission Projects (filed with the Arizona Corporation Commission, image E000049050) (plan years 2026-2035), p.63 · OpenStreetMap: Corona Road and Irvington / Sonoran area (OSM base 2026-11-21). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
The project in the plan
| Project | Where in the plan | Line siting case |
|---|---|---|
| Interconnection of Irvington - Sonoran 138-kV Transmission Line #1 into Planned Corona 138-kV Substation | p.63 | Not printed |
Generation interconnection requests filed in Pima, AZ: APS queue, 2 active of 2. Same county, not the same substation.
Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.
Before relying on any of this
- No Arizona ten-year plan prints a county for a substation. A county shown here is printed for that station in the plan or in a Line Siting Committee docket; otherwise it is left blank.
- The plans are scanned images with an OCR text layer. Quotes are copied from that layer; where it misspells a name, the page says so.
- An in-service date is the year the plan prints, not a construction schedule.