Sabre
In the Arizona Public Service ten-year transmission plan filed with the Arizona Corporation Commission.
Described as new. The quoted wording calls this substation proposed or future. “The future Sabre switchyard will tie into the line along Olive Avenue near the 147th Avenue alignment.” — APS 2026-2035 Ten Year Transmission Plan, p.25
Note. Reported in service. APS's CEC 198 compliance filing (ACC image E000055854, 2026-11-18) says "Construction was completed in December 2025, and the project was put into service in March 2026." The plan still calls it future.
Also mentioned: “Decision No. 79601 amended the CEC authorizing the addition of the Sabre switchyard to serve a large-load customer.” — APS 2026-2035 Ten Year Transmission Plan, p.25 · “Sabre 230kV Shunt Capacitor Additions (2 units)” — APS 2026-2035 Ten Year Transmission Plan, p.9
Note. The plan says the switchyard was added (Decision No. 79601, 11/15/2024) "to serve a large-load customer".
No county is printed for this substation in the plan or in a Line Siting Committee docket found for it.
Location
33.5649, -112.3820 · Maricopa County, AZ · view on a map
Read off a planning map. Read off a planning map by matching it to roads and other mapped features. Accurate to about ±150 m, as estimated by the research. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: Symbol anchored: the drawn "Proposed Switchyard Site" footprint (light-blue hatched square, ~180 x 140 m) on APS's Exhibit C "Project Site Map, CEC 198 Amendment for Sabre 230kV Switchyard" (aerial, north to the left, 1,000 ft scale bar). Affine fit on OSM anchors: W Olive Avenue centreline (33.5660), N Reems Road (-112.3936), and the OSM "Aligned Data Centers" outline (way 1293777436), whose south edge (33.5622) and east edge (-112.3804) match the map's dashed "Data Center Area"; fitted scale 1.11-1.15 m/px on both axes, consistent with each other. Point is the centre of the switchyard footprint, south of Olive Avenue at the east end of the data center site. ±150 m (anchor fit and reading).
Note: Tracker finding: already built. APS's CEC 198 compliance filing (2026-11-18): Sabre "Construction was completed in December 2025, and the project was put into service in March 2026." The plan (filed 2026-01-30) still calls it "The future Sabre switchyard" (in-service 2026). Not yet in OSM.
County: the Census county at this point.
Sources: APS 2026-2035 Ten Year Transmission Plan (Arizona Public Service Company), ACC Docket E-99999A-25-0006 (A.R.S. 40-360.02 ten-year plans) (filed 2026-01-30), p.25 · APS Application to Amend Decision No. 78543 (CEC 198), Sabre Switchyard, Docket L-00000D-22-0030-00198, with Exhibit C site map and Exhibit D (Chaulk declaration) (filed 2024-06-06), Exhibit C · APS CEC 198 annual compliance filing, Decision No. 78543 (filed 2026-11-18), p.2 · OpenStreetMap: W Olive Avenue, N Reems Road, Aligned Data Centers outline (OSM base 2026-11-21). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
The project in the plan
| Project | Where in the plan | Line siting case |
|---|---|---|
| Contrail 230kV Lines | p.25 | CEC 198 |
Generation interconnection requests filed in Maricopa, AZ: APS queue, 82 active of 259. Same county, not the same substation.
Source: the utilities’ ten-year transmission plans filed with the Arizona Corporation Commission under A.R.S. 40-360.02, docket E-99999A-25-0006: APS 2026-2035 Ten Year Transmission Plan (filed January 30, 2026); TEP 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); UNS Electric 2026-2035 Ten-Year Transmission Plan (filed January 30, 2026); SRP 2026-2035 Ten Year Plan (filed January 29, 2026); SRP supplement to the 2026-2035 Ten Year Plan (filed August 13, 2026); Arizona G&T Cooperatives 2026-2035 Ten Year Plan (filed January 30, 2026). Retrieved 2026-11-20; records reviewed by hand 2026-11-20.
Before relying on any of this
- No Arizona ten-year plan prints a county for a substation. A county shown here is printed for that station in the plan or in a Line Siting Committee docket; otherwise it is left blank.
- The plans are scanned images with an OCR text layer. Quotes are copied from that layer; where it misspells a name, the page says so.
- An in-service date is the year the plan prints, not a construction schedule.